1 / 23

MICE Target Report

MICE Target Report. Chris Booth (for target team) Sheffield 24 th March 2010. History & Overview T1 – DLC bearings – running in ISIS >155k + 50 k actuations T2 – nominally identical to T1 Bearing failed rapidly T2.2 – like T1, improved QA Failed after ~80k actuations

Télécharger la présentation

MICE Target Report

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. MICE Target Report Chris Booth (for target team) Sheffield 24th March 2010

  2. History & Overview T1 – DLC bearings – running in ISIS >155k + 50 k actuations T2 – nominally identical to T1 Bearing failed rapidly T2.2 – like T1, improved QA Failed after ~80k actuations T2.3 – same stator & shaft as T2.2 New Vespel (polyimide) bearings Tested for >2.1M pulses in R78 Results of T1 running, T2.3 tests, and plans Chris Booth University of Sheffield 2

  3. BCD (beam centre distance) Histograms(analysis by Paul Hodgson) T1 T2 distribution 3-4 times as broad Can be interpreted as a result of the target “sticking” Use the BCD histograms as a diagnostic to spot changes in target performance T2 Chris Booth University of Sheffield 3

  4. T1 Calibration Plots • Running in ISIS allowed subject to • “target integrity tests” every 10k (formerly 5k) actuations • 400 pulses taken under standard conditions • Check for changes in behaviour • Inspections for dust every 50k actuations 0.4 mm

  5. Overlay of Calibration Plots

  6. Conclusions for Target 1 Target continues to perform reliably No sign of significant change in BCD distributions No sign of dust production on view port Keep running! Chris Booth University of Sheffield 6

  7. Status of Target 2 • T2 Vespel installed in R78 Jan 25th 2010 • DLC coated shaft (from T2.2) – Vespel bearings • Same stator body as previous T2 • Pulsed target continuously for 2.15×106 pulses • Approx. one month of operation at ~1 Hz • Two short interruptions, chiller failed 1/2/2010, UPS failed 8/2/2010(!) • Neither problem associated with target mechanical performance • Target was deliberately stopped for inspection • Very little dust on view-port (~ daily photos) Chris Booth University of Sheffield 7

  8. T2 BCD over month Early Mid Late Change over ~1 day 1×106 pulses Start up period DAQ gain changes 720k s 1680k s

  9. Look at BCD histograms in 3 regions Region 1 Early operation 120k – 360k pulses RMS 0.135 Asymmetric tail Region 2 Mid operation 720k – 960k pulses RMS 0.122 Asymmetric tail Region 3 late operation 1860k – 2100k pulses RMS 0.155 More symmetric with double peak structure but broader Chris Booth University of Sheffield 9

  10. Comparison of BCD plots for T1 (DLC) and T2 Vespel T1 T2 Region 3 RMS of T2 Vespel is approximately twice that of T1 (Note different scales) Chris Booth University of Sheffield 10

  11. T2 Acceleration over month Chiller failure UPS failure Test power off Chris Booth University of Sheffield 11

  12. T2 Acceleration regions Late Mid Early Steady decline 848 to 838 ms-2 Increased variability Stable operation (838 ± 5) ms-2 720k s 1680k s Chris Booth University of Sheffield 12

  13. Questions and Comments How would the target have performed if we had carried on pulsing ? Remember we arbitrarily stopped at 2.15 × 106 pulses. Does the early period correspond to the target “bedding in” ? The mid period lasted approx. 1 million pulses where the target seemed to wear gradually. There was a reasonably rapid (1 day) change in performance after which the target parameters were (slightly) more variable. None of the variation seen above would compromise the normal target operation. The typical beam centre varies more than the target BCD. Chris Booth University of Sheffield 13

  14. Disassembly & Inspection of Target 2(Jason Tarrant) • Target stopped after 2.16M actuations • Optics block removed & upper bearing exposed • Bellows removed & lower bearing exposed • Significant amounts of vespel dust, adhered to surfaces Chris Booth University of Sheffield 14

  15. MICE Target First look • Disassembly – View of upper Bearing Little dust (polished flat) Most dust (rough flat) Dust On shaft, On bearing, On lock ring Rough flat Survey point Polished flat Amalgamated dust balls

  16. MICE Target External face • Disassembly – View of lower Bearing Dust around bearing, lock ring removed Chris Booth University of Sheffield 16 Internal face

  17. MICE Target • Observation – Dust • Amount • Most at upper bearing – esp. anti-rotate rough flat side • (Only one flat on shaft polished) • Amalgamated at bearings – scraped off • Location • Coated internal components, has escaped externally • How does it move / defy gravity? • Thrown off? • Electrostatic attraction? • Vibration movement? • When let up to air? • Attachment • Fixed – by what? Chris Booth University of Sheffield 17

  18. Next Steps? • Reduce wear & dust production • Polished flats, burnished bearing faces • Possibly harder plastic (Duratron or Celazole) • Improved stator? (See below) • Observe when dust produced • Trap dust in catcher • Further tests start in May Chris Booth University of Sheffield 18

  19. Stator QA • Is stator 2 different from stator 1? • Map field, with assistance of group at Diamond • Support rig built by Geoff Barber • Chiller, PSU, temperature interlocksready • Measurements to start this week • Stator 3 (unwelded) built in Sheffield • Permanent magnets will be (re-)measured • Modelling (Paul Smith, Owen Taylor?) to connect field asymmetries with off-axis forces Chris Booth University of Sheffield 19

  20. Target Electronics & DAQ Upgrade • Phase 1 hardware complete,tested (Paul Smith) • USB interface to PC • Menu-driven interface in use(see screen shots) • GUI under development (James Leaver) • Control, monitoring, error notification • Much simpler interface (for non-experts!) • Plan to exercise thoroughly in R78 before installation in ISIS • Soak-test during next bearing evaluation Chris Booth University of Sheffield 20

  21. Menu-driven controls Framework for terminal code programmed by James Leaver P J Smith - University of Sheffield

  22. Prototype GUI for Target Control GUI screenshot provided by James. The exact layout may change a bit over the next weeks P J Smith - University of Sheffield

  23. Summary Target 1 installed and operating well in ISIS Target 2 with plastic bearings performed reliably for >2M actuations Stopped for inspection, not due to failure Test & measurement programme for reducing and trapping dust Stators will be mapped to improve QA FPGA-based control essentially ready will give easier operation and enhanced monitoring Chris Booth University of Sheffield 23

More Related