1 / 17

Mountain States Transmission Intertie (MSTI) Open Season Update Meeting

Mountain States Transmission Intertie (MSTI) Open Season Update Meeting. Thursday, June 21, 2007 8:30 am to 12:00 pm General Office Auditorium Butte, MT. Agenda. Welcome and Meeting Purpose Discuss MSTI Announcement MSTI Brochure / Fact Sheet

aleron
Télécharger la présentation

Mountain States Transmission Intertie (MSTI) Open Season Update Meeting

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Mountain States Transmission Intertie(MSTI)Open Season Update Meeting Thursday, June 21, 2007 8:30 am to 12:00 pm General Office Auditorium Butte, MT

  2. Agenda • Welcome and Meeting Purpose • Discuss MSTI Announcement • MSTI Brochure / Fact Sheet • Discuss Idaho Power / PacifiCorp Projects / Fact Sheet • Engineering and Preliminary Siting Update • WECC Planning Process • MSTI Project Costs • NWE System Upgrades / Mitigation • Indicative Pricing • Next Steps • Additional Transmission Requests Received • NWE Consultant Developing Other Pricing Mechanisms • Schedule Next Meeting • Provide Framework for Moving Forward

  3. Mountain States Transmission Intertie (MSTI) • Background • Purpose, Benefit , and Need • Project Detail • Project Timeline • Siting, Permitting, and Environmental Review • Public Outreach and Communications • Contacts

  4. MSTI Brochure / Fact Sheet

  5. MSTI Brochure / Fact Sheet

  6. PacifiCorp / Idaho Power Fact Sheet

  7. MSTI Engineering and Preliminary Siting Update • Overview of 2006 Preliminary Engineering and Siting Analysis • 2007 Work Plan • MFSA Process

  8. WECC Planning Process • WECC Regional Planning Initiated May 17 • 17 responses • Discussed at FERC Technical Conference June 13 • Discussed at WECC PCC meeting June 14 • NTTG Sub-regional coordination July 9 • MSTI • PAC • IP • USE consulting

  9. WECC Planning Process • WECC Regional Planning Initiated May 17 • 17 responses • Discussed at FERC Technical Conference June 13 • Discussed at WECC PCC meeting June 14 • NTTG Sub-regional coordination July 9 • MSTI • PAC • IP • USE consulting

  10. MSTI Project Costs

  11. NWE System Upgrades / Mitigation

  12. Indicative Pricing • Process • Several scenarios were analyzed. The following illustrates three projects based on varying transmission capacity size and construction cost estimates. • Capital construction cost estimates were developed based on Power Engineering consultants in association with NWE personnel. • Pricing is based on a traditional FERC revenue requirement and return on rate base analysis. • Return on rate base plus operating expense, depreciation expense, property and other taxes, and income taxes combine to determine the net revenue requirement. • Each scenario assumes pricing over a 30-year period. The pricing options and ranges for each include a 30-year levelized and 10-year step pricing structure • Pricing ranges are stated in terms of dollars per MWh and dollars per KW month.

  13. Indicative Pricing • Assumptions • Rate base is the total of construction capital, AFUDC (8.9%), mitigation required capital, Idaho sales and use tax (6%) for the portion of the investment assumed in Idaho (50%), working capital, and depreciation reserve. • Each scenario assumes a 13% return on equity based on recent FERC approved returns for new transmission development. The debt rate is assumed at 6.794% with a 50-50 capital structure. Thus, the authorized return on rate base assumed is 9.897%. • O&M costs are assumed at 3.5% of the capital construction cost and escalate 3% per year over the 30-year period. • Depreciation is based on 30-year straight-line for book, and 20-year MACRS for tax purposes. • Property taxes assume 50% MT at 3.132%, and 50% ID at 1.025%. • The plan and pricing could also be considered conservative, as we are reviewing current legislation based on House Bill 3 and other potential impacts and savings regarding property tax rates or other state/federal incentives associated with new generation and related development.

  14. Indicative Pricing • Projects/Scenarios • Project #1: A 390 mile 500 kV line from Townsend, MT to Midpoint, ID with capacity of 1,500 MW. For pricing, a 75% subscription factor (1,125 MW) and a 100% subscription factor (1,500 MW) is illustrated. This project would be the most preferred approach, assuming sufficient demand and system utilization. • Project #2: A 305 mile 345 kV line from Townsend, MT to Borah, ID with capacity of 900 MW. For pricing, a 100% subscription factor (900 MW) is illustrated. • Project #3: A 270 mile 230 kV line from Mill Creek, MT to Borah, ID with capacity of 625 MW. For pricing, a 100% subscription factor (625 MW) is illustrated.

  15. Indicative Pricing • Summary of Results

  16. Next Steps • Additional Transmission Requests • Powerex • Cargill • NWE Engaged CRA International • Tariff Pricing Alternatives • FERC Presentation • Schedule Next Meeting • Develop Plan for Moving Forward

  17. Questions And Discussion

More Related