440 likes | 448 Vues
Tam Valley School Modernization - Phase 1 Summer 2011. Tam Valley Bond Election Project List. Tam Valley Phase 2 - Summer 2012 Project List. Safety and Communication Replace outdated fire alarm system Replace outdated clock, bell and paging system American Disabilities Act compliance
E N D
Tam Valley School Modernization - Phase 1 Summer 2011
Tam Valley Bond Election Project List Tam Valley Phase 2 - Summer 2012 Project List Safety and Communication Replace outdated fire alarm system Replace outdated clock, bell and paging system American Disabilities Act compliance Food service kitchen compliance Building Systems and Renovation Repair or replace aging electrical system components Upgrade inefficient lighting systems including exterior lighting Upgrade computer wiring and infrastructure Repair or replace aging plumbing system components Repair or replace leaking or deteriorating roofs and skylights Paint interior and exterior of buildings Replace flooring Repair or replace windows, doors, hardware and signage Site Improvements Construct solar ready covered outdoor eating area Restore or resurface deteriorating concrete or blacktop Reconfigure parking lot to improve fire access and traffic flow Upgrade aging electrical and plumbing utility systems Safety and Communication American Disabilities Act compliance Building Systems and Renovation Repair or replace signage Site Improvements Construct solar ready covered outdoor eating area Restore or resurface deteriorating concrete or blacktop Reconfigure parking lot to improve fire access and traffic flow Upgrade aging electrical and plumbing utility systems
After Before Windows, paint, roof, doors, lights, gutter, landscape, retaining walls, electrical service, parking lot, playground striping
After Before Windows, paint, roof, doors, lights, gutter, landscape, retaining walls, electrical service, remove one level of sun screen, maintenance path and asphalt
After Before Windows, paint, roof, doors, lights, gutter, landscape, ramp, server room HVAC, water fountain and railings
After Before 1960’s Addition with storefront Windows, paint, roof, doors, lights, gutter, landscape, and landings
After Before Windows, paint, roof, doors, lights, gutter, and remove one level of sun screen
After Before Windows, paint, roof, doors, lights, gutter, remove one level of sun screen, remove storage shed, new landings at doors
After Before Windows, paint, roof, doors, lights, gutter, remove one level of sun screen, ramp, railings, new landings at doors
After Before Windows, paint, lights, asphalt, and ramp surfaces
After Before Windows, paint, roof, doors, lights, gutter, ramp and railings
After Before Windows, paint, roof, doors, lights, and gutter
After Before 1960’s Addition with storefront Windows, paint, roof, doors, lights, gutter, landing at door
After Before Windows, paint, roof, doors, lights, and gutter
After Before Paint, abrasive action floor covering, and non-wax floor covering
Before After Paint, abrasive action floor covering, new double door into MPR
After Before Paint, abrasive action floor covering, and non-wax floor covering
After Before Paint, non-wax floor covering, cubbies protector to assist seeing impaired
After Before Windows, door, paint, abrasive action floor covering, and non-wax floor covering
After Before Paint, abrasive action floor covering, and non-wax floor covering
After Before Windows, paint, doors, motorized blinds, new fire alarm speaker and bell systems
After Before New clock and bell system, wireless access points, and wall mounted short throw projectors
After Before Non operable windows Operable windows, ceiling paint, motorized shades, and touch up paint to cabinets
After Before Wall mounted televisions Removed all wall mounted televisions and replaced with short throw projectors
After Before Replaced all slipper rugs with abrasive actions carpets
After Before Phase 1 - windows, paint, roof, doors, gutter, and landings at doors. Phase 2 in summer 2012 will have a new walkway and ramps
Before After Phase 1 - windows, paint, roof, doors, gutter, and landings at doors, new bell system. Phase 2 in summer 2012 will have a new walkway and ramps
After Before Moved ball walls, slurry seal and restriped blacktop
After Before Paint, roof, doors, lights, gutter, landscape, larger landing under lunch table
After Before Windows, paint, roof, doors, lights, gutter, slurry seal and striping
After Before Paint, lights, ramp surfaces, new fire alarm, clock and speaker systems, slurry seal and restriping blacktop
After Before Paint, lights, water fountain, railing, roofs, gutter, new fire alarm, clock and speaker systems, slurry seal and restriping blacktop
After Before Paint, lights, roofs, remove railing, new landing, gutter, new fire alarm, clock and speaker systems, slurry seal and restriping blacktop
After Before Paint, lights, water fountain, railing, roofs, gutter, new fire alarm, clock and speaker systems, slurry seal and restriping blacktop
After Before Roof, operable skylights, and venting with curb detail
After Before Scuppers Replace all scuppers with gutters, all gutters have screen covers
After Before Patched roofs All new roofs on main building and modular wing
After Before New heater unit and ducts at Admin offices
After Before New roof, new windows, and new conduit for data, fire, bell and electrical upgrades
Before After Phase 1 - Paint, lights, door hardware. Phase 2 summer 2012, landscape changes
After Before Phase 1 - Remove dumpster enclosure, and new sidewalk. Phase 2 - Parking lot renovation
After Before Windows, paint, roof, doors, lights, gutter, landscape, ramp, stairs, and railings
Phase 2 – Summer 2012 Phase 1 – Summer 2011