An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. SCADA Test Bed Project Alaap Anujan, Mike Beacham, Chris Dyer Sponsor: Dr. Brian Johnson

  2. ORIGINAL PROJECT OBJECTIVES Display real time system status and alarms on a user accessible HMI screen Critical alarms to be sent out as text/email messages Maintenance access to connected devices

  3. PROBLEMS WE EXPECTED TO ENCOUNTER • Compatibility issues with older technology • Security concerns with network connectivity • Programming the existing test bed to suit the project requirements

  4. SYSTEM COMPONENTS SEL 2030 RTU Six SEL-734 Meters Synchronizing clock Alarms for motion and temperature SEL 3530 RTAC (Room for future expansion) Computer on Idaho Network (for access)

  5. COMMUNICATION ARCHITECTURE

  6. SEL-2030 RTU Data Concentrator Self contained network switch Capable of passing time synchronization Automation logic platform Can record faults/alarms

  7. PROJECT IMPLEMENTATION Step 1: Assessing the existing SCADA Test Bed Setup Step 2: Tracing and updating the wiring Step 3: Determine NEW system architecture Step 4: Locate proper software tools. Step 5: Project Implementation

  8. PROJECT IMPLEMENTATION (PART II) • Using SEL 5020, update RTU configuration to current status • Update port inputs to attached 724’s • Reprogram RTU to accept changes • Wire alarm outputs to RTU inputs • Incorporate RTAC into system • Connect RTU to RTAC via serial RS232 • Develop HMI tags onto RTAC software • Implement alarm messages into mailer server • Used IEC 61131 structured text format • Used SMTP router to use mailer daemon • Got help from PK Northcutt

  9. THE SCADA TEST BED

  10. The HMI (Human Machine Interface) • Displays the current state of the system and operational alarms on a user friendly interface. • Model Power System metering data • Device & system status • Can be viewed from a remote location. • https://129.101.221.82/default.sel • Configurable for read only for security purposes • Can be modified for future updates.

  11. Opportunities, not problems! XP security updates stopping Test Bed isolated, and also disassembled. No real wiring guide Lacking proper software IT difficulties RTU improperly configured

  12. Questions?