FAR 15: Contracting by Negotiation

FAR 15: Contracting by Negotiation. 15.4 Contract Pricing 15.5 PreAward , Award, and Postaward Notification, Protest and Mistakes 15.6 Unsolicited Proposals. Contract Pricing. Scope

anevay
Télécharger la présentation

FAR 15: Contracting by Negotiation

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. FAR 15: Contracting by Negotiation 15.4 Contract Pricing 15.5 PreAward, Award, and Postaward Notification, Protest and Mistakes 15.6 Unsolicited Proposals

  2. Contract Pricing • Scope • Cost / price negotiations for contracts and subcontracts and contract modifications, including sealed bid awards • Definitions • Price = cost + fee or any profit • Subcontract – includes commercial item transfer between affiliates 15.400-15.401

  3. Contract Pricing (cont.) • Policy • Establish fair and reasonable price (FRP) by requiring submission of certified cost or pricing data (CC/PD), or data other than CC/PD • Require only necessary data • Contract priced separately • Price evaluated without contingencies if contract terms will allow for adjustment 15.402

  4. Prohibition on Obtaining CC/PD • Not obtained for contracts≤ SAT • Exceptions – CC/PD not required when: • CO determines adequate competition • Price based on law or regulation • Commercial item acquired • Waiver granted • Modifying contract or subcontract for commercial items • Other circumstances • Exercise of option at price established at contract award • Overrun funding or interim billing price adjustments 15.403-1, 15.403-2

  5. Requiring Data Other Than CC/PD • Obtain from USG sources to determine FRP; if unavailable, use: • Offeror’s cost data; pricing data on same/similar items • Contract Pricing Reference Guide • Use offeror’s format; ensure data current or updated • Contractor ineligible if data not provided, unless HCA determines otherwise in best interest of USG • Commercial items • Price analysis required • Requests for sales data - limit to relevant time frame 15.403-3

  6. Requiring CC/PD • Required if CO determines no exceptions apply • Threshold: $700,000 • CC/PD obtained before award of contract, subcontract or modification exceeding the threshold • Threshold amount includes both increases and decreases in price adjustments • Exception: HCA may authorize obtaining CC/PD for contracts > SAT < CC/PD Threshold • Required info • CC/PD or other than CC/PD • Certificate of CC/PD 15.403-4

  7. Instructions for Submission • CO specifies in solicitation: • If CC/PD required • If Offeror may request exception • If data other than CC/PD required • If Pre- or post-award access to records required • What data format to use for CC/PD, other than CC/PD, or forward pricing rate agreements 15.403-5

  8. Proposal Analysis Techniques • Purpose: ensure final, agreed-to price is fair and reasonable • Techniques • Price analysis – CC/PD not required (commercial) • Cost analysis – CC/PD required + price analysis for overall price • Cost analysis – data other than CC/PD • Cost realism – when FRP can’t be determined for commercial or non-commercial items; CR contracts • Expert advice as needed; conclusions not divulged to offeror without CO concurrence • Contract Pricing Reference Guides 15.404-1(a)

  9. Price Analysis for Commercial and Non-Commercial items • Evaluate price w/o separate cost elements or profits • If no exception, CO obtains data, without certification, on prices for same or similar items • If FRP can’t be determined, get data other than CC/PD • Compare proposed prices received* • Compare historical prices - valid basis* • Parametric estimates to reveal inconsistencies • Competitive published prices vs independent USG estimates • Proposed prices compared to market research • Analysis of data other than CC/PD • Value analysis – relative worth 15.404-1(b)

  10. Cost Analysis • Performed when CC/PD required • Evaluate separate cost elements & fee • Verify cost or pricing data • Effect of current practices on future costs? • Compare of proposed costs • Verify costs comply with applicable cost principles • Determine whether pertinent data missing and obtain from offeror • When evaluating subcontracts, compare make-or-buy program reviews 15.404-1(c)

  11. Cost Realism Analysis • Independently evaluate whether cost elements realistic, USG requirements understood, elements consistent with methods/materials in proposal • Performed on Cost Reimbursable contracts • CO determines probable cost to add or reduce to adjust offeror’s proposal to realistic levels • May also be used on FPI or FP contracts if scope not understood, quality concerns, or quality/service shortfalls • Offered price may not be adjusted after analysis 15.404-1(d)

  12. Technical Analysis • Determines need for and reasonableness of resources • Performed by specialists at CO request • At minimum, review types and quantity of materials, labor hours, labor mix • Analysis also used for evaluating prices of “similar to” or commercial items “of a type”, or items that require minor modifications 15.404-1(e)

  13. Unit Prices • Reflect intrinsic value proportional to base cost, unless adequate competition • No allocation method distorting costs • Offerors must identify which items they will not manufacture or to which they don’t contribute significant value 15.404-1(f)

  14. Unbalanced Pricing • Line items over/understated as determined by cost or price analysis • Risk indicators • Startup work, mobilization, first articles/testing • Base and option quantities • Price aggregate of est. quantities on separate line items • All proposals with separate line item pricing evaluated • CO considers risk in determining competitive range and source selection, USG price, and whether risk acceptable 15-404.1(g)

  15. Data to Support Proposal Analysis • CO requests field pricing assistance when information available inadequate for FRP • Audit or technical reports, pricing practices, sales history, offeror’s other customary business practices • Pricing information directly to CO; becomes part of contract file • Cognizant audit office assistance – auditor responsible for scope/depth • Deficient proposals – data insufficient or offeror non-cooperative, CO to request data or elevate to next level 15.404-2

  16. Subcontract Pricing Considerations • CO evaluates • Contractor/sub approved purchasing system? • Contractor analyzed sub’s costs and negotiated price before submitting proposal? • Separate analysis of prime and subcontractor’s proposals, including CC/PD • Prime or sub shall • Conduct price or cost analysis to establish reasonableness • Include results in price proposal 15.404-3

  17. Subcontract Pricing Considerations (cont.) • If CC/PD required, Contractor or Sub shall obtain and analyze CC/PD from their respective subcontractors • Required for subcontracts lower of either • ≥$12.5M or • Both >$700K (CC/PD threshold) and >10% of prime contractor’s proposed price • Data must be current and accurate; updated by Prime during negotiations as necessary • If > one contender for specific scope, submit only most likely subcontractor’s CC/PD 15.404-3

  18. Profit • Establishing profit or fee portion of prenegotiation objectives based on cost analysis • Potential total remuneration > allocable costs (not net income) • USG estimate of allowable costs to be incurred • Policy: structured approach ensures relevant factors considered • Noncompetitive awards >$100K totaling $50M/year must use structured approach, unless exemption approved 15.404-4(a) and (b)

  19. Profit (cont.) • CO responsibilities: • If negotiation not based on cost analysis, profit analysis not required • Used structured approach or profit analysis factors for prenegotiation objectives • Contractor acquired equipment/property and facilities cost of capital excluded from analysis • Statutory limits • CPFF experimental or R&D: 15% • A/E services for public works or utilities: 6% • CPFF all others: 10% • (Percentage of estimated costs excluding fee) 15.404-4(c)

  20. Profit (cont.) • Profit-analysis factors • Contractor effort • Contract cost risk • T&M, Labor Hour, FFP, and LOE term treated as CPFF contracts by CO for evaluation purposes • Federal socioeconomic programs • Capital investments • Cost control / past accomplishments • Independent development • Additional factors may be added by agency 15.404(d)

  21. Price Negotiation • Purpose to reach agreement on FRP • If expert recommendations not incorporated, CO must justify in writing • Overall price USG pays is primary concern • Greatest incentive for contractor efficiency • Profit/fee not negotiated without concurrent negotiation of cost and type of contract • If contractor unreasonable, CO refers contract action to level above CO 15.405

  22. Documentation • Prenegotiation Objectives • Results of CO analysis • Established before negotiating price • Cost analysis – issues, objectives, profit/fee • Certificate of Cost or Pricing Data • When CC/PD required, certificate also required and part of contract file • Certificate applies to data, not contractor’s judgment • Concurrence on cutoff dates for data • Submitted with proposal • Updated as necessary prior to final price negotiations • Later exception: certificate not submitted, data not certified 15.406-2

  23. Documenting the Negotiation • Price negotiation memorandum • Purpose, acquisition, parties involved, contractor systems considered • If threshold exceeded, exception for CC/PD • If CC/PD required, how used, whether accurate, whether exception applied • Proposal summary, field pricing recommendations, USG position and any variance in final • Prenegotiation objectives – initial and final • Impact of any congressional or agency direction • Prenegotiation objective profit/fee – initial and final position • Documentation of FRP • Field pricing assistance – CO sends copy of documentation to office providing assistance 15.406-3

  24. Special Cost or Pricing Areas • Defective CC/PD • Before award – notify contractor, corrected, documented • After award – Per contract clauses, USG entitled to price adjustment including profit/fee • Offset for understated data up to amount of USG claim of overstated pricing, if contractor entitled and CC/PD available but not submitted • Disallowed if data known to be understated, price wouldn’t have increased • Overpayment exists only if made for accepted supplies or services • Interest charged for each quarter from time of overpayment to repayment • Penalty for known defective data submission is equal to amount of overpayment • Demand letter issued by CO 15.407-1

  25. Special Cost or Pricing Areas (cont.) • If CO learns of defective data, can request audit • If defective, CO gives contractor opportunity to respond; FAPIIS updated if final determination changed • Right to reduced price whether subcontract a cost estimate or firm agreement • Defective subcontract data adjustment limited to ∆ between price used for prime and actual subcontract or actual cost to contractor, if no subcontract awarded • CR/FP except FFP and FP with economic price adjustment: disallowance or non-recognition of costs 15.407-1

  26. Make-or-buy Programs • Contractor ensures lowest cost and risk to USG • USG may reserve right to review/agree • Acquisitions requiring make-or-buy • CC/PD required and value >$12.5M, except R&D or no follow-on production • Under $12.5M – if CO determines info necessary, reasons documented • Solicitation must include requirement and evaluation factors 15.407-2(a),(b),(c),(d)

  27. Make-or-buy Programs (cont.) • Program requirements in proposal • Items and work included, categorized by ‘make’ or ‘buy’; • Production location, whether near labor surplus area; • Identification of subcontractors, location, size • Whether make-or-buy decision should be deferred • Evaluation, negotiation • Before contract award; no ‘make items’ if otherwise available unless lower cost to USG • Incorporation in contracts for major systems or other supplies/services if cost reimbursable or contractor cost share <25% 15.407-2(e),(f),(g)

  28. Forward Pricing Rate Agreements • Any FPRA must be identified in proposal and latest cost or pricing data updated regularly • Negotiated with CO • If changed condition affects agreement, FPRA revised • Certification of FPRA not required unless used to price agreement requiring CC/PD 15.407-3

  29. Should-cost Review • Form of cost analysis which doesn’t assume historical costs reflect efficiency • Promotes improvements to reduce cost • Program review • Evaluate significant elements of direct costs • Separate audit required • CO determines which operations have greatest cost savings potential • Team report required • Identified in acquisition plan and solicitation • Estimating Systems – cognizant audit agency • Auditor provides corrective action recommendations 15.407-4

  30. Should-cost Review Overhead review • Evaluate and negotiate FPRA • Separate audit report required • Evaluate significant indirect cost elements in depth • Identify, recommend corrective actions for inefficient practices • No separate report required if performed with program should-cost review • Follow-up plan to monitor corrections 15.407-4(c)

  31. Table 15-2 – Instructions for submitting CC/PD • Requirement met when all reasonably available data submitted • Requirement for submission continues until price negotiated or earlier date established • Include index of all certified data and information accompanying proposal, annotate future revisions • Explain estimating process, identify contingencies, include cost element breakdown • Identify preaward costs incurred • Include FPRA, if negotiated • Submit Certificate of Current Cost or Pricing Data 15.408 - Table 15-2

  32. Table 15-2 • Cost Elements • Materials & services • Subcontractor cost analyses, if threshold exceeded; prime responsible for updating subcontractor data • Adequate price competition (subs, purchase orders, materials, etc.) • Direct Labor • Indirect Costs • Other costs • Royalties, if >$1500 • Facilities Capital Cost of Money, if claimed

  33. Preaward, Award, and Postaward Notifications, Protests and Mistakes • Applies to competitive proposals • Notifications to unsuccessfulofferors • Preaward Notices • Notice of exclusion from competitive range; basis for determination, proposal revision not considered • Small business programs: • Notified prior to award, after completion of negotiations, type of small business selected • Identify successful offeror, no subsequent revisions considered; no response required unless SBC status of apparent awardee challenged • Notice not required if urgency necessitates award, or contract is under 8(a) program 15.503(a)

  34. Postaward Notices • 3 days after date of contract award, CO issues written notification to those in competitive range not selected or not previously notified • Notice also made on request for proposals under simplified acquisition procedures • Information in notice: • Number of offers solicited and proposals received • Name and address of award recipients, including offered items/quantity/unit prices • Reason proposal not accepted • No confidential business information revealed 15.503(b)

  35. Award to Successful Offeror • If award includes information different from proposal, both parties sign • If award for less than all possible items, notice states USG may make subsequent awards within proposal acceptance period • If USG forms OF 307, SF 26, or SF 33 not used, USG acceptance statement must be included with CO name, signature, date; likewise, contractor must sign if award contains different information than proposal 15.504

  36. Preaward Debriefing of Offerors • May request debriefing within 3 days of notice if excluded from competitive range • May be delayed until after award, but can affect protest timliness • No more than one debriefing per proposal • CO should debrief in timely manner, but may refuse if in USG’s best interest • Debriefings chaired by CO and include • Evaluation of significant elements, rationale for elimination, reasonable responses to questions • Do not disclose number or identity of other offerors, content, ranking, evaluation or other prohibited information 15.505

  37. Postaward Debriefing of Offerors • Agency should receive request for debriefing within 3d of unsuccessful offeror’s receipt of notice • Debrief occurs within 5 days of receipt of request • If late, not entitled to debrief • Delayed debriefing or untimely request doesn’t automatically extend protest deadline • Debrief format determined by CO • Evaluation of weaknesses, cost or price, technical rating; offerors’ ranking; rationale for award, make/model of items supplied; responses to questions • Excludes specific comparisons, business confidential information 15.506

  38. Protests Against Award, Mistakes • Handled per Part 33 • If protest causes agency within one year of award: • Issue new solicitation • All offerors receive debriefing and other non-proprietary information given to original offerors • Request revised proposals • Copy of debriefing and other non-proprietary information provided to offerors in the competitive range of the original proposal • If mistakes disclosed after award, process at 14.407-4 followed. 15.507

  39. Unsolicited Proposals • Responses encouraged to to BAA, SBIR, STTR, or Program R&D announcements or any government-initiated solicitation or program • Results in contract for R&D • Such proposals must be • Unique and innovative, independently developed • Sufficiently detailed to evaluate agency benefit • Evaluated for energy-savings performance 15.601-15.603

  40. Agency Points of Contact • Agency POC must make following available: • Definition and content for acceptability • Requirements for responsibility (9.1) and organizational COI (9.2) • Preferred methods and procedures for submittal • Names of agency POCs • Information sources • Instructions for marking proprietary info • Only cognizant CO has authority to bind USG 15.604

  41. Content of Unsolicited Proposals • Basic information • Contact information, date, signature, other agencies, proprietary data identification • Technical information • Title and abstract, objectives, key personnel, agency support needed • Supporting information • Price or total estimated costs, period and duration, type of preferred contract, organizational description, agency personnel contacted 15.605

  42. Agency Procedures • Agency must control receipt, evaluation, disposition of proposals • Establish agency points of contact • Receipt and initial review • Is proposal valid, suitable, relevant, sufficient to evaluate merit, properly approved, proper marking requirements • If rejected, agency POC notifies offeror • Evaluation • Methods, merit, contribution, capabilities, key personnel skills, realistic cost 15.606

  43. Criteria for Acceptance and Negotiation - Unsolicited Proposal • Return if • Available elsewhere without restriction, resembles pending competitive acquisition, not relevant to mission or not innovative • Negotiate sole source if • Favorably evaluated, justification approved, agency funds, CO complied with synopsis requirements • USG prohibited from • using proposal as basis for any solicitation w/o permission or from disclosing restrictively marked information 15.607, 15.608

  44. Limited Use of Data • Offerormay restrict use if marked appropriately, otherwise proposal will be returned • Agency POC routes with restriction unless offeror specifically states no restrictions imposed • If unrestricted and evaluation outside USG necessary, proposal data may not be disclosed to others • If restricted, offeror must agree to external review • If not an educational/non-profit institution, written permission required before release for evaluation • Written concurrence from non-USG evaluator not to disclose 15.609