1 / 10

STF General Schedule

STF General Schedule. K.Yokoya EC at KEK, Sep.4.2008. Boundary Conditions. GDE Plan TDP1 ~ July 2010 TDP2 (end of) 2012 What must be done at KEK-STF S1-Global Quantum Beam Project STF2. Module C. Module A. upstream. downstream. S1-Global. Goal Establish 31.5MV/m in average

Télécharger la présentation

STF General Schedule

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. STF General Schedule K.Yokoya EC at KEK, Sep.4.2008

  2. Boundary Conditions • GDE Plan • TDP1 ~ July 2010 • TDP2 (end of) 2012 • What must be done at KEK-STF • S1-Global • Quantum Beam Project • STF2

  3. Module C Module A upstream downstream S1-Global • Goal • Establish 31.5MV/m in average • Demonstrate plug-compatibility • An important item in TDP1(though cannot be completed by July 2010) • Structure • Module C • cryostat from INFN • cavities: 2 from FNAL, 2 from DESY • Module A • cryostat: same as STF1 module A • cavities: 4 from KEK (existing 4 cavities will be replaced)

  4. Would like to form an international team for • design • installation • operation • FNAL/DESY cavities • expect to get them by ~Oct.2009 • in what form? • INFN cryostat : expected about the same time

  5. 量子ビーム(Ryoushi Biimu, Quantum Beam)Project • A new budget framework of MEXT/JST • For beam technology innovation ready for realization • Industries must be involved • 5 year plan. Max. 5 OkuYen per year • We proposed a project “High-Intensity Compact X-ray Source” which includes • RF gun • Laser-Compton scattering • SC acceleration • And were accepted. (Almost guaranteed every year till JFY2012) • 4.5 OkuYen for JFY2008 but this includes • Overhead (23%) • But a good news is that we can employ staffs for 5 years by using this overhead • Planning to add 4 persons for SC (e.g., 2 for cavity, 1 for cryomodule, 1 for cryogenics) • Budget for other fields such as ERL • Budget for participating universities

  6. High-Intensity Compact X-ray Source • Must be demonstrated by JFY2012 • Includes 25 MV SC acceleration and deceleration (but perhaps, deceleration can be omitted) • Beam current (9mA) and pulse length (1ms) same as ILC, but bunch distance factor of ~50 smaller

  7. Better to combine with STF2 for saving manpower and money • Build QB in STF tunnel • Identify 25MV acceleration cavity = STF capture cavity, though QB does not need 2 cavities • Can share the RF gun (but not the laser --- different pulse structure) • But the price is the schedule delay • Interruption for at least half a year, likely ~1 year(installation of QB beamline and tuning for X-ray) • To minimize the delay, plan to finish QB before 2012 summer vacation.

  8. STF2 • ILC 1 RF Unit + injector (RF gun, capture system) • Establish the reliability of the system • Big step to industrialization • Detail under planning. Need one more month.

  9. Infrastructure • Some reinforcement of EP (Nomura  KEK) • Long-module related • clean room • assembly area • pathway to underground • Budget and Manpower • ~40 OkuYen needed • Expect little increase of manpower • Out-sourcing • Schedule • Installation can only start in 2nd half of 2012 (due to Ryoushi Biimu) • Debating whether interim operation (1 module) is needed • feedback to the design : realistic? • Cavity production • First batch : 11 cavities (2 for capture, 9 for module #1) • 2nd batch (17 cav.) : when? (KEK and industry capacity)

More Related