1 / 14

UKNF/MICE Oversight UK plans for this FY......and beyond.....

UKNF/MICE Oversight UK plans for this FY......and beyond. Background & local history Schedule & planning considerations Spectrometer solenoid update Re-defining the UK project Electrical engineering Future plans. Andy Nichols, STFC 30th June, 2010 . ......Circa 2007.

arien
Télécharger la présentation

UKNF/MICE Oversight UK plans for this FY......and beyond.....

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. UKNF/MICE OversightUK plans for this FY......and beyond..... • Background & local history • Schedule & planning considerations • Spectrometer solenoid update • Re-defining the UK project • Electrical engineering • Future plans Andy Nichols, STFC 30th June, 2010

  2. ......Circa 2007 But this is what we’re aiming for...........>> Circa 1963......

  3. ........Installation of MICE Step VI in R5.2

  4. Schedule and planning considerations • Where we are today: • Have been ready for Steps II &III for a few months • Were geared towards Step II start in Mid-May, 2010 • Won’t happen till later in 2011, • What to do........?

  5. Spectrometer solenoid update • Sensitive issue, project is at a critical turning point and at some risk! • Both magnets are partially dismantled at Wang in US • Both are ‘broken’ to some extent • Very difficult, if not impossible, to influence the course of action from outside US • Clear that a change of organisationis required: • Reinforce US labour force • ‘Start again’ with robust and properly policed QA and assembly plan • Cultivate a better environment for information flow • Efforts are being made to induce this approach from the US management • Hard to imagine that the recovery process will take less than eighteen months • Very bad position to be in......BUT • Technical and organisational issues ARE getting clearer

  6. Re-defining the UK project • Steps II & III are delayed for at least eighteen months • UK installation team and infrastructure construction were very carefully geared towards spectrometer solenoid #1 arriving at May 15th and #2 six months later • We musthold the projectteam together, so: • Advance work on the LH2 system • Vent system • Civil engineering • Pipe/valve & gas panel work • Control and safety engineering • RF power work • Design of waveguide/power/cooling infrastructure, placement of amplifiers • Specification and procurement of hardware with US • ‘Hands on’ work at DL with RAL team – second LBNL amplifier • Both RF & LH2 projects contain significant technical risks – better to find out early

  7. LH2 external infrastructure Extensive civil and mechanical engineering, design and installation working with BPG & ISIS All this has to be designed & built outside R5.2.

  8. And it’s a similar story inside...... This is ‘just’ the R&D system, muchdesign, procurement and installation required Also controls and safety work There is also a huge and understandable safety overhead, but good progress already made Must not underestimate the LH2 work content.....!

  9. RF Power • Two RF amplifiers from LBNL are being reconditioned at DL • One is complete, the other is waiting • Plan to deploy some of existing team on second amplifier • Important to do this early while we have time • Led by Daresbury Lab • Very beneficial DL/RAL relationship • RF amplifiers quite big, 4m high and 1 tonne – we have to fit four of them in a very confined space behind shield wall • Ultimately, STFC has to provide and support an RF power station

  10. Need to fit all this........ .....Under here! Not trivial....

  11. Electrical Engineering • Also led by Daresbury Lab: • All detector wiring and cabling • Electrical services in general • Complete implementation of PPS (Personnel Protection System) • Contribution to electrical substation upgrade project • Conventional and S/C magnet power supplies • Cooling Channel controls project • Target power, readout & controls • Liquid hydrogen system controls • Major contribution from BPG: • Power for heating, lighting • Implementation of fire detection • A/C power • Electrical substation upgrade project

  12. Future Plans • Between now and 2014, MICE has to successfully build and install several large and complex subsystems, for example: • Two spectrometers • Three absorber-focus coils • Two RF-coupling coil magnets • And all their services and ancillaries • In a very confined space to a reasonable degree of accuracy • Also have to accommodate several different engineering ‘cultures’ and standards • Have demonstrated that a more rigorous engineering approach pays dividends – eg, the MICE target • Now want to read that across to the other subsystems • Easier said than done.......

  13. Future plans • So we’re changing the emphasis slightly, from infrastructure and surroundings to the subsystems and interfaces • Top level assembly now successfully driven by one (large!) Solid Edge CAD assembly • We MUST reinforce the RAL/DL engineering team • Full time integration engineer is appointed • Am now working on support for him • Monthly MICE Technical Board will be forum for integration issues • Integration activity will be centralised at RAL - important • Discussions just beginning with subsystem owners to encourage information flow • Jason ready to start mid-late July

  14. Future plans • Believe it’s also time to start planning staffing levels etc for future years, given: • External pressures on STFC • Inertia in the ‘system’ • Competition from other projects • Three phases to worry about: • Short-term • Mechanical design effort for integration support, liquid hydrogen, RF implementation and continued support for target project • Medium term • Cryogenic and installation support, theoretical, but also some ‘hands-on’ • Long-term • Resident (at RAL) RF engineer and specialist technical support • Need to start post FY 10/11 project plans and provoke discussion with PED/TEC

More Related