UPDATE ON DWSD’S LONG TERM CSO CONTROL PLAN. Presented to: Board of Water Commissioners May 12, 2010. Topics to be Covered. System Configuration Before CSO Controls (pre-1995) CSO Controls 1995 – 2008: Rouge River National Demonstration Grant Projects
E N D
UPDATE ON DWSD’S LONG TERM CSO CONTROL PLAN Presented to: Board of Water Commissioners May 12, 2010
Topics to be Covered • System Configuration Before CSO Controls (pre-1995) • CSO Controls 1995 – 2008: • Rouge River National Demonstration Grant Projects • Original (1996) Long Term CSO Plan Projects • Recent Developments • Submittal of Long Term CSO Plan Update (October, 2008) • Financial Crisis: Termination of URT($1 B) and DRO-2 ($300 M) • Analysis of less costly CSO Alternatives (2009 – 2010) • Recommended Future CSO Control Projects: • Future Rouge River CSO Control Facilities • Green Infrastructure Program • Future Detroit River CSO Control Facilities
Pre-1995 CSO Discharges in Detroit • 76 permitted outfalls (33 to Rouge River and 43 to Detroit River) • ~ 50 discharge events/year (average); • ~ 20 billion gallons discharged/year; • Major impact on Rouge River water quality: • Dissolved Oxygen depletion • Bacteria exceedances • Sediment deposits and bank erosion • Lesser impacts on Detroit River: • Bacteria exceedances
1989 NPDES Permit:Original CSO Control Requirements • 1989 NPDES Permit initially required ALL Rouge River CSO Outfalls to be treated/disinfected by Retention Treatment Basins by August, 2005; • DWSD contested the permit and then negotiated a settlement requiring: • 3 “Demonstration” Basins: Hubbell-Southfield; Puritan-Fenkell and 7 Mile West (constructed in 1995-1996); • 6 In-System Storage “Task 1” control gates (installed 1996) • Prepare a “Long Term CSO Control Plan” (submitted July, 1996)
1996 Long Term CSO Control Plan Recommended Projects • WWTP Primary Treatment Capacity Increase • Conner Creek CSO Basin • Leib Screening & Disinfection Facility • St. Aubin Screening & Disinfection Facility • Baby Creek Screening & Disinfection Facility • Upper Rouge CSO Tunnel (“URT”) • Additional In-System storage gates • Belle Isle CSO Basin* • Oakwood CSO Basin, P. Station & Sewer Improvements* * Projects added after the Long Term Plan was submitted in 7/96
CSO Project Costs(Construction Start ) • Hubbell-Southfield Basin (1994): $ 58.9 M • Puritan-Fenkell Basin (1995) $ 18.1 M • 7 Mile Basin (1996): $ 14.9 M • Task 1 In System Storage (1996): $ 3.4 M • St. Aubin S&D Facility (1999): $ 19.8 M • Leib S&D Facility (1999): $ 33.4 M • WWTP Expansion (2000): $ 101.2 M • Conner Creek CSO Basin (2001) $ 201.4 M • In-System Storage Devices (2002): $ 30.8M • Baby Creek S&D Facility (2003): $ 76.1 M • Belle Isle CSO Basin (2005): $ 16.1 M • Oakwood Basin & P. Sta. (2007) $ 168.7 M • Oakwood Sewer Improvements (2008) $ 15.0 M $1,593 M
October, 2008 Update to Long Term CSO Control Plan • Assumed completion of URT tunnel by 2015 (construction to begin on 1st tunnel segment in 2008) • Recommended that 41 Detroit River CSO outfalls be controlled with innovative Disposable Net + In-Pipe Disinfection technology • Work to be undertaken over 20 year period: 2010 – 2030 • Estimated construction cost = $ 185 M (2009 $) • MDNRE informally expressed concurrence with the Plan recommendations, but has not responded in writing
Key Facts re: Upper Rouge CSO Tunnel • 30′ diameter tunnel; 7 miles long; 150’ underground • 215 million gallons capacity • Would reduce CSO discharges to < 1/year • Controls 17 Detroit CSOs and 11 suburban CSOs • Includes 100 mgd Pump Station and 14 Drop Shafts • 10 surge control surface structures in Rouge Park • Construction period: 2008 – 2015 • Construction cost = $880 million as of 2/09; expected to escalate to $1 billion after all 8 contracts bid • 83% of costs allocated to Detroit customers
DWSD’s Permit Modification Request due to Economic Hardship MDNRE approval sought to eliminate URT Project and DRO- 2 Outfall based on economic hardship, including: • Population Decline/Loss of Customer Base • Job Losses and Manufacturing Declines • Housing Data: SEV, Taxable Value • Water Sales; Projected Revenues and Rates • Actual CSO Control Project Expenditures >> Estimates • Detroit sewer costs as a % of Median Annual Household Income > EPA’s 2% threshold for “affordability”
NPDES Permit Requirement re: Study of CSO Control Alternatives • DWSD required to analyze alternative CSO Controls • Initial report due: December 15, 2009 • Initial recommendation: Build $484 M smaller CSO tunnel (“URT-2”) with ~ 3.2 untreated overflows/yr • MDNRE requests 90 day Supplemental Study to examine other alternatives to avoid dispute on approvability of URT-2 recommendation • Supplemental Report submitted April 30, 2010
Guiding Principles for CSO Alternative Evaluation Reduce capital cost as much as possible; Utilize an extended implementation schedule to reduce impact on rate payers and allow time for Detroit’s economic recovery; Minimize O&M costs by limiting the number of new CSO facilities; Achieve in-stream water quality comparable to what would have resulted from the URT project; Incorporate “Green Infrastructure” activities to the extent they are feasible, cost effective and beneficial (i.e. reduce or retard runoff); Consider the cost impacts of ongoing projects (Oakwood, Baby Creek remedial measures, TRC Minimization, etc.) as part of the overall CSO program implementation schedule.
Conventional CSO Technologies: Storage Tunnels Retention Treatment Basins Vertical Shafts West Arm Interceptor Extension Screening & Disinfection First Flush Tanks Disposable Nets w/Disinfection Vortex Separators In-System Storage Green Infrastructure Options: Downspout disconnection Re-vegetate vacant lots Bioswales & rain gardens Rain Barrels Green roofs Tree planting/Urban Forest Demolish abandoned structures Porous Pavement Curb bump outs Roadside Tree Trenches Alternatives Evaluated by DWSD
Supplemental Report Recommendations • Replace URT tunnel with a series of innovative, end-of-pipe treatment systems consisting of: • First Flush storage tanks at multiple outfalls • Connecting sewers to eliminate small outfalls • Disposable Net installations to screen out sanitary trash • Disinfection by chemical injection of NaOCl into existing sewers far enough upstream from overflow point to allow contact time for effective bacteria kill • Limit capital expenditures for CSO Projects to < $35 M/yr to stay within Detroit’s Financial Capability • Establish a 25 year schedule for program (including both Rouge River and Detroit River CSO outfalls) • Implement a Green Infrastructure program to reduce stormwater flow tributary to combined system • Demonstrate new CSO control technology with Pilot Projects
Recommended Conventional CSO Control Projects Ongoing Projects ($63 Million): • Oakwood Sewer Improvements (3 remaining segments): $59 M • Baby Creek Remedial Measures (NaOCl feed, mech. mixers, emerg. bypass): $3 M • TRC Minimization & In-Stream Assessments: $1 M New Projects ($791Million): • Hubbell-Southfield Basin Improvements: $3 M • Task 1 In System Gate renovations: $5M • Carbon, Fort St. Outfall eliminations: $1 M • 2 Pilot Projects (First Flush Tank + Disp. Nets w/disinf.) @ 7 Mile East & Pembroke: $41M • Glenhurst outfall diversion and pump station: $3 M • Replace URT Tunnel with First Flush Tank/Disposable Net/In-Pipe Disinfection @ 383 M • RRO-2 shallow conduit in lieu of DRO-2 outfall (2 construction contracts): $130 M • Re-invest in existing CSO Control Facilities: $40 M • Control of Detroit River CSO Outfalls using Disposable Nets/In-Pipe Disinfection @ $185M
Original “URT” 30’ Diameter 7 Miles long 201 MG capacity 17 CSO Outfalls 100 MGD Pump Station Includes Redford, Dearborn Hts flow 1 Overflow/yr (untreated) 850,000 gal/yr discharged (untreated) $880 Million capital cost $1.5 Million annual O & M cost 2008 Construction Start Concurrent Tunnel Contracts 7 Year Construction Period $126 M/yr Avg Cost (over 7 year constr. period) First Flush Tank Alternative 9 First Flush Tanks 13 Outfalls w/Disposable Net Installations 13 Chem. Storage/Pumping Sites > 24 Chemical Injection Points 34.6 MG capacity Includes Redford, Dearborn Hts flow ~ 13 Overflows/yr (treated) 1.2 B gal/yr discharged (treated) $ 426 Million capital cost $2.83 Million annual O & M cost 2012 Construction Start: Pilot Projects Only Sequential Construction Contracts 25 Year Construction Period $20 M/yr Avg Cost (over 25 year constr. period) Comparison of URT and Current Recommendation for Upper Rouge Outfalls
Recommended “Green Infrastructure” Program Rationale for including Green Infrastructure: • Expected to reduce inflow to combined sewers by at least 10% - 20% upon completion; • Provides quick water quality benefit while conventional CSO facilities are designed, sited, financed and built; • Acknowledges the ongoing demographic and population changes that are profoundly affecting the tributary area; • Consistent with the Mayor’s objective to remove abandoned homes and deal with urban blight • Consistent with approach being used in many other urban areas (Philadelphia, Portland, Cincinnati, Washington D.C.)
Proposed “Green Infrastructure” Activities • Disconnect residential downspouts and, where feasible, commercial and industrial downspouts; • Demolish and remove vacant structures, seal pipes and re-vegetate the parcel to return it to pervious cover; • Use bioswales and tree trenches along roadways and parking lots to intercept runoff and reduce stormwater inputs; • Plant trees for uptake and evapotranspiration along roadways and open spaces; • Implement activities on municipally-owned land, focusing on managing stormwater runoff in under-utilized parks
Phasing Of Recommended Projects • Proposed Implementation Schedule: > 25 years (beyond 2034); • Stage Projects in multiple 5-Year Phases; • Spread out new CSO Project construction to average <$35 Million per year as a target “manageable” level of new debt; • Accelerate funding of Green Infrastructure projects early in the implementation plan to achieve immediate beneficial results while conventional facilities are designed and built; Green Infrastructure Budget Recommendation: • $3 Million/Year for first 10 years (2010 – 2019) • $2 Million/Year for next 10 years (2020 – 2029) In addition to these DWSD sewer revenues, also pursue grants, loans, support from foundations and private stakeholders
Recommended Phase I CSO Control Projects(2010 – 2014) PHASE I (2010-2014) :Const. Cost: • Oakwood Sewers Segments 2,3: $44 M • Baby Creek Remedial Measures: $ 2 M • Carbon, Fort St outfall elimination: $ 1 M • TRC Minimization + In-Stream Evaluations: $ 1 M • Hubbell-Southfield Improvements: $ 3 M • Task 1 In-System Gate renovations: $ 5 M • Pembroke outfall First Flush Pilot Project: $24 M • RRO-2 segment 1 (WWTP work): $30 M • Green Infrastructure Program: $15 M PHASE I SUBTOTAL: $125 M
Recommended Phase II CSO Control Projects(2015 – 2019) PHASE II (2015-2019):Const. Cost: • Oakwood Sewers Segment 4: $ 15 M • 7 Mile East Pilot Project: $ 17 M • Glenhurst Pump Station/Diversion: $ 3 M • RRO-2 Segment 2 (outfall conduit): $100 M • Re-investment in existing CSO facilities: $ 10 M • Detroit River CSO Outfalls*: $ 34 M • Green Infrastructure Program: $ 15 M PHASE II TOTAL: $194 M * specific outfalls to be undertaken in Phase II not yet identified
Future Phases (2020 and beyond) • Continue Green Infrastructure Program through 2029 @ $2 M/Yr ($50 M total Green investment); • Continue re-investment in existing CSO Control Facilities; • Undertake new CSO Control Facilities along Rouge River and Detroit River based on re-evaluation of Detroit’s Financial Capability every 5 years (presumably Disposable Nets with In-Pipe Disinfection Systems assuming Pilot Projects demonstrate that the new technology performs as expected)
Factors That Could Affect CSO Schedule • Time period needed by Detroit to achieve economic recovery; • Financial solvency of the City and ability to sell bonds to finance capital improvements; • Demographic changes in the tributary area which affect wet weather flows; • Green Infrastructure progress and stormwater flow reductions actually achieved; • Availability of low interest SRF loan money or grant funding; • Expenditures needed for new regulatory requirements (e.g. de-chlorination); • Need for additional re-investment in existing CSO facilities; • Cost of non-CSO capital improvement projects
2008 Projects: URT (201 MG) $1,000M Oakwood Sewers $ 59M Baby Creek $ 2M Carbon/Fort St elimination $ 1M TRC Minimization $ 1M WWTP outfall (DRO-2) $ 299M Future Detroit River CSOs $ 185M TOTAL$1,547M Average Cost/Yr 2008 - 2015: $169 M/yr Note: 2008 CSO Program did not included a budget for ongoing re-investment in existing CSO facilities. 2010 Projects: 2 Pilot Projects: $ 41 M Glenhurst outfall $ 3 M Remaining Upper Rouge Outfalls $383M Oakwood Sewers $ 59 M Baby Creek $ 2M Carbon/Fort St elimination $ 1M TRC Minimization $ 1M Task 1 Gate renovation: $ 5 M RRO-2 outfall $130M Re-invest in CSO Facilities $ 43M Future Detroit River CSOs $185M SUBTOTAL$ 853 M Green Infrastructure $ 50 M TOTAL $ 903 M Average Cost/Yr 2008 - 2015: $ 21 M/yr Comparison: Then and Now(2008 vs 2010 CSO Program Costs)
Comparison of 2008 and 2010 CSO Control Programs(estimated construction cost/yr)
Next Steps • Meet with MDNRE to negotiate CSO project schedules • MDNRE to modify NPDES Permit with new CSO project schedule • Design Pembroke Pilot Project for First Flush Tank + Disposable Net + In-Pipe Disinfection System • Design new RRO-2 outfall (1st segment @ WWTP) • Develop and implement Green Infrastructure program (with other City Departments) • Complete TRC Minimization Program and evaluate alternative disinfection systems