1 / 54

Steven C. Braun, P.E. Senior Project Manager

Steven C. Braun, P.E. Senior Project Manager. A Master Plan identified a Locally Preferred Alternative (LPA) for the corridor … This LPA was adopted by Broward County and approved by FHWA The “corridor” LPA is advancing through two separate projects: ● ●. Project Limits.

armina
Télécharger la présentation

Steven C. Braun, P.E. Senior Project Manager

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Steven C. Braun, P.E. Senior Project Manager

  2. A Master Plan identified a Locally Preferred Alternative (LPA) for the corridor … This LPA was adopted by Broward County and approved by FHWA The “corridor” LPA is advancing through two separate projects: ● ●

  3. Project Limits To Naples To Port Everglades/Airport Project Limits To Miami

  4. The Planning “Vision” for I-595 Reversible Lanes Transit Facility Ramp Braid

  5. Project Need • Broward County has been one of the fastest growing urban areas in the US • Only east-west expressway in Broward County • Strategic Intermodal Corridor • Existing AADT >180,000 vpd • 2034 AADT >300,000 vpd

  6. Strategic Intermodal Corridor • District 4 SIS – Growth Management Priority • Truly Multi-Modal Corridor • I-75 & Sawgrass Expressway • I-95 & Florida’s Turnpike • Fort Lauderdale-Hollywood International Airport • Port Everglades • Connection to Tri-Rail and Amtrak • Proposed Transit Facility • Broward County Greenway

  7. Key Components • Transit Facility • Highway Improvements • Reversible Lanes • Ramp Braids • Turnpike Interchange • CD (Collector-Distributor) System • SR 84 Continuous Connection • Auxiliary Lanes

  8. PD&E Study • Unique project due to complexity and integration with other projects • Overall project cost >$1 Billion • High profile project with interest by many agencies, municipalities, residential communities and businesses • Priority corridor for roadway and transit improvements

  9. 75 The I-595 System Transit System Sawgrass Mills /Bank Atlantic Center To Downtown Ft. Lauderdale SR 84 SR 7 Florida'sTurnpike Davie Rd. University Dr. Pine Island Rd. Nob Hill Rd. Hiatus Rd. Flamingo Rd. 136th Ave. C-D System Sawgrass Expressway / Interstate 75 To Port / Airport I-595 GP Lanes Reversible Lanes Florida'sTurnpike

  10. PD&E Study Functions & Goals • Maintain Consistency with the LPA • Minimize overall project impacts • Develop a project that can be implemented • Build Consensus • Maintain project schedule • Advance corridor improvements • Phases of project funded

  11. Why Invest in 3D Visualization? • Priority project • High profile complex project • Public Understanding • Design Decisions • Early validation of project alternatives • Public expectations

  12. Why Invest in 3D Visualization? • Obtain (and maintain) buy-in from: • Management • Stakeholders • Agencies • Team members

  13. Development of 3D Visualization • 12-mile Corridor • Focus Areas • Cost & Schedule • Developed one section of the corridor • Different Alternatives • Elevated Reversible Lanes • Transit Location • Ramp Braids • Community Concerns (Location, Noise, Visual) • Turnpike Interchange

  14. Oh, Okay … Elevated Reversible Lanes ! Elevated Reversible Lanes ????

  15. What is a “Braided Ramp” ??

  16. No, seriously … what is a “Braided Ramp” ??

  17. Braided Ramps

  18. Public Hearing

  19. Master Plan’s LPA

  20. PD&E Preferred Alternative

  21. The Results • Improved deliverable from the PD&E process • Better Integration of Transit Improvements • Helped identify the best use of existing right of way for both roadway and transit • Helped create a shared vision • Helped “visualize” the vision

  22. The Results • Gained consensus • Project is being advanced • Better understanding of proposed improvements • Ownership of the PD&E alternative’s geometry = No major re-design • Selection of THE Preferred Alternative • BEAT the original aggressive project schedule!

  23. Future Opportunities? Use the 3D Visualization as a Tool … • 3D Visualization at Key Milestones • Project Website • Future Public Meetings • Agency Coordination • Value Engineering / Design Review • Incorporate Data (GIS, Environment, Traffic, Land Use, Public Comments)

  24. Future Opportunities? Develop a Project that can be Implemented • Constructability Review • Review key decisions • Facilitate a “seamless” transition to Final Design • Develop the phasing of multiple design/construction packages • Build onto the 3D Model • Review & evaluate constructability, compatibility and MOT between adjacent projects

  25. Steven C. Braun, P.E. Senior Project Manager

  26. PROJECT DEVELOPMENT & ENVIRONMENT (PD&E) STUDY • Martin County MPO’s #1 Priority • Engineering & Environmental Analysis • New Bridge Crossing on a New Alignment • Connecting Palm City with the City of Stuart • Alternate Route to SR 714 & the Palm City Bridge • Widen Existing Local Roads • Environmental Impact Statement (EIS) • Cost Estimate: $200 Million

  27. SR 714 CR 714 Palm City Residential Community Proposed Bridge Palm City Bridge Environmentally Sensitive Area Kanner Highway Intersection Indian Street

  28. PUBLIC INVOLVEMENT • Community Assessment Task Team (CATT) • Agency & Stakeholder Workshops • Continuous Public Involvement • Exchange Information  Build Consensus • Community Characteristics Inventory & Database

  29. CATT MEETINGS WITH STAKEHOLER GROUPS • Regulatory Agencies • Community Associations • Local Government • Community Services • Emergency Services

  30. 3D VISUALIZATION • Justification • Public Interest and Expectations • Participation in the process • Understand the alignment alternatives • Martin County MPO’s #1 Priority • 3D Model = Database • Design / Permitting • Construction

  31. 3D VISUALIZATION • Implementation • “In-house” Project  “Hybrid” Project • Consultant Support • District 4 Commitment • Management Support • High Profile Project • Understanding of the Benefits

  32. 3D VISUALIZATION • Development • 4-mile Corridor • Key Areas to Reference (“Landmarks”) • Different Alternatives • Grade Separation • “Phased Development” for the Public

  33. PUBLIC WORKSHOPS Interactive Stations: • Typical Sections • Alignment Alternatives • Evaluation Matrices • 3D Visualization

  34. PUBLIC WORKSHOPS 3D Visualization … Allowed people to have a better understanding of the project, visualize the alternatives & make constructive comments.

  35. Please show me the difference between the alternatives…

  36. ALIGNMENT ALTERNATIVES

  37. Alternative 2A

  38. Alternative 2B

  39. Alternative 2C

  40. What is a “Grade Separation” ??

  41. What will the intersection look like??

  42. What is the bridge going to look like from my patio??

More Related