Welcome to WinPond Workshop Demo #1

Welcome to WinPond Workshop Demo #1. Demonstration Problem #1. Demonstration Problem #1. Mr. Chan L. Cat wants a pond built on his property in Lamar County, TX for livestock water. Location is 0.7 miles SW of Chicota, TX. This will be a low hazard pond.

arvin
Télécharger la présentation

Welcome to WinPond Workshop Demo #1

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Welcome to WinPond Workshop Demo #1

  2. Demonstration Problem #1 CNTSC-WinPond Workshop DEMO1

  3. Demonstration Problem #1 • Mr. Chan L. Cat wants a pond built on his property in Lamar County, TX for livestock water. Location is 0.7 miles SW of Chicota, TX. This will be a low hazard pond. • The Elevation-Surface Area data in acres: 89.9 – 0.0 96.0 – 1.21 97.0 – 1.60 98.0 – 1.90 99.0 – 3.80 100.0 – 3.90 101.0 – 4.0 102.0 – 4.1 CNTSC-WinPond Workshop DEMO1

  4. Demonstration Problem #1 • Now execute WinPond • Click > File > New • This will automatically pull up the default template that you created previously. CNTSC-WinPond Workshop DEMO1

  5. Demonstration Problem #1 CNTSC-WinPond Workshop DEMO1

  6. Demonstration Problem #1 Location-Lamar County, TX-0.7 miles SW of Chicota, TX Principal Spillway Design Storm-5 yr-24 hr=5.55 inches Freeboard Design Storm=25 yr-24 hr=7.8 inches Allowable Velocity=5.0 fps. "NOT STAKED YARDAGE" CNTSC-WinPond Workshop DEMO1

  7. Demonstration Problem #1 Saving your data • Select “File -> Save” or • “File -> Save As” • or press F10 • Save As-DEMO1.prj • Save frequently CNTSC-WinPond Workshop DEMO1

  8. Demonstration Problem #1 CNTSC-WinPond Workshop DEMO1

  9. Demonstration Problem #1 CNTSC-WinPond Workshop DEMO1

  10. Demonstration Problem #1 • The drainage area data: Land Use: Pasture-47.9 Acres HSG-B-28.9 Acres-Fair HSG-C-19.0 Acres-Good Average Watershed Slope-2% Flow Length-1940 Ft. • Auxiliary Spillway Design Storm-25 yr-24 hr-7.8 inches-Type III • Allowable velocity in the Auxiliary Spillway-5.0 FPS • Auxiliary Spillway velocity without a pipe is 5.6 FPS • The Principal Spillway Design Storm will be 5.55 inches for a 5 yr-24 hr storm. CNTSC-WinPond Workshop DEMO1

  11. Demonstration Problem #1 LAMAR COUNTY CNTSC-WinPond Workshop DEMO1

  12. Demonstration Problem #1 POND #1 CNTSC-WinPond Workshop DEMO1

  13. Demonstration Problem #1 LAMAR COUNTY CNTSC-WinPond Workshop DEMO1

  14. Demonstration Problem #1 LAMAR COUNTY CNTSC-WinPond Workshop DEMO1

  15. Demonstration Problem #1 CNTSC-WinPond Workshop DEMO1

  16. Demonstration Problem #1 CNTSC-WinPond Workshop DEMO1

  17. Demonstration Problem #1 CNTSC-WinPond Workshop DEMO1

  18. Demonstration Problem #1 • Sediment storage required will be: Above Inlet (aerated sediment)= 0.03 AF Below Inlet (submerged sediment) = 0.03 AF • The Principal Spillway Crest will be set at Elevation 96.0. • The landowner wants a pipe drop for his pond. Top width is 12.0 ft. Front and back slopes will be 4:1 No berms are needed Pool Bottom elevation is 89.9 Channel and Outlet elevation is 86.0 Tailwater elevation is 87.5 Outlet extension is 6.0 ft. C/L low point elevation is 87.1 Auxiliary Spillway Exit Slope is 7.4% Conduit Invert is 89.0 CNTSC-WinPond Workshop DEMO1

  19. Demonstration Problem #1 Estimated sediment : 0.06 AF 1/2-Above the inlet (aerated)=0.03AF 1/2-Below the inlet (submerged)=0.03AF. CNTSC-WinPond Workshop DEMO1

  20. Demonstration Problem #1 Reduces the amount of storage available when the floodrouting is done. Used to determine the minimum height for the inlet elevation. CNTSC-WinPond Workshop DEMO1

  21. Demonstration Problem #1 LAMAR COUNTY CNTSC-WinPond Workshop DEMO1

  22. Demonstration Problem #1 Do you have adequate water yield for your purpose? For Lamar county the exhibit shows approx. 5 acres of drainage for each AF of storage. For this location we have 47.9 acres and should be able to supply 47.9/5.0=9.6 AF of storage. This location we need our water yield to supply approx. a max of 5.5 AF. So the pond has adequate water yield. Computer models such as RESOP or SPAW can be used for this determination if needed. CNTSC-WinPond Workshop DEMO1

  23. Demonstration Problem #1 CNTSC-WinPond Workshop DEMO1

  24. Demonstration Problem #1 LAMAR COUNTY CNTSC-WinPond Workshop DEMO1

  25. Demonstration Problem #1 We want to be sure we have adequate depth for long time water storage. Based on this location we should have a minimum water depth of 8 ft. over 25% of the area. We are providing 6.1 ft. (96.0-89.9) of natural depth and will pick up additional depth from the borrow area in front of the pond. For this pond the constructed front bottom depth was El. 86.0 for a depth of 10.0 ft. (96.0-86.0). CNTSC-WinPond Workshop DEMO1

  26. Demonstration Problem #1 CNTSC-WinPond Workshop DEMO1

  27. Demonstration Problem #1 CNTSC-WinPond Workshop DEMO1

  28. Demonstration Problem #1 • We will use three pipe trials, all HCMP-Helical Corrugated Metal Pipe • 12”, 18”, & 24” barrel • Use 18”, 30”, & 40” for riser size. • The inlet extension horizontal distance is 5.0 ft • Use an entrance coefficient of 1.0 • A Manning's “n” value of .011, .013, & .015 will be used • Pipe length is computed based on constructed fill and slopes. CNTSC-WinPond Workshop DEMO1

  29. Demonstration Problem #1 CNTSC-WinPond Workshop DEMO1

  30. Demonstration Problem #1 This is for new pipe. You should add 10-20% to design for aged pipe condition. CNTSC-WinPond Workshop DEMO1

  31. Demonstration Problem #1 List of pipe sizes or direct entree. Accept default “n” or direct entree. CNTSC-WinPond Workshop DEMO1

  32. Demonstration Problem #1 CNTSC-WinPond Workshop DEMO1

  33. Demonstration Problem #1 CNTSC-WinPond Workshop DEMO1

  34. Demonstration Problem #1 • We will use the calculated method. • The auxiliary spillway width is 20 ft. with a C retardance. • The level section is 25 Ft. with 4:1 side slope. • The exit channel will be a C retardance. • The permissible velocity is 5.0 FPS • Length 1 is 65 ft-5%; Length 2 is 105 ft.-5% CNTSC-WinPond Workshop DEMO1

  35. Demonstration Problem #1 An auxiliary spillway will not be routed. Discharge will be calculated as in DAMS2 A file containing stage-discharge data will be read. Qe values will be read from the file ASFILE (same format as in DAMS2) CNTSC-WinPond Workshop DEMO1

  36. Demonstration Problem #1 Discharge will be calculated as in DAMS2 CNTSC-WinPond Workshop DEMO1

  37. Demonstration Problem #1 CNTSC-WinPond Workshop DEMO1

  38. Demonstration Problem #1 The top of fill elevation can be changed, but only to a larger value. CNTSC-WinPond Workshop DEMO1

  39. Demonstration Problem #1 “Use New Pipe Length” This will return you to T-7, Principal Routing screen to run through the calculations with the new pipe length. CNTSC-WinPond Workshop DEMO1

  40. Demonstration Problem #1 CNTSC-WinPond Workshop DEMO1

  41. Demonstration Problem #1 CNTSC-WinPond Workshop DEMO1

  42. Demonstration Problem #1 CNTSC-WinPond Workshop DEMO1

  43. Demonstration Problem #1 NOTE: To change H.I. or % ground slope, double click on Elev. Or Dist. Field. NOTE: Negative distance are upstream of centerline. CNTSC-WinPond Workshop DEMO1

  44. Demonstration Problem #1 CNTSC-WinPond Workshop DEMO1

  45. Demonstration Problem #1 CNTSC-WinPond Workshop DEMO1

  46. Demonstration Problem #1 Station----Upstream RR/Distance---CL---Downstream RR/Distance 0+00 8.5 / 6.0 8.5 8.5 / 6.0 0+25 9/0 / 8.0 9.0 9.0 / 8.0 0+75 10.7 / 10.0 10.7 10.7 / 10.0 0+95 12.5 / 21.2 12.5 12.5 / 21.2 1+15 14.2 / 27.6 14.4 14.0 / 27.2 1+35 15.1 / 31.6 15.3 15.0 / 31.2 2+05 18.8 / 46.4 21.6 22.3 / 60.4 2+56 16.7 / 38.0 17.2 17.7 / 42.0 3+13 8.7 / 8.0 8.7 8.7 / 8.0 3+50 6.0 / 6.0 6.0 6.0 / 6.0 CNTSC-WinPond Workshop DEMO1

  47. Demonstration Problem #1 CNTSC-WinPond Workshop DEMO1

  48. Demonstration Problem #1 CNTSC-WinPond Workshop DEMO1

  49. Demonstration Problem #1 CNTSC-WinPond Workshop DEMO1

  50. Demonstration Problem #1 CNTSC-WinPond Workshop DEMO1