1 / 23

Welcome to WinPond Training Exercise #1

Welcome to WinPond Training Exercise #1. Exercise #1.

miya
Télécharger la présentation

Welcome to WinPond Training Exercise #1

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Welcome to WinPond Training Exercise #1

  2. Exercise #1 • Mr. R. B. Trout wants a grade stabilization structure to stop the gully erosion and provide livestock water for field #1 on his property in Washington County, TX. Location is 4.4 miles SE of Independence, TX. This will be a low hazard pond. • The Elevation-Surface Area data in acres: 85.5 – 0.0 89.5 – 0.3 96.4 – 1.20 100.0 – 4.80 104.3 – 10.80 106.0 – 11.80 CNTSC-WinPond Workshop Exercise #1

  3. Exercise #1 • The drainage area data: Total Drainage Area: 103.0 Acres Land Use: Pasture-75.0 Acres HSG-C-50.0 Acres-Good HSG-D-25.0 Acres-Good Woods-28.0 Acres HSG-B-28.0 Acres-Fair Average Watershed Slope-3.2% Flow Length-3000 Ft. • The head cut is 98.0 Elevation. Normal pool should be 1.0 ft above the head cut. CNTSC-WinPond Workshop Exercise #1

  4. Exercise #1 • Auxiliary Spillway Design Storm-25 yr-24 hr-8.95 inches. • Allowable velocity in the Auxiliary Spillway-5.0 FPS • Auxiliary Spillway velocity without a pipe is 5.7 FPS • The Principal Spillway Design Storm will be 7.5 inches for a 10 yr-24 hr storm. CNTSC-WinPond Workshop Exercise #1

  5. Exercise #1 • Inlet Auxiliary Spillway Dimensions: • Length 1=165 ft.-2.5% • Length 2=280 ft.-2.5% • Level section=50 ft. CNTSC-WinPond Workshop Exercise #1

  6. Exercise #1 WASHINGTON COUNTY CNTSC-WinPond Workshop Exercise #1

  7. Exercise #1 GSS #1 CNTSC-WinPond Workshop Exercise #1

  8. Exercise #1 WASHINGTON COUNTY CNTSC-WinPond Workshop Exercise #1

  9. Exercise #1 Washington County, TX CNTSC-WinPond Workshop Exercise #1

  10. Exercise #1 Washington County, TX CNTSC-WinPond Workshop Exercise #1

  11. Exercise #1 WASHINGTON COUNTY CNTSC-WinPond Workshop Exercise #1

  12. Exercise #1 • The landowner wants a pipe drop for his pond. Top width is 12.0 ft. Front and back slopes will be 4:1 No berms are needed Pool Bottom elevation is 85.5 Channel and Outlet elevation is 88.0 Tailwater elevation is 90.0 Outlet extension is 6.0 ft. C/L low point elevation is 89.5 Auxiliary Spillway Exit Slope is 4.5% CNTSC-WinPond Workshop Exercise #1

  13. Exercise #1 Sediment Estimates: Computations or use RUSLE2 Acres Rate RxAC 8 - 5 ton/ac/yr – 40 ton/yr 20 - 2.5 ton/ac/yr - 50 ton/yr 21 - 1 ton/ac/yr - 21 ton/yr 54 - 1 ton/ac/yr - 54 ton/yr Total 103 - - 165 ton/yr - 330,000 lbs/yr @2000 lbs/ton - 3511 ft3/yr @ 94 lbs/ft3 - 130 cy/yr @27 ft3/cy - 0.08 AF/yr @1613 cu/AF - 1.13 AF @ 25 yr @ 56 % 1/2 aerated - 0.565 AF 1/2-submerged - 0.565 AF CNTSC-WinPond Workshop Exercise #1

  14. Exercise #1 Washington County, TX CNTSC-WinPond Workshop Exercise #1

  15. Exercise #1 CNTSC-WinPond Workshop Exercise #1

  16. Exercise #1 Washington County,TX CNTSC-WinPond Workshop Exercise #1

  17. Exercise #1 • You will use three pipe trials, all HCMP-Helical Corrugated Metal Pipe • The inlet extension horizontal distance is 4.0 ft • Use an entrance coefficient of 1.0 • Choose a Manning's “n” value from chart and apply an aging factor of 10%. CNTSC-WinPond Workshop Exercise #1

  18. Exercise #1 CNTSC-WinPond Workshop Exercise #1

  19. Exercise #1 • The auxiliary spillway width is 30 ft. with a C retardance. • The level section is 50 Ft. with 4:1 side slope. • The exit channel will be a C retardance. • The permissible velocity is 5.0 FPS CNTSC-WinPond Workshop Exercise #1

  20. Exercise #1 Station----Upstream RR/Distance---CL---Downstream RR/Distance 0+00 6.6 0+43 8.3 0+73 9.6 1+03 11.8 1+33 13.0 1+63 14.2 1+93 15.7 2+23 16.2 2+53 19.0 2+87 23.1 3+37 18.6 3+67 17.4 3+87 16.8 4+17 15.7 4+57 9.3 4+87 5.6 H.I.=112.6 CNTSC-WinPond Workshop Exercise #1

  21. Exercise #1 • Fill in the blank. • The Auxiliary Spillway Crest is____________Ft. Elevation. • The Principal Spillway Crest is ____________Ft. Elevation • The estimated settled fill is _______________CY. • The barrel diameter is ___________________inches. • The riser diameter is ____________________inches. CNTSC-WinPond Workshop Exercise #1

  22. Exercise #1 CNTSC-WinPond Workshop Exercise #1

  23. Exercise #1 • COST ESTIMATE: • Embankment Fill__________CY x $1.10/CY=____________ • Sodding ____________2000 SY x $0.11/SY=__$220.00____ • Pipe Barrel______Dia(in)_____Ft.x $_____=_____________ • Concrete____________2.0 CY x $200.0/CY=__$400.0______ • Installation__________Ft. of Barrel x $8.00=_____________ • Total Cost=____________ CNTSC-WinPond Workshop Exercise #1

More Related