ERCOT PROGRESS REPORT

DESCRIPTION

ERCOT PROGRESS REPORT. Board of Directors Austin, Texas December 16, 2003. ERCOT Updates. CEO Overview Grid Operations (Sam Jones/Bill Bojorquez) Financial (Maxine Buckles) Texas Nodal Team (Trip Doggett). Current Activities. Interim fee (2004) approved by PUCT

1 / 4

Télécharger la présentation

ERCOT PROGRESS REPORT

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript

Playing audio...

  1. ERCOT PROGRESS REPORT Board of Directors Austin, Texas December 16, 2003

  2. ERCOT Updates • CEO Overview • Grid Operations (Sam Jones/Bill Bojorquez) • Financial (Maxine Buckles) • Texas Nodal Team (Trip Doggett)

  3. Current Activities • Interim fee (2004) approved by PUCT • Draft Operations Audit presented to Finance and Audit Committee • Market design options continue to be explored at TNT • Taylor expansion project nearing kickoff (pending completion of value engineering) • “Level of effort” process under review

  4. Board Retreat • Location: Barton Creek Resort • Dates: January 20th and 21st • Program: • Antitrust Training • Roles of Corporate Directors (NACD) • Transition Planning • Note: Board Meeting will follow (afternoon of 21st)