The Arlington Elementary Renovation, designed by Ross Tarrant Architects and managed by WS Construction, began substantial work towards its completion. The project's cost totals $12,450,800, with a general contractor contract sum of $9,920,194. As of September 2009, significant progress includes completed mock-ups of exterior wall materials, a water detention system installation, and ongoing mechanical, electrical, and plumbing work. The project remains on schedule, with an estimated completion rate of 17% as of September, with demolition nearly finished and foundation work continuing.

avital
Télécharger la présentation

Arlington Elementary Renovation Project Overview and Progress Update

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Arlington Elementary – Renovation • Architect: RossTarrant Architects • General Contractor: WS Construction • Substantial Completion Date: August, 2010 • GC Contract Sum: $9,920,194 • Total Project Cost: $12,450,800 • Change Orders: $36,900 (#1--Demo) • Current Phase: 1 (On Schedule) • Estimated Completion: 17% September 2009

  2. Arlington Elementary – Renovation Rendering of Final Façade September 2009

  3. Arlington Elementary – Renovation Work Completed in Last 30 Days: Mock up of exterior wall materials has been completed. Water detention system is in place. Joists have been set in the gymnasium and the slab is scheduled to be poured on 9/16. CMU walls continue in the kitchen. Current Work Effort (September): Demolition is almost complete. The shoring of the existing structure is in place and reconstruction of the bearing wall between existing and new construction has begun. Mechanical, electrical and plumbing work continues on site and in the existing building. Foundations continue at the main entry and in the media center. September 2009

  4. Arlington Elementary – Renovation Water Detention System New Walls for Kitchen Bearing Wall Between Old & New Construction Mechanical, Electrical Plumbing Work September 2009