An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. MontajTurbinaEoliana 3mw,CU INALTIMEA DE 105m WORK TEAM ROMANIA

  2. Prima sectiune de turn- Din pozitia de transport se ridica in pozitia de montaj FOLOSINDU-SE DOUA MACARALE. ACTIUNEA ESTE SUPRAVEGHEATA DE O PERSOANA AUTORIZATA ISCIR (RSVTI)

  3. A douasectiune de turn- sectiunile de turn se prind cu ajutorulsuruburilor, 178 DE BUCATI CU O GREUTATE DE 18KG FIECARE, GREUTATEA SI NUMARUL LOR SCADE LA FIECARE SEGMENT MONTAT

  4. A treiasectiune de turn

  5. A patrasectiune de turn

  6. A cinceasectiune de turn- Dupaaceastasectiune se monteazanacela

  7. Nacelafara rotor- toateechipamentele de ridicaresuntminutiosverificate DATORITA GREUTATII MARI RIDICATE 70 TONE

  8. Nacela cu rotor - in timpulmontajului / ridicarii

  9. Nacelamontata- greutateatotala A NACELEI + ROTOR este de 96 tONE

  10. Prima Pala- din motive de siguranta a lucratorilor, palele se monteazaunacateuna

  11. Prima Pala- palaesteprinsa de rotor cu 90 de suruburi

  12. A doua Pala- comunicarea se face prinstatie de emisiereceptie

  13. A treiapala- in timpulmontajului nu stanimeni sub sarcina

  14. A treia Pala- eliberareasistemului de ridicare se face iesind in afaranaceleipurtandcentura de siguranta tip ham.

  15. Turbinamontata- o turbinaestemontata in maxim douazilesi produce energietimp de 24 de ani