1 / 12

Hybrid & Module Testing Status

Hybrid & Module Testing Status. Week of 5/2-5/6. UCSB Hybrid Testing Status. Failing Hybrids Over-counted. This Week 4 with shorts in PA Lithography errors-fixable. Cumulative 7 with Shorts in PA Repairable 1 Major Scratch in PA 1 Smashed APV-PA Bonds Repairable 2 Failed Inspection

bellis
Télécharger la présentation

Hybrid & Module Testing Status

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Hybrid & Module Testing Status Week of 5/2-5/6

  2. UCSB Hybrid Testing Status Failing Hybrids Over-counted

  3. This Week 4 with shorts in PA Lithography errors-fixable Cumulative 7 with Shorts in PA Repairable 1 Major Scratch in PA 1 Smashed APV-PA Bonds Repairable 2 Failed Inspection Never should have sent 1 Broken Ceramic 1 Bad Bond Feet 1 Weak Wirebonds 1 Too Many Opens 2 with unknown failure UCSB Hybrid Testing Failures

  4. UCSB Hybrid Testing Issues • Need to finish validation of new software • Bruno contacted about bugs/features • Need to add automatic upload of data to new software • Hybrids with shorts need repairing • Once repaired need to keep bookkeeping straight

  5. UCSB ARCS Testing Status

  6. This Week None Fixed 1 module Found the problem with another Fixable, need to ship to FNAL for solder repair Cumulative 1 with >2% Bad Channels Debris on sensor 1 Bad DCU Fixable, soldering problem 1 HV Shorted to CF Frame FIXED!! 2 with >20 mA Bias Current 1 leaky pinhole 1 scratched sensor UCSB ARCS Testing Failures

  7. FNAL ARCS Testing (2005)

  8. FNAL ARCS Testing (from 12/2004)

  9. This Week (8105-8167) one unexpected pinhole - pulled (mod 8140 # 3) 8 PHL-: 8138 (#92), 8139(#430), 8144(#438), 8146 (#58), 8152(#78), 8153(#645), 8154(#650), 8167(#119) 1 SHT ARCS 8.0 has been installed and is being tested; looks ok so far Cumulative (7835-8167) 2 grade “B” (mishandling; missing bonds on p/a) 7970 - breakdown current behavior @430V Total of 11 pinholes Cumulative (7702-8167) 2 grade “B” (mishandling; missing bonds on p/a) 2 grade “F” mishandling 7970 - breakdown current behavior @430V FNAL ARCS Testing Failures

  10. UCSB LT Testing Status

  11. FNAL LT Testing Issues • Modules 30200020008064 – 8100 were tested during May 3-May 10 period. • Modules 30200020007961 - 7970 were retested. • All modules successfully passed LT with grade A. • All runs were performed with 2 CCU6’s. • Currently working on configuring 2 CCU25’s • (0x14 and 0x11).

  12. Weekly Cumulative fFail Pass Fail Pass % Pass L12pu 0 0 0 0 0.00% L12pd 0 0 12 0 100.00% L12su 0 0 0 0 0.00% L12sd 0 0 0 0 0.00% 9150 L34p 37 0 1 99.33% L56p 10 0 104 0 100.00% R5N 0 0 0 0 0.00% 00 00 00 R5S 0 0.00% R6 0 0 0 0 0.00% R7 0 0 0 0 0.00% Total 47 0 266 1 99.62% FNAL LT Testing Status

More Related