1 / 15

A WORKSHOP ON FINANCIAL MANAGEMENT IN HYDROLOGY PROJECT – PHASE-II

A WORKSHOP ON FINANCIAL MANAGEMENT IN HYDROLOGY PROJECT – PHASE-II. G ujarat W ater R esources D evelopment C orporation Ltd. GWRDC GANDHINAGAR (GW Component GUJARAT). FINANCIAL MANAGEMENT IN HYDROLOGY PROJECT (PHASE-II) LOAN NO. 4749-IN TOTAL PROJECT COST RS. 55559 LACS.

bernie
Télécharger la présentation

A WORKSHOP ON FINANCIAL MANAGEMENT IN HYDROLOGY PROJECT – PHASE-II

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. A WORKSHOP ON FINANCIAL MANAGEMENT IN HYDROLOGY PROJECT – PHASE-II Gujarat Water Resources Development Corporation Ltd. GWRDC GANDHINAGAR (GW Component GUJARAT)

  2. FINANCIAL MANAGEMENT IN HYDROLOGY PROJECT (PHASE-II) LOAN NO. 4749-IN TOTAL PROJECT COST RS. 55559 LACS. TOTAL COST OF GW COMPONENT-GUJARAT-RS.1044 LACS PROJECT SPAN : 6 YEARS STARTING FROM 2006-07 TO 2011-12

  3. PROJECT COST DETAILS FOR GROUND WATER COMPONENT (GUJARAT) I : INVESTMENT COST SR.NO. CATEGORY TOTAL COST (RS. IN LACS) 1 WORKS 124.09 2 GOODS 322.19 3 TRAINING 162.30 4 CONSULTANCY 94.82 TOTAL - I: 703.40 II: RECURRENT COST 1 O & M WORKS 15.97 2 O & M GOODS 4.75 3 STAFF 225.27 4 O & M OFFICE 65.02 5 O & M VEHICLES 29.63 TOTAL COST : I + II RS.1044.04

  4. Hydrology Project Phase-II A B S T R A C T CATEGORY WISE (GUJARAT - GW) Detailed Base Cost I. INVETMENT COST (Rs. In lacs) CATEGORY Y E A R TOTAL 2006 2007 2008 2009 2010 2011 W O R K S 0 29.79 37.19 38.76 12.06 6.30 124.09 G O O D S 33..51 93.20 89.61 62.28 27.21 16.40 322.19 T R A I N I N G S 23.86 34.57 31.73 27.88 24.06 20.22 162.30 C O N S U L T A N C Y 7.27 20.95 26.06 19.22 13.51 7.82 94.82 T O T A L INVESTMENT COST 64.63 178.50 184.58 148.13 76.84 50.74 703.40

  5. II. R E C U R R E N T COST O & M Works 2.46 2.46 2.56 2.77 2.87 2.87 15.97 O & M Goods 0 0 0.46 1.23 1.53 1.53 4.75 Staff 19.65 35.34 44.17 52.99 45.40 27.74 225.27 O & M Office 4.72 10.82 16.15 20.75 10.11 2.45 65.02 O & M Vehicles 1.02 4.09 6.13 6.13 6.13 6.13 29.63 T O T A L R E C U R R E N T COST 27.85 52.71 69.47 83.87 66.04 40.72 340.64 G W T O T A L H. P. - I I 92.48 231.21 254.05 232.00 142.88 91.46 1044.04

  6. PROJECT COST Rs. 1044.04 Lacs

  7. CAPITAL COST Rs. 703.40 Lacs

  8. RECURRENT COST Rs. 340.64 Lacs

  9. FINANCIAL TARGETS FOR F.Y.2006-2007(RS. IN LACS) I INVESTMENT COST SR.NO. CATEGORY ESTIMATED BASE COST (2006-07) ANTICIPATED EXPS. 2006-07 REMARKS 1 WORKS 0 0 2 GOODS 33.51 21.28 For procurement of Goods, CGW is, Faridabad, vide letter dt.21/6/06 has stated that procurement can be made after specification is finalized by specification committee to be constituted by MOWR, Delhi. 3 TRAINING 23.86 9.56 Training for onsite sampling analysis under water Quality Procedure @ WALMI will be completed by September-06 and Govt.of Gujarat has approved Rs.9.56 lacs for the same. 4 CONSULTANCY 7.27 0 Total :- 64.64 30.84

  10. FINANCIAL TARGETS FOR F.Y.2006-2007 (RS. IN LACS) SR.NO. CATEGORY ESTIMATED BASE COST (2006-07) ANTICIPATED EXPS. 2006-07 REMARKS II RECURRENT COST 1 O & M WORKS 02.46 0.00 2 O & M GOODS 0.00 0.00 3 STAFF 19.65 26.06 4 O & M OFFICE 04.72 0.00 5 O & M VEHICLES 01.02 0.00 Total : II 27.85 26.06 GRAND TOTAL : I + II 92.49 56.90 Increment staff cost is estimated to be of Rs.26.06 lacs and considered from July-06 onwards. Anticipated Expes. For the first year of project span is less than estimated Exps. But will be absorbed on spill over works.

  11. HYDROLOGY PROJECT – PHASE-II GW-COMPONENT DISBURSEMENT ARRANGEMENT :  Function of GROUND WATER COMPONENT IS UNDER the control of Principal Secretary, Narmada Water Resources, Water Supply and Kalpasar Department Gandhinagar (Gujarat). The Funds are allocated as per Budget provisions in Annual Budget of the Deptt. Budget provision for the year 2006-07 for Hydrology Project amounts of Rs.29.90 lacs. Whereas,Targated expenditure for the year 2006-07 is Rs.56.90 lacs. Remaining amount is expected to be provided by the Govt. of Gujarat in supplementary budget Allocations. Govt. of Gujarat is allotting Funds as per requirement of the project hence, the allocation of fund is not the hurdle in Implementing the project.

  12. Sr.No. Expenditure Category Financing Percentage 1 Civil work 90% 2 Goods including equipments Machinery, Vehicles,materials 100% Foreign Exps. 100% Local expenditure (Ex. factory) 80% Local expenditure procured locally. 3 Consultancy Charges 90% 4 Training 100% 5 Incremental operating costs including salaries 80% up to 31-3-2007 75% up to 31-3-2008 60% up to 31-3-2009 50% there after HYDROLOGY PROJECT – PHASE-II GW-COMPONENT REPORTING FORMATS : (1) SOE (Statement of Expenditure) Like HP-1 Project, SOE will be prepared with full documentation and supporting vouchers and submitted to Government of Gujarat considering eligible expenditure at prescribed % for financing. (2) Quarterly Progress Report :- (QPR)   Physical and Financial Quarterly progress reports will be prepared and submitted to Govt. of Gujarat for Further disposal.

  13. HYDROLOGY PROJECT – PHASE-II GW-COMPONENT ACCOUNTS AND AUDIT : (A) Accounts : GWRDC Ltd., is a wholly owned Govt. company within the meaning of section 617 of the companies Act, 1956. As such Accounts are prepared on Accrual basis and as per Mercantile System of Accounts. So for as Hydrology Project-II is concerned Accounts of the project will be maintained on CASH BASIS OF ACCOUNTS and expenditure will be classified as per a) Budget head of account and b) Disbursement category Also, prescribed registers will be prepared at each unit level and all concerned accounts personnel will be trained with the requirement of Financial Management as prescribed. (B) Audit : As stated in (A) above, being a Govt. Company, accounts of the corporation are audited by statutory Auditors appointed by comptroller and Auditor General of India, New Delhi and Supplementary Audit is also conducted by C & A.G. More over, Internal Audit is carried out by the experienced firm of Chartered Accountants. In HP, -1 project GWRDC Ltd., got audited the Hydrology project expenditure through a firm of Chartered Accountants and prescribed audit reports were submitted to MOWR. Likewise, audit of HP-II will be carried out by the firm of Chartered Accountants and reports of the auditors will be submitted within reasonable time limit.

  14. HYDROLOGY PROJECT – PHASE-II GW-COMPONENT (GUJ.) FINANCIAL MONITORING : 1)Adequate provision of funds will be made through Budget provisions of Govt. of Gujarat during Project Span of 6 years starting from 2006-07. 2)Procurement of goods, equipments, materials, machinery, hiring of consultants will be done as projected and as per the Bid documents, bid procedures etc., as done in HP-1 project and as per prescribed procedure. 3)Expenditure incurred will be monitored with reference to estimates made and on components of the project. 4)Required Information will be collected and submitted to the concerned Authorities on due date. Proper Accounts will be maintained for which training will be given to concerned Accounts personnel of each Implementing units.

  15. The Presentation reveals the Financial Management for HP – II by the Gujarat State Gujarat Water Resources Development Corporation Ltd. (GWRDC Ltd) THANKS

More Related