December 11, 2013 |Westborough, ma

December 11, 2013 |Westborough, ma. Michael N. Taniwha. DIRECTOR, IT DEVELOPMENT AND POWER SYSTEM SUPPORT. Clarify Information Policy re sharing Operating Reliability Data - Meeting #1. Information Policy Changes. Overview. Background The Interregional Security Network (ISN)

bijan
Télécharger la présentation

December 11, 2013 |Westborough, ma

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. December 11, 2013 |Westborough, ma Michael N. Taniwha DIRECTOR, IT DEVELOPMENT AND POWER SYSTEM SUPPORT Clarify Information Policy re sharing Operating Reliability Data - Meeting #1 Information Policy Changes

  2. Overview • Background • The Interregional Security Network (ISN) • Information Policy Changes • Transition of NERCnet to the EIDSN

  3. Background Mandatory reliability standards and other FERC/NERC initiatives have pushed for: • Improved “situational awareness” • Better understanding of impact of “external contingencies” • Availability of more detailed information for wide area monitoring August 2003 Northeast Blackout • U.S.-Canada Power System Outage Task Force Sept. 2011 CA/AZ Outages • FERC/NERC Staff Report on the September 8, 2011 Blackout

  4. The Interregional Security Network (ISN) • The Interregional Security Network (ISN) is commonly referred to by the term NERCnet and has been in operation since 1997 • NERCnet is a communication network used by NERC, Reliability Coordinators (RCs), Transmission Operators (TOPs), Balancing Authorities (BAs) to share real-time operating reliability data (ORD) across the Eastern Interconnection • The ORD is used to provide wide area situational awareness and sharing of ORD is a requirement of the mandatory NERC Reliability Standards • The ORD consists of transmission interface limits, line flows, circuit breaker status , generator output etc. • Likely to include phasor measurement data (PMU) in the near future

  5. Information Policy Changes • The ISO proposes changes to the ISO New England Information Policy so that the policy better reflects the ISO’s obligations to share reliability-related data pursuant to NERC and similar requirements

  6. Example Reference NERC standards • http://www.nerc.net/standardsreports/standardssummary.aspx • COM-001-1.1 • TOP-005-2a

  7. Transition of NERCnet to EIDSN • NERC has moved to transition management and support of the reliability tools (RCIS, NERCnet, IDC) to the industry • The “Eastern” Reliability Coordinators are establishing the Eastern Interconnection Data Sharing Network (EIDSN) and management entity to pick up NERCnet • NERCnet is scheduled to become the EIDSN in 2014

More Related