1 / 4

Maintenance Outage Level Designation Revision Process

The system is being revised to require MPs to input Planned Start date and Outage Type for each Maintenance Outage. ERCOT is initiating the project to implement these changes for more accurate outage designation. Updated requirements and schedules will be shared with MPs. Development and Testing will follow with a testing window provided before going live.

Télécharger la présentation

Maintenance Outage Level Designation Revision Process

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. SCR770 Revision to Outage Scheduler Entry for Maintenance Outage Level Designation Woody Rickerson QMWG

  2. SCR770 Revision to Outage Scheduler Entry for Maintenance Outage Level Designation • Current Process: • Outage Scheduler system automatically determines the level for each Maintenance outage based on the date the outage request is submitted and the Planned Start of the outage: • Maintenance Level 1 – The Planned Start is less than 24 hours from the outage request submission • Maintenance Level 2 – The Planned Start is greater than 25 hours and less than 7 days from the outage request • Maintenance Level 3 – The Planned Start is greater than 8 days and less than 30 days from the outage request QMWG

  3. SCR770 Revision to Outage Scheduler Entry for Maintenance Outage Level Designation • New Process: • This System Change will require MPs to enter the requested Planned Start date and the appropriate Outage Type for each Maintenance Outage. QMWG

  4. SCR770 Revision to Outage Scheduler Entry for Maintenance Outage Level Designation • Project to Implement Changes: • ERCOT is starting the project now • Requirements will be shared with MPs • ERCOT is working on Design • Schedule will be shared when it is known so that MPs can line up Development and Testing resources for any changes they may need to make • ERCOT intends to complete Development and Testing and then allow a window of time for MPs to test in MOTE before go-live QMWG

More Related