1 / 19

NATCOR Stochastic Modelling Course Inventory Control – Part 3

NATCOR Stochastic Modelling Course Inventory Control – Part 3. Adam Letchford Department of Management Science Lancaster University Management School. Multi-Item Problems. So far, we have only considered problems in which there is a single product type (“item”) to order.

blairj
Télécharger la présentation

NATCOR Stochastic Modelling Course Inventory Control – Part 3

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. NATCOR Stochastic Modelling CourseInventory Control – Part 3 Adam Letchford Department of Management Science Lancaster University Management School

  2. Multi-Item Problems • So far, we have only considered problems in which there is a single product type (“item”) to order. • In real life we typically have many items to order. • This leads to some complications. • We now briefly consider three commonly-used multi-item models. • For simplicity we assume demand is deterministic. • We let n denote the number of items.

  3. Variant I: Shared Space • Let item i have annual demand Di, order cost Co(i) and annual holding cost Ch(i). • We may also have lower bounds li and upper bounds ui for the delivery quantities. • Now suppose that one unit of item i takes up si space, and the total space available is S. • Each item must be ordered at regular intervals.

  4. Variant I: Shared Space (cont.) If order quantity for item i is Qi, then: • number of times i ordered per year is Di/Qi • annual ordering cost for i is Co(i) Di/Qi • average amount of i in stock is Qi/2 • annual cost of holding i in stock is Ch(i) Qi/2.

  5. Variant I: Shared Space (cont.) So we need to solve the Nonlinear Programme: This NLP is convex and can be solved efficiently (see Ziegler, 1982).

  6. Variant II: Clustered Items • Now forget about the issue of shared space. • Suppose that the company wish to make inventory control easier by grouping the items into k “clusters”. • We are free to choose integers T1, …, Tk so that items in cluster i are ordered every Ti time units. • E.g., items in cluster 1 ordered every 4 weeks, items in cluster 2 ordered every 7 weeks, etc. • The optimal clustering can be computed efficiently, by dynamic programming (Chakaravarty, 1981).

  7. Variant III: Joint Replenishment Now suppose that the n items all come from the same supplier. Then, if several different items are delivered at the same time, there may be a discount. One way to model the discount structure is to suppose that we have a “major” delivery cost M, together with a “minor” delivery cost mi for each item i. The cost of a delivery is then the major cost plus the sum of the relevant minor costs.

  8. Variant III: Joint Replenishment (cont.) • The resulting problem is called the Joint Replenishment Problem (JRP). • It can be formulated as a mixed-integer nonlinear programme. • It is “NP-hard”, which makes it unlikely that an efficient algorithm exists for all instances. • But some good heuristics exist. • See the survey Khouja & Goyal (2008).

  9. And now for somethingcompletely different…

  10. A “One-Off” Model: the Newsboy Problem At the start of each day, a newsboy must decide on the number of papers to purchase. Daily sales are stochastic, and are represented by the random variable x. Purchasing one copy costs p. Selling one copy yields revenue r (> p). Scrapping an unsold copy costs s. How many copies should he purchase?

  11. Newsboy Problem (cont.) It is helpful to compute: Unit cost of over-stocking = co = p + s Unit cost of under-stocking = cu = r – p. (Note: if desired, one can also attempt to incorporate “loss of customer goodwill” by increasing cu.)

  12. Newsboy problem: cost function Suppose he orders Q copies. For a given demand x, Cost of over-stocking = co× Max {0, Q – x} Cost of under-stocking = cu× Max {0, x – Q}. So we wish to choose the value Q that minimises the expected value of : coMax {0, Q – x} + cu Max {0, x – Q}.

  13. Newsboy problem: cost function (cont.) Therefore if f(x) is the probability density function for the demand variable x, we wish to minimise the function: To find such a minimum, we need to set the derivative of g(Q) to zero!

  14. Newsboy problem: solution Now, Leibnitz’ rule states that… And therefore = coF(Q) - cu (1 – F(Q)), where F(.) is the cumulative density function.

  15. Newsboy problem: solution (cont.) So for a minimum we need coF(Q) - cu (1 – F(Q) = 0, or, equivalently, F(Q) = cu/(co + cu). So just compute cu/(co + cu) and then find the desired value of Q (e.g., from Normal tables).

  16. Newsboy problem: visualisation

  17. Newsboy problem: final remarks To be sure that we have a minimum, we should check that the second derivative of g(Q) is positive for our chosen value of Q. In fact, the second derivative is (co + cu) f(Q), which is always positive. Therefore not only do we have a minimum, but we know that g(Q) is a convex function.

  18. References I: Books W.J. Hopp & M.L. Spearman (2011) Factory Physics (3rd edn.) S. Nahmias (2008) Production & Operations Analysis (6th edn.) E. Porteus (2002) Foundations of Stochastic Inventory Theory. E.A. Silver, D.F. Pyke & R. Peterson (1998) Inventory Management and Production Planning and Scheduling (3rd edn.) D. Sipper & R.L. Bulfin Jr (1997) Production: Planning, Control and Integration.

  19. References II: Papers A.K. Chakaravarty (1981) Multi-item inventory aggregation into groups. J. Oper. Res. Soc., 32, 19-26. F.W. Harris (1913) How many parts to make at once. Factory, The Magazine of Management, 10, 135-136, 152. M. Khouja & S. Goyal (2008) A review of the joint replenishment problem literature: 1989–2005. Eur. J. Oper. Res., 186, 1-16. H. Ziegler (1982) Solving certain singly constrained convex optimization problems in production planning. Oper. Res. Lett., 1, 252–256.