MoE Priorities for the Next 5 Years

MoE Priorities for the Next 5 Years . Presentation No 2 - Dtd (2 nd June 2009). Iraqi Electricity Sector: The electricity sector in Iraq requires large investments to fulfill the increasing demand on electrical power.

blaise
Télécharger la présentation

MoE Priorities for the Next 5 Years

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. MoE Priorities for the Next 5 Years Presentation No 2 - Dtd (2nd June 2009)

  2. Iraqi Electricity Sector: • The electricity sector in Iraq requires large investments to fulfill the increasing demand on electrical power. • The below table shows the expected peak demand for electricity from 2009 to 2015. • The below table shows the situation of the electricity network for the first five months in 2007 and 2008.

  3. The required investment is estimated to be $16 Billion US Dollars from the period 2007 – 2010 according to the National Development Strategy issued by the Ministry of Planning and Development Cooperation and these estimates include government and private investments. • MoE have plans to increase the production capacity and improve the performance of their transmission and distribution to cover the full demand gradually till 2012 by: First: Rehabilitation of the existing power plants to produce electric power to their existing access design capacity. This will have a low cost effectiveness as well as short time for implementation. Second: Establishment of new production plants (Thermal & Gas) according to the central plan to cover the entire requirement of electricity power till 2012.

  4. REHABLITATION OF GAS STATIONS FOR 2009 & 2010

  5. REHABLITATION THERMAL POWER STATIONS 2009 - 2014

  6. NEW THERMAL POWER STATIONS FOR 2009 - 2015

  7. NEW GAS STATIONS 2009 - 2015

  8. NEW GAS TURBINE PROJECTS 2009 – 2014 The MoE’s plan includes the establishment of Gas Turbine projects units as follows : 1) 60 Units 125 MW each (GE). 2) 4 units 40 MW each (GE). 3) 6 units 260 MW each (SIEMENS). 4) 10 units 160 MW each (SIEMENS).

  9. No. 18, 19 & 20 are under prequalification