CONTROLLING VOLTAGE AT TRIVANDRUM AND FLOW ON EDAMON-KAYATHAR

This article discusses the advantages, issues of concern, and possible solutions for controlling voltage at Trivandrum and flow on the Edamon-Kayathar line. It also explores the impact on the overall stability and transfer margin of the Kerala power system.

boucherc
Télécharger la présentation

CONTROLLING VOLTAGE AT TRIVANDRUM AND FLOW ON EDAMON-KAYATHAR

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. CONTROLLING VOLTAGE AT TRIVANDRUM AND FLOW ON EDAMON-KAYATHAR

  2. ADVANTAGES OF MADURAI-TRIVANDRUM LINE • ALTERNATE SUPPLY PATH TO TRIVANDRUM AREA • INCREASED STABILITY OF S.KERALA SYSTEM • DECREASED LOSSES • IMPROVED TRANSFER MARGIN – FACILITATING BETTER MERIT ORDER OPERATION AND ECONOMY

  3. THE ISSUES OF CONCERN • HIGH VOLTAGE AT TRIVANDRUM • TRIPPING OF ICT ON V/F AT NIGHT • RISK OF TRIPPING OF LINE • CONTINUED HIGH LOADING ON 220 KV EDAMON-KAYATHAR PREVENTING FURTHER DECREASE IN GENERATION IN KSEB SYSTEM

  4. CONTROLLING VOLTAGE AT TRIVANDRUM AND FLOW ON EDAMON-KAYATHAR

  5. POSSIBLE SOLUTIONS • TRIPPING 220 KV EDAMON KAYATHAR LINE • ADVANTAGES • FLOW INCREASES ON 400 KV MADURAI-TRIVANDRUM LINE • CONSTRAINTS OF DRAWAL BY KERALA ARE RELAXED • VOLTAGES AT 400 KV REDUCED • ISSUES/CONCERNS • INCREASED LOADING IN TN SYSTEM ESPECIALLY DURING WINDMILL GENERATION • HIGH LOADING ON 220 KV S/C TTPS-SIPCOT SECTION(16 KMS) • LINE TO BE BROUGHT BACK WHEN EVER POSSIBLE

  6. POSSIBLE SOLUTIONS • SPLIT BUS OPERATION AT 220 KV EDAMON STATION • ADVANTAGES • FLOW INCREASES ON 400 KV MADURAI-TRIVANDRUM LINE AND DECREASES ON 220 KV EDAMON-KAYATHAR LINE • CONSTRAINTS OF DRAWAL BY KERALA ARE RELAXED • VOLTAGES AT 400 KV REDUCED • ISSUES/CONCERNS • SPLIT BUS OPERATION RESULTS IN PROTECTION SYSTEM AND OPERATIONAL COMPLEXITIES • MAY HAVE TO BE RE-WORKED DEPENDING ON CHANGING SYSTEM CONDITIONS • ACTUAL SITE CONDITIONS REQUIRES TO BE EXAMINED

  7. 110 KV

  8. CONSTITUENTS TO REVERT BACK WITH FOLLOWING DETAILS • SINGLE LINE DIAGRAM OF EDAMON 220 KV STATION, 220/110 TRF LOADS • WINDMILL GENERATION IN TN, TYPICAL LOADING ON TTPS EVACUATION LINES • SCHEME HAS TO BE RE-WORKED IN CASE GENERATION PROFILE CHANGES • KAYAMKULAM IS ON BARS • LOW WINDMILL IN TN ETC