1 / 23

PORTOLA MIDDLE SCHOOL PROJECT STATUS PRESENTATION May 31 , 2014

PORTOLA MIDDLE SCHOOL PROJECT STATUS PRESENTATION May 31 , 2014. School Designer Design Awards Bronze Award: Library/Media Center. BUILDING D. BUILDING C. BUILDING B. BUILDING A. LOWER LEVEL – PHYSICAL ACTIVITY. BUILDING D. BUILDING C. BUILDING A. BUILDING B. MID-LEVEL

brede
Télécharger la présentation

PORTOLA MIDDLE SCHOOL PROJECT STATUS PRESENTATION May 31 , 2014

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. PORTOLA MIDDLE SCHOOL PROJECT STATUS PRESENTATION May 31,2014 School Designer Design Awards Bronze Award: Library/Media Center

  2. BUILDING D BUILDING C BUILDING B BUILDING A

  3. LOWER LEVEL – PHYSICAL ACTIVITY BUILDING D BUILDING C BUILDING A BUILDING B

  4. MID-LEVEL ENTRY AND ACADEMIC BUILDING D BUILDING C BUILDING A BUILDING B

  5. UPPER LEVEL ARTS / MULTI-USE BUILDING D BUILDING C BUILDING A BUILDING B

  6. BUILDING A ORIGINAL CLASSROOM BUILDING

  7. BUILDING B NEW GYM / ADMIN / LIBRARY

  8. BUILDING C NEW CLASSROOM BUILDING

  9. BUILDING D NEW MULTI-PURPOSE BUILDING

  10. SCHEDULE Complete Construction– Today – Dec 2015 Outfit FF&E Jan 2016 – March 2016 Move-in – March/April 2016 Renovate Temp Campus for Fairmont June 2016 - Sept 2016

  11. Leroy F. Green Design Awards Award of Merit FAIRMONT ELEMENTARY SCHOOL

  12. CURRENT CAMPUS • 55 year old campus • 2.95 acres • 38,500 S.F. of Buildings • 580 Pre-K through 6th grade enrollment in 2013-2014 • 24 classrooms • Administration, Kindergarten classrooms, and Library are undersized. • Special Education classrooms are inadequate. • Staff parking used by Public Library and Senior Center

  13. PROGRAM NEEDS • Increase in Enrollment up to 611 students • 10% Special Ed. – appropriate spaces needed • Increase in classrooms required • Flexible Multi-Use spaces required • Larger Multi-Purpose & Administration • More kindergarten classrooms • Maintain existing play area • Improve Sp. Ed Bus Pick-Up / Drop-off • Improve control of campus entry points

  14. PROGRAM DRIVEN REPLACEMENT CAMPUS • 3.23 acres • 75,973 S.F. • 611 Pre-K through 6th grade enrollment • 34 classrooms • Administration controls campus points of entry • Sp. Ed. classrooms - size increased to 1,450 S.F. District Standard • Two Multi-Purpose rooms for instructional Flexibility. • Outdoor learning spaces

  15. CLASSROOM WING • 960 S.F. classrooms following District standards. • 18 foot long teaching wall • Ceiling mounted projector & pull down screen • 4 computer stations • Tall operable windows • Classrooms meet CHPS criteria STANDARD CLASSROOM

  16. SPECIAL ED. CLASSROOMS • Three 1,450 S.F. classrooms with changing room, showers, laundry, restroom, and office/storage area. • Pre-K, Primary and Secondary Severely Handicapped • Learning Center • Speech • Full Inclusion / ICHAT • Occupational Therapy STANDARD SPECIAL ED CLASSROOM

  17. KINDERGARTEN WING • 4 classrooms @ 1,450 S.F.; includes shared workspace, storage and student restrooms • 18 foot long teaching wall • High sloped ceilings for daylighting and ventilation. SHARED WORKROOM STANDARD KINDERGARTEN

  18. MULTI-PURPOSE BUILDING • 8,513 S.F. • Kitchen / Community kitchen • Speedline • Stage with access ramp • Table / Chair Storage • Lobby • Outdoor Eating Area MULTI-PURPOSE ROOM STAGE KITCHEN LOBBY

  19. ADMINISTRATION WING • Control of visitors entering campus. • Administration on ground floor. • Community Clinic, Parents’ Workroom, and Staff Lounge on second floor. GROUND SECOND

  20. LIBRARY • 2,800 S.F. state-of-the-art Library / media center • Story area with built in seating • Computer area easily supervised • Ceiling mounted projection screen • Centrally located • Flexibility MEDIA CENTER WORK ROOM STOR. LIBRARY

  21. SITE FEATURES • Fully accessible site • Tactile learning panels at all classroom entries • Making use of outdoor spaces as learning areas • Emphasis on local history & ecosystems • Daylighting circulation – both floors Classroom wing • Community Garden • Design meets CHPS requirements

  22. SCHEDULE Complete Design – May – Sept 2014 Permit - WCCUSD QA/QC Oct 2014 – Sept 2015 Bidding – May 2016 – Sept 2016 Construction – Sept 2016 – Sept 2018 Renovate Temp Campus for Fairmont June 2016 - Sept 2016

  23. Thank you!