CSX’s I-95 Corridor for the Virginians for High Speed Rail

CSX’s I-95 Corridor for the Virginians for High Speed Rail. March 13, 2007. Today’s discussion:. Provide an overview of CSX’s I-95 Corridor in Virginia Discuss Amtrak performance Review actions to improve performance Update construction projects In depth look at the Quantico Bridge cut-in

bree
Télécharger la présentation

CSX’s I-95 Corridor for the Virginians for High Speed Rail

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. CSX’s I-95 Corridorfor theVirginians for High Speed Rail March 13, 2007

  2. Today’s discussion: • Provide an overview of CSX’s I-95 Corridor in Virginia • Discuss Amtrak performance • Review actions to improve performance • Update construction projects • In depth look at the Quantico Bridge cut-in • The path to the Corridor of the Future and to the funding

  3. On-time performance of Amtrak trains is largely dependent on three factors. • Physical characteristics of the operating territory • Single/double track? • Signal System? • The operating mix of train traffic • How many trains? • What kinds of trains? • The validity of schedules • Can they be reliably maintained? • Do they adjust for known activities?

  4. Washington Richmond Washington Richmond CSX’s DC to Richmond corridor is our busiest multi-use, double track corridor and one of the busiest in the US. • ~110 miles of double track with centralized traffic control (CTC) • 48 Daily passenger/commuter trains • 18 Amtrak trains • 30 VRE commuter trains • ~32 daily freight trains • Over half the train slots filled by passenger trains • And until recently, a single track bridge

  5. Passenger operations outperform freight operations even with increased traffic and few capacity enhancements. • The high standard deviations for freight trains mean poor reliability for freight customers • Poor freight reliability means more highway congestion

  6. Freight Interference by Road CSX and BNSF have the lowest levels of freight train interference.

  7. Maintenance of Way, Signal, and Slow Order Caused Amtrak Delays In 2005 and 2006, CSXT delays to Amtrak trains have been driven more by maintenance than by freight train delay.

  8. CSX is completing a robust RF&P maintenance program. • Invested $19 million in RF&P track structure in 2005 and 2006 • Replaced 176,092 ties (138.2 track miles) • 97,165 feet of rail (9.2 track miles) • Another $10.5 M planned in 2007 • Replacing 48,000 ties (43.68 track miles south of VRE service area) • Replacing 78,000 feet of rail (14.74 miles) • Investments benefit passenger service: Better ride and more reliable service • However, tie replacement: • Requires the removal of the rail anchors • Breaks the surface friction between the ties and the ballast • Destabilizes track, and • Requires a conservative approach to heat.

  9. Last summer’s passengers experienced significant delays; the root cause was a lack of capacity. • The most severe delays resulted from a combination of causes • June flooding set records • Severe electrical storm caused catastrophic damage at Possum Point • Traffic congestion due to booming economy • Lack of capacity • Lack of capacity identified as the root cause of delays years ago • VRE agreement • 1999 Federal Railroad Administration Report to Congress • 2000 CANAC Line Capacity Study for Virginia, VRE and CSX • MAROPS (Mid Atlantic Rail Ops Study - VA, FRA, FHWA, state DOTs, and Ports) • Causes significant traffic congestion which inhibits reliability and growth • Prevents recovery, regardless of the cause of the initial delay • Few stations have platforms serving both tracks, resulting in a single track operation for VRE • Only a small portion of the delays were attributable to heat orders • Affects trains between 1 PM and 7 PM only • 50 MPH, not 70 MPH, but multiple station stops limit the impact • Maximum delay of 10 minutes for Fredericksburg riders; more for Richmond and Newport News

  10. As responsible partners, we’ve taken a number of actions to improve performance as the capacity improvements are underway. • Intensified tactical focus produces results • Assigned experienced dispatchers to territory • Added operations superintendent to network dispatch center to monitor daily operations • Established new train manager for area • Increased signal, track and mechanical maintenance presence on corridor • Changed freight schedules for trains departing Richmond, Baltimore and Cumberland • Partnering with Amtrak & VRE on major maintenance work • Working nights to minimize disruptions when possible • Minimizes train cancellations • Less productive, more costly and more challenging for workers • But produces additional concerns during summer heat • Establishing an experienced based, realistic schedule

  11. The capacity enhancements will make a real difference, especially the opening of the Quantico Bridge. • Phase One – Complete • AF Interlocking • Dispatcher Consolidation • Phase Two – Complete • Arkendale crossovers • Elmont crossovers • Phase Three – Underway • L’Enfant 3rd main • Phase Four – 2007/2008 • Quantico Bridge (Feb. 2007) • Slater’s Lane to RO (Design) • Franconia 3rd main (Design) • Phase Five – 2008 • Fredericksburg to HA 3rd main (Design)

  12. The new 2-track Quantico Bridge opened February 17.

  13. P098 was the first train over the new Quantico Bridge.

  14. The $30M Quantico cut-in involves far more than just the construction of a new bridge.

  15. In addition, the Rail Advisory Board is funding the preliminary engineering for 11 miles of 3rd main between Arkendale and Powells Creek. • Increases capacity significantly • Eliminates congestion at Quantico Creek • Capitalizes on new Quantico Creek Bridge; from 1 to 3 tracks • Complements on-going, publicly-funded capacity improvements • Includes a new Cherry Hill VRE station stop • Uses match from a private developer

  16. But the consensus finding is that major investments are needed to finish the project in three phases. • Phase 1 • Build the third main track from DC to Richmond now • Exclude the high cost projects • Seek the preliminary engineering needed for firm estimates • Phase 2 • Attack the challenging, high cost projects next • Major bridges • Potomac • Aquia • Ashland constraints • Fredericksburg viaduct • Phase 3 • Develop the Corridor of the Future • Sealed high-speed freight passenger separation • Expanded freight capacity

  17. The DC to Richmond Third Track Feasibility Study provides the path for completion. • Complete the VTA 2000 program of projects. • Complete a comprehensive alternatives analysis • Conduct operational modeling • Review alternate right-of-ways • Analyze public and private benefits • Conduct an environmental review and the preliminary engineering • Determine the specific design • Develop accurate estimate of costs • Establish agreements • Identify a dedicated source of funding for capital and operating costs

  18. Funding Federal appropriations (primary source of funding) 2008/9 Transportation Reauthorization Bill Corridors of the Future State Appropriations ~$100m spent by Commonwealth of VA ~$20m in VA transportation bill Local governments and other agencies (1995 VRE agreement to fund 3rd main) Amtrak CSX - right of way & existing improvements Benefits Intercity passenger capacity / reliability Commuter capacity / reliability Trucks off the highway Reduced highway congestion on I-95 Environmental benefits Federal support is the key.

  19. CSX’s Corridor of the Future application may surprise you. • Corridor stretches 1,200 miles from Washington to Miami. • Corridor must be modified to address three major challenges • Both passenger and freight trains need to travel faster • Both passenger and freight trains need greater reliability and recoverability • Both passenger and freight train volume will increase • CSX’s vision for the future is: • Passenger trains must be able to travel unimpeded at 110 MPH • Freight trains must be able to operate at speeds of 50 MPH to 70 MPH • Passenger service must be physically separated from freight operations • Higher density industrial areas may require freight tracks on both sides of passenger tracks • The corridor must be sealed to prevent motor vehicle intrusion • 1700 at-grade highway rail crossings must be addressed

  20. We must finish the project; the next steps are… • Set realistic expectations during current construction • Align stakeholders around a common plan • Seek consensus and action on “Quick Hits” • Perform preliminary engineering – refine cost estimates • Organize and energize all stakeholders to advocate for these changes • Gain federal support

  21. Thanks for your attention. Questions?