1 / 17

Vermont Yankee

Vermont Yankee. Boiling Water Reactor. Reactor Building. Spent fuel pool. Concrete 3.8 Ci/m3. (Fe-55, Ca-45). Carbon steel 370 Ci/m3. (Co-60, Fe-55, Mn-54). Reactor Vessel and Internals. 2.9 Million Ci/m 3. (Co-60, Fe-55, Cr-51). (0.7 – 3 R/hr). Radioactivity as a Function of Time.

Télécharger la présentation

Vermont Yankee

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Vermont Yankee

  2. Boiling Water Reactor

  3. Reactor Building Spent fuel pool Concrete 3.8 Ci/m3 (Fe-55, Ca-45) Carbon steel 370 Ci/m3 (Co-60, Fe-55, Mn-54)

  4. Reactor Vessel and Internals 2.9 Million Ci/m3 (Co-60, Fe-55, Cr-51) (0.7 – 3 R/hr)

  5. Radioactivity as a Function of Time

  6. Decommissioning Alternatives • Dismantlement – remove all radioactive materials. Terminate license, except for spent fuel and hot core components. In VT, hopefully return to greenfield. • Safstor – remove much of external contamination. All fuel in storage casks. Remove cooling water pipes. Seal up reactor internals and wait. Revise license.

  7. CT Yankee Dry Storage

  8. Dry Storage Cask

  9. Cask 1.0

  10. Hi-Star 100 Cask

  11. Remaining Amts to Collect

  12. Entergy Misses the Mark

  13. TLG Projected Costs to Decom VY

  14. What must be done? • While the labor force is intact, immediate steps must be taken. VY will have to produce a decom plan for NRC, but we need a site survey now. • Safe, careful dismantlement must start asap. No guarantee SAFSTOR will lead to sufficient decom fund. The financial risk is too high. • Sufficient funds must be available to dismantle the reactor, dispose of waste and bring the VY site to greenfield condition. • VT must do an independent economic audit, and ensure the decom fund is fully funded.

  15. Money at Year End $297.1 $315.9 $372.8 $416.5 $439.6 $372.0 $428.4 Interest Rate Int rate 6.2% (est) (above cpi) Real cumulative rate 4.2% Average CPI infl rate 2.4% Net rate 1.8% (above cpi) Money in Decom Fund

  16. CT Yankee 619 MWe PWR $871 Million Shutdown 1996 Payments to 2015 DECON VT Yankee 620 MWe BWR $893 Million (estimate) $600 Million (TLG) ?? Shutdown 2012 Pay out to 2019 DECON Rate return 8.85% Amt Trust Fund $420 M Comparison CT and VT Yankees

More Related