1 / 29

St George Wharf

St George Wharf. Team Members. Marcus Blake - St George South London Tim Dodd - White Young Green Richard Moss - BRE Martin Stephenson- Stephensons. St George Wharf. Proposed innovations, expected improvements, implementation and results. Electronic Exchange of rebar information.

Télécharger la présentation

St George Wharf

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. St George Wharf

  2. Team Members • Marcus Blake - St George South London • Tim Dodd - White Young Green • Richard Moss - BRE • Martin Stephenson- Stephensons

  3. St George Wharf • Proposed innovations, expected improvements, implementation and results

  4. Electronic Exchange of rebar information • Expected Improvement • Significant savings in time on the part of the rebar supplier • Some savings in time on the part of the frame contractor and the main contractor

  5. Electronic Exchange of rebar information • Method of Measurement • Anecdotal evidence on reduction in number of mistakes • Cost and time comparison by the rebar supplier • Cost and time comparison by the rebar detailer • Cost and time comparison by the contractor

  6. Electronic Exchange of rebar information Electronic Exchange of rebar information • Implementation • Introduced part-way through project • Run in parallel with conventional approaches due to need for familiarisation and failure of large rebar manufacturer in the UK • Little perceived benefit by the detailer - tight existing programme • Greater potential for use where schedules produced electronically • Simple call-offs arranged - limited benefit in terms of control by the contractor

  7. Electronic Exchange of rebar information

  8. Rationalisation of main reinforcement • Expected Improvement • 15% reduction in man hours • 15% reduction in combined steel supply and fixing costs

  9. Rationalisation of main reinforcement • Method of Measurement • Feedback on experience of use by designer/ contractor • Direct comparison between rationalised/non-rationalised by frame contractor • Out-turn cost on steel fixing from frame contractor

  10. Rationalisation of main reinforcement • Implementation • Previous rationalisation already undertaken • Opted for standard 12m long stock length bars -Speed and simplicity of fixing + minimum material cost • Further comparisons required between consultant detailed slabs on first phase and trade contractor detailed slabs on subsequent phases • Man hours and costs being processed to quantify benefits

  11. Use of prefabricated punching shear reinforcement • Expected Improvement • From manufacturer's literature (up to 80% saving in man hours) • From manufacturer's literature (up to 50% in overall cost)

  12. Use of prefabricated punching shear reinforcement • Method of Measurement • No. of man hours per column head from frame contractor • Overall costs per column head from frame contractor

  13. Use of prefabricated punching shear reinforcement • Implementation • Two shear stud systems investigated • Comparison with traditional links • Shear steel obviated wherever possible by increasing main steel over column heads • Limited benefits unless large number of links required

  14. Use of prefabricated punching shear reinforcement

  15. Accurate prediction of deflections • Expected Improvement • Greater predictability of actual deflections occurring leading to savings on future blocks on architectural details to accommodate deflections (i.e. cladding/internal finishes)

  16. Accurate prediction of deflections • Method of Measurement • Actual deflections measured compared with predicted deflections using simple /sophisticated models

  17. Accurate prediction of deflections • Implementation • Improved knowledge of actual deflections • Improved understanding of deflection behaviour • Greater confidence in predicting actual deflections in future • Further validation of the work from Cardington

  18. Early age strength assessment using LOK tests • Expected Improvement • Quicker confirmation of slab strength • Cheaper and less time consuming than making and testing cubes • Manufacturers correlation may be relied upon • Cubes no longer required for early age strength assessment

  19. Early age strength assessment using LOK tests • Method of Measurement • Direct comparison of costs and availability of test results using LOK tests as opposed to cubes • Accuracy and spread of test results • Need for correlation

  20. Early age strength assessment using LOK tests • Implementation • LOK test run in parallel with cubes • Highlighted difficulty of accurately gauging concrete strengths at early ages • Further work required to convince all parties on reliability of LOK tests • Limited benefits on this phase owing to desired age at striking • No direct cost benefit

  21. Early age strength assessment using LOK tests

  22. Site comparison

  23. New criteria for striking • Expected Improvement • Benefits to speeding up floor cycle with/without limitation posed by vertical elements • Increased certainty of delivering existing programme • Speeding up of existing programme

  24. New criteria for striking • Method of Measurement • Comparison of criteria used and limitations on age at which striking can be undertaken

  25. New criteria for striking • Implementation • Detailed comparisons of new and old criteria • Limited benefit in terms of striking strength owing to assumptions made • Limited benefit in early striking in general owing to time taken to construct vertical elements

  26. New criteria for design of backpropping • Expected Improvement • Reduced requirement for backproping with consequent savings in labour and materials (50%)

  27. New criteria for design of backpropping • Method of Measurement • Comparison of backpropping arrangements and in particular numbers of levels of backpropping required

  28. New criteria for design of backpropping • Implementation • Benefit from pre-loading props clearly demonstrated • Resulting distribution through slabs closer to conventional assumptions • Difficult to predict/control level of preloading

  29. Conclusions Prerequisites • Earlier contractor involvement • Contractor detailing - Minimise/eliminate shear reinforcement - Construction of vertical elements is a constraint. Benefits of innovations limited until impact of this removed or reduced - cost/benefits of novel methods of doing this being investigated

More Related