1 / 20

Status JRA-SRF

Status JRA-SRF. List of submitted deliverable reports Report on continuing activities WP 2, WP 4 Status of remaining deliverables Highlights Approaching the end of JRA-SRF Annual meeting 2008 Final reports. Status WP2.2 Improved component design.

cahil
Télécharger la présentation

Status JRA-SRF

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Status JRA-SRF • List of submitted deliverable reports • Report on continuing activities • WP 2, WP 4 • Status of remaining deliverables • Highlights • Approaching the end of JRA-SRF • Annual meeting 2008 • Final reports

  2. Status WP2.2 Improved component design • First cavity prototype with bellows in the middle of the He tank finished and successful tested (tuner WP 8.1) • Design of an improved end group finished • Construction contract placed to ZANON for two new end groups (end of July) • Mechanical test of new end group starts end of October

  3. 5 mm NbTi end dish. Stiffness is about 28 kN/mm for each end dish. 7 mm NbTi end dish. Stiffness is about 38 kN/mm Stresses (MPa) are calculated for 2 bar pressure difference. Curved NbTi end dish. Stiffness is about 69 kN/mm

  4. WP 4 Vacuum arc coating • Detailed studies on samples to improve the adhesion • Treatment with 15% citric acid solution • Profilometer measurements • High pressure water tests • Successful recipe for samples • But no success with cavity coating • Still peeling off after high pressure water cleaning • Analysis of x-ray diffraction measurements (DORIS) indicate the presence of two distinguished niobium phases. • Still mechanical problems with cavity shape

  5. Linear Arc coating

  6. WP 4.2.3 Report on Deposition HTC Material by UHV Cathodic Arc • Several films have been deposited using a niobium cathode in a nitrogen atmosphere. • The nitrogen pressure, arc current and voltage bias were varied in order to obtain nitride films with good superconducting properties. • Despite the effort the maximum Tc obtained was ~15K with a large transition width. • The films were not uniform and presented on the surface aggregates of irregular shape formed in flight. • Conclusion: • Due to the extreme criticality of parameters it was concluded that it would be very difficult to obtain the desired nitride cubic phase everywhere on a cavity cell complex geometry surface.

  7. Report on Deposition HTc Material by UHV Cathodic Arc Figure 3 -Transition to the superconducting state of one of the first UHV arc deposited NbN samples. Tc about 15K, ∆Tc ~5K, Fig.6 – Peeling on the anode in the cathodic region

  8. INFN Legnaro: finished 9-cell cavity by spinning

  9. Status seamless cavity by hydroforming • Finished since some time • Waiting in cue with many TTF cavities for cold test, now ready for cold test

  10. Summary status JRA-SRF • There is no real show stopper • Basically all work is finished • Prototypes are fabricated, but not all are measured; is beyond the scope of deliverable • High risk tasks have been clearly identified in the Annex1 • Deliverable is de-scoped, some activities continue • Summary report in preparation

  11. HIGHLIGHT 1 Seamless 9-cell cavity by hydroforming Aktenzeichen PCT/EP 2008/006577 beim Europäischen Patentamt in München

  12. HIGHLIGHT 2 PhD on best EP ParametersElectropolishing without HF

  13. JRA-SRF Annual Meeting 08 • Not during Annual CARE Meeting at CERN, program is too crowded • Scheduled for November 08 as Video conference • We need guidelines for the final report ASAP • Draft should be finished until our annual meeting

More Related