Alpha Taxiway Rehabilitation Improvement Project

Yakima Air Terminal. Alpha Taxiway Rehabilitation Improvement Project. Project Overview Project Schedule Impacts Project Status Questions. Presentation Overview. The Yakima Air Terminal has received an $11,000,000 grant. The grant is to:

caleb-bauer
Télécharger la présentation

Alpha Taxiway Rehabilitation Improvement Project

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Yakima Air Terminal Alpha Taxiway Rehabilitation Improvement Project

  2. Project Overview Project Schedule Impacts Project Status Questions Presentation Overview

  3. The Yakima Air Terminal has received an $11,000,000 grant. The grant is to: • Resurface and widen Alpha Taxiway, Taxiway Connectors A1-A5, and portions of Bravo and Charlie Taxiways; • Resurface airfield pavement between the north taxiway edge line to the non-movement line; • Replace the existing MITL system with LED MITL, including new conduit, fixtures, and regulator; • Replace all existing directional and hold short signs; and • Correct several markings not meeting FAA standards. Project Overview

  4. Project Overview

  5. Project Overview

  6. Expected construction START DATE October 27, 2014: • October 27, 2014 – November 14, 2014 • Preliminary electrical work outside regular Phases 1-7 • Inclement Weather Shutdown • Phase 1: April 20, 2015 – May 15, 2015 • Phase 2: May 16, 2015 – May 29, 2015 • Phase 3: May 30, 2015 – June 12, 2015 • Phase 4: June 13, 2015 – July 3, 2015 • Phase 5: July 4, 2015 – July 24, 2015 • Phase 6 / 7: July 25, 2015 – August 25, 2015 Project Schedule

  7. Project Overview – Phase 1

  8. Phase 1:April 20, 2015 – May 15, 2015 • Ramp Closures. • McCormick West, and Plath Hangar. • Partial Ramp Closures. • Fuel Tank/House and McCormick Air Center. • Temporary Runway 9/27 Closure for work within the Runway Safety Area. • On-going construction activities and vehicle traffic on service roads and ramps. Impacts

  9. Project Overview – Phase 2

  10. Phase 2: May 16, 2015 – May 29, 2015 • Ramp Closures. • Airlift Northwest, FedEx Air Cargo and Airport Maintenance Building. • Partial Ramp Closures. • McCormick Air Center and Private Hangars (formerly Noland-Decoto). • Temporary Runway 9/27 Closure for work within the Runway Safety Area. • On-going construction activities and vehicle traffic on service roads and ramps. Impacts

  11. Project Overview – Phase 3

  12. Phase 3: May 30, 2015 – June 12, 2015 • Ramp Closures. • GE Aviation, West Itinerant Ramp, Med Assets, and West Terminal Apron Ramp. • Partial Ramp Closures. • Private Hangars (formerly Noland-Decoto). • Temporary Runway 9/27 Closure for work within the Runway Safety Area. • On-going construction activities and vehicle traffic on service roads and ramps. Impacts

  13. Project Overview – Phase 4

  14. Phase 4: June 13, 2015 – July 3, 2015 • Ramp Closures. • East Terminal Apron Ramp. • Partial Ramp Closures. • East Itinerant Ramp. • Runway 4/22 and Bravo Taxiway Closed. • Temporary Runway 9/27 Closure for work within the Runway Safety Area. • On-going construction activities and vehicle traffic on service roads and ramps. Impacts

  15. Project Overview – Phase 5

  16. Phase 5: July 4, 2015 – July 24, 2015 • Ramp Closures. • No Ramps Closed. • Alternate routes required for: Cub Crafters, McAllister Museum, Advanced Medical Systems, and South Air Park. • Temporary Runway 9/27 Closure for work within the Runway Safety Area. • On-going construction activities and vehicle traffic on service roads and ramps. Impacts

  17. Project Overview – Phase 6

  18. Phase 6: July 25, 2015 – August 25, 2015 • Partial Ramp closures denoted by barricades. • Runway 4/22 closed intermittently. • On-going construction activity and vehicle traffic on service roads and taxiways. Impacts

  19. Project Overview – Phase 7

  20. Phase 7: July 25, 2015 – August 25, 2015 • Not expecting any closures, however a schedule will be provided of the impacted areas to minimize air traffic and vehicle operations within the work areas. • On-going construction activities and vehicle traffic on service roads and ramps. Impacts

  21. If at all possible, avoid construction areas. • Please plan all operations around construction to the maximum extent possible. • If there are known operations that will be impacted by the proposed schedule, please let us know. • The Airport Management will provide NOTAMs. • Do not travel (plane or car) across barricades delineating closed pavement. • Do not provide direction to the contractor unless there is an emergency. Operations During Construction

  22. Robert Peterson Rob.Peterson@yakimaairterminal.com Office: (509) 575-6149 (#7) Cell: (509) 833-0898 Kris Yalovich Kris.Yalovich@yakimaairterminal.com Office: (509) 575-6149 (#7) Stephanie Ray, PE sray@hlacivil.com (509) 966-7000 Michael Battle, PE mbattle@hlacivil.com (509) 966-7000 Questions