70 likes | 191 Vues
This special report outlines the ongoing installation of the NT-06 beamline at the NuMI Target Hall. Key activities for the week starting April 4 include beamline installation, target beam scans, and preparations for full NuMI beam operations. Completed tasks include the installation of NT-06 in the carrier frame assembly and target surveying, all within specified tolerances. Contingency measures for NT-02 have been outlined, and an ALARA plan has been submitted for addressing slipping couplers and drive bearing issues. Work is scheduled to commence on April 5.
E N D
Kris Anderson 04-Apr-2011 Special Report NuMI Target Updates Status Update Target Hall • Target hall work for week starting 4/4 will be focused on NT-06 beamline installation, survey, target beam scans, and readiness for full NuMI beam operation NT-06 Preparation for Beamline Installation • Completed installation of NT-06 in carrier frame assembly • Completed target survey in several target z-locations at MI-8 • All features fall within specified tolerance (~ ¼ mm) III. Reclaim NT-02 as a contingency spare • ALARA plan generated to remedy slipping couplers and install a new DS screw drive bearing block • Plan has been submitted to AD/Radiation Safety • Work to recover z-drive motion expected to start Tuesday 4/5
Special Report NuMI Target Updates NT-06 Retrofit NT-06 Target/Baffle Carrier Assembly Survey work in LE10 position
Special Report NuMI Target Updates NT-06 Retrofit NT-06 Target/Baffle Carrier Assembly
Special Report NuMI Target Updates NT-06 Retrofit NT-06 Target/Baffle Carrier Assembly View of baffle from US end (beams-eye view)
Special Report NuMI Target Updates NT-06 Retrofit NT-06 Target/Baffle Carrier Assembly Target assembly moved into NuMI Target Hall
Special Report NuMI Target Updates NT-06 Retrofit NT-06 Target/Baffle Carrier Assembly Moving target carrier to workcell for installation on module
Key Dates Special Report NuMI Target Updates Estimated Key Dates-Nominal Scenario NT-06 Installation • Installation of NT-06 into beamline chase 4/4 – 4/9 • Estimate for beam ~12:00 on Sunday 4/10 II. NT-02 Path (Contingency Target) • NT-02 is leak tight but status of z-drive reclamation is still TBD • Efforts will start Tuesday 4/5 at CO to remedy slipping drive couplers and install a new bearing block assembly on the drive screw at the downstream location