1 / 26

M ICE O perations M anager Report

M ICE O perations M anager Report. Linda Coney University of California, Riverside UKNF Meeting June 8, 2010. Outline. Overview of MICE motivation and beam line layout MICE Schedule Target & Beamline Detector Commissioning p , e, p, and m beams Supporting infrastructure

cedric
Télécharger la présentation

M ICE O perations M anager Report

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. MICE Operations Manager Report Linda Coney University of California, Riverside UKNF Meeting June 8, 2010

  2. Outline • Overview of MICE motivation and beam line layout • MICE Schedule • Target & Beamline • Detector Commissioning • p, e, p, and m beams • Supporting infrastructure • Beam studies • Upcoming Production Running • Conclusions MOM Report-Coney

  3. MICE Motivation • The muon beam after the front end of a Neutrino Factory is: • Wide – sx ~ 10(+) cm • Divergent – sq ~ 150(+) mr • Need to cool the beam: • Increases number of muons in the acceptance of the accelerator by factor of 2-10 • Ionization cooling is the only good option: • Muon lifetime is short ~2 ms • Cannot use stochastic cooling – slow, iterative process • Muons pass through absorber material followed by RF cavities • Lose transverse and longitudinal momentum in absorber – restore longitudinal with RF g reduction in transverse emittance • Competition between cooling (dE/dx) and heating (multiple scattering) • Optimal results with: • Low Z, large X0 material • Tightly focused beam • H2 most promising absorber material • Simple premise; however, the reality is not simple a need a test MOM Report-Coney

  4. Muon Ionisation Cooling Experiment MICE: Design, build, commission and operate a realistic section of cooling channel Measure its performance in a variety of modes of operation and beam conditions … … i.e. results will be used to optimize the Neutrino Factory design

  5. Layout of MICE: Decay solenoid MICE Local Control Room Linde refrigerator Target Instrumentation in place: Beam profile monitorsTrigger/rate scintillatorsCKOVs, TOF0,1&2, KL Upstream beam line Downstream beam line

  6. MICE Schedule • Current focus is on Step I: • Beamline commissioning • Detector comissioning and calibration MOM Report-Coney

  7. Target Operations • 50,000 pulses of redesigned target in test stand in R78 • Current target installed in ISIS August 2009 • Run at base rate (50 Hz/32) and with ISIS at 50 Hz (Normal User Run) • Inspected regularly – PASSED • Target is working beautifully – NO problems • Target stability checked every 10,000 pulses • Process to monitor target behavior agreed upon with ISIS • Target timing wrt ISIS MS signal monitored • Coordinating Beam Loss measured by MICE with that measured by ISIS • Target Operation: 233,000 pulses to date • February/March User Run – 10 days • April/May User Run – 15 days • See target update during this session MICE target path ISIS cycles MS marker ISIS losses MOM Report-Coney

  8. Upstream Beamline MOM Report-Coney

  9. Beamline • Conventional magnets • Controls software improved • Automatic gradual ramp up/down implemented (DL) • Eases burden on electrical infrastructure & on shift crew • Faulty water flow gauges in all magnet power supplies replaced • Removes cause of most magnet trips during running • Water flow through magnets increased to recommended level • Monitored in Alarm Handler, archived • New pressure valves installed on magnets • Water pressure reduced from 8 to 4 bar • Field monitoring with Hall probe a Configuration Database in the works • Polarity detection scheme implemented • Proton Absorber installed in February downstream of Decay Solenoid -see talk this session – Chris Rogers (RAL) MOM Report-Coney

  10. Beamline: Decay Solenoid • Running well during data-taking September – December 2009 • Linde Fridge serviced in January a developed problems • Cooldown failed end of January • Fridge developed fault – N2 contamination in DS cold box • Blockage in cold trap? • Linde engineer to RAL late March gchanged charcoal in gas panel absorber, cycled through processes, no leaks • But when compressor isolated from cold box and cold trap back into operation N2 levels rose again • Leak in compressor shaft seal? • Easter g Engineer back to RAL mid April g new shaft seal g stuck & would not move • Compressor removed & taken to Linde contractor • Back April 20th with completely new compressor • Stuck seal suspected of being root cause of the problem • Still not solved • Wrong seal from manufacturer – designed for air not He • Ordered new seal – sent wrong one again • Finally got correct seal for compressor • Vacuum gauges also needed to be replace • Scroll pumps needed servicing as well (now done) • Cooldown (re)started mid-May – record time of 5 days • Liquid He level probe not working - Problem with old electronics? • Debugged – replaced suspected chip – end May determined sensor had gone bad • Friday – cold swapped for new sensor – now working • Magnet cold – undergoing current testing MOM Report-Coney

  11. Data Taking Program: Positive Particles • Detector Calibration: • 300 MeV/c pions - used for calibrating the TOF system • 290 MeV/c pions – TOF, KL • 270 MeV/c pions – TOF, KL • 250 MeV/c pions – TOF, KL • 200 MeV/c pions – TOF, KL • 300 MeV/c positrons - CKOV and KL calorimeter • 250 MeV/c positrons - CKOV and KL calorimeter • 200 MeV/c positrons - CKOV and KL calorimeter • 150 MeV/c positrons - CKOV and KL calorimeter • Beam Studies: • Luminosity monitor studies • Particle Rate vs Losses in ISIS Study • Muon beam configurations to study proton absorber(s) • Muon Beams:  • pi+ to mu+ beam (6-200, 3-200, 10-200)- 3500 pulses 17 MOM Report-Coney

  12. 0.48 m 0.48 m 10 x 4cm scintillator bars sx = 1.15 cm st = 50 ps 7 x 6cm scintillator bars sx = 1.73 cm st = 50 ps Tof-0 Tof-1 Detector Commissioning: Time of Flight Counters • TOF0, TOF1 installed for September & Nov/Dec User Runs • TOF2 installed in late November • Horizontal and vertical bars • Have proven to be essential in beamline commissioning MOM Report-Coney

  13. Detector Commissioning: Time of Flight Counters • Time resolution after the calibration: • TOF0 – 51ps; • TOF1 – 62ps; • TOF2 – 52ps. MOM Report-Coney

  14. Detector Commissioning: TOFs • Time of flight distributions for different data sets: MOM Report-Coney

  15. Detector Commissioning: e/m Identifier • KL lead/scintillating fiber calorimeter module • Calibration in progress • 50% of electrons 240 MeV/c at target, and 80% of electrons 360 MeV/c at target release energy in KL tag counter • Muons with 220 MeV/c at target reach EMR • Muons with < 80 MeV/c at KL will die in KL (170 at target) • More data needed: • 170 < mp <200 MeV/c at target • 195 < pp < 230 MeV/c at target Energy Response 27 MOM Report-Coney

  16. Beam Studies • Particle rate vs beam loss – Adam Dobbs - Imperial • Hold target timing steady – vary depth into beam to increase losses • Measure particle rate in MICE beamline • Luminosity Monitors – see talk this session – David Forrest - Glasgow • Determine particle rate close to target & find protons on target as function of depth • Validate particle production in target and beamline simulations • Emittance measurement with TOFs – see talk this session – Mark Rayner - Oxford • Purpose: generate the elements of the “emittance-momentum matrix” Study performance at every portion of a full cooling channel MOM Report-Coney

  17. Infrastructure: Access, DB, & Data Analysis • New ssh bastion is working • Successfully connected through from outside to computers in the MLCR • X-forwarding is working • Two areas of disk space are set up on PPD cluster for MICE • G4MICE will be installed and available on the PPD system • Database • Configuration Database is installed on new database server & web services server at RAL • Database interface is visible from control room • EPICs client now in place to read/write values set in a run • Tested EPICs client with database – successful • NEXT: run in parallel with spreadsheet during Machine Physics runs • Monitoring • environmental conditions, ISIS loss monitors • AC units, magnet PS water flow MOM Report-Coney

  18. Computing Infrastructure SSH Bastion Micenet / MLCR Outside World SSH ssh EPICS EPICS Gateway Config Database DB DB API “Web” services PPD-Grid managed DB API eLog EPICS archiver web interface Spare node SSH / web services Grid Transfer Box MICE managed Grid clients PPD-IT supervised Analysis Node/Farm SSH ssh + analysis code 18 MOM Report-Coney

  19. Data-taking Run: 12 hours MOM & BLOC MOM & BLOC shifter1 shifter2 Next: Finish Step I • Moving into Intense data-taking period to finish Step I before long shutdown • Production Running - User Run in June/July/August: • Run 5 days/week – M-F • 10-12 hours/day (8am-8pm) • Personnel needed: MOM, BeamLine Expert, Shift Leader, Shifter • Shift leader has more experience and trains up new person • Novices need 1 week training shifts before official shifter • Experts/those doing the study are also there to guide & monitor progress MOM Report-Coney

  20. June/July/August Run • Developing Global Run Plan: • User Run JUNE 22-AUGUST 12 • Machine Physics Aug 13-15 • SHUTDOWN August 16 – January 30, 2011 • Machine Physics studies • Activation Study at 4V beam loss • Beam Loss vs Rate • Beam Bump Study • User Run • Week1: Tues June 22-Fri June25 • 3 days TOF calibration • 1 day KL data • Week2: June 28-July 2: Emittance/Momentum matrix with muon beams • Week3 g more emittance/momentum matrix data MOM Report-Coney

  21. Fill in e-p matrix data P (MeV/c) • finding the element (3,240) means to find the BL optics that matches the MICE optics for a beam of 3 mm rad at a P=240 MeV/c 3,140 3,200 3,240 6,140 6,200 6,240 eN (mm rad) • the element (10,200) is the BL optics matching a MICE beam with 10 mm rad at P=200 MeV/c 10,140 10,200 10,240 This pair is our goal: how do we get it? 24/3/2010 CM26 - Riverside CM26 - Riverside 21 21 (*) 700mV ~ 20 mu-/spill

  22. m Conclusions • Beamline is (mostly) working! – negative or positive particles • New target operating smoothly - Systematic monitoring of performance • Decay Solenoid needed for operation – factor 5 increase muon rate • Major increase in loss limits 50 mV (2008) g 1V (2009/10) g 2V? soon • DAQ increase in efficiency: <50 particles/spill (2008) g ≤ 200 part/spill (2009) • Beam loss vs particle rate shows linear dependence • Detectors are working! • TOF0, TOF1, TOF2 calibrated • Need more data for KL but progressing • Tracker works – nearing dual-readout stage • Muon beam physics happening again soon! • Initial measurement of muon beam emittance • More (e,P) matrix data in June/July/Aug MOM Report-Coney

  23. MOM Report-Coney

  24. Extra! Extra! m- m- m- m- m- m- m- m- m- m- m- m- m- m- m- m- m- m- m- m- m- m- m- m- m- m- m- m- m- Muon Beam Studies at MICE! Extra! Extra! • The MICE experiment takes 17000 target pulses of muon beam data! • ~170,000 m at TOF1 • Muon beam e studies begin! Blimey! Muons! Worldwide celebrations ensue! Locals in Britain express strong support for the experiment 35 MOM Report-Coney

  25. Detector Commissioning: Cherenkovs • Two aerogel Cherenkov counters • Installed downstream of Q6 and TOF0 • Used to separate e/m/p 220-350 MeV/c • e/m/p calibration data taken • Sample electron data shown 26 MOM Report-Coney

  26. Run Summary • May 27-28: 10,700 target pulses • Target count is at 233,750 • 300 MeV/c e+ beam TOF calibration – TOF0 trigger • Th/Fri – 6,4000 pulses with ~45 particle triggers/spill • Muon beam: 6-200 point on emittance-momentum matrix – TOF1 trigger • Fri – 1250 pulses ~6 particle triggers/spill • Muon beam: 10-200 point on emittance-momentum matrix – TOF1 trigger • Fri – 1000 pulses ~6 particle triggers/spill • Muon beam: 3-200 point on emittance-momentum matrix – TOF1 trigger • Fri – 1000 pulses ~4 particle triggers/spill MOM Report-Coney

More Related