1 / 40

Project management

Project management. Organising, planning and scheduling software projects Objectives To introduce software project management and to describe its distinctive characteristics To discuss project planning and the planning process

Télécharger la présentation

Project management

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Project management • Organising, planning and scheduling software projects • Objectives • To introduce software project management and to describe its distinctive characteristics • To discuss project planning and the planning process • To show how graphical schedule representations are used by project management • To discuss the notion of risks and the risk management process

  2. Terminology • Milestones • Have a duration of zero • Identify critical points in your schedule • Shown as inverted triangle or a diamond • Often used at “review” or “delivery” times • Or at end or beginning of phases • Ex: Software Requirements Review (SRR) • Ex: User Sign-off • Can be tied to contract terms

  3. Terminology Example Milestones

  4. Waterfall Model: Analysis Phase I1:Open A.I1:Open I2:Open I3:Open A.I2:Open SD.I1:Open Analysis Analysis SD.I3:Open SD.I2:Open

  5. Waterfall Model: Design Phase I1:Closed A.I1:Open I2:Closed I3:Open A.I2:Open SD.I1:Open Analysis Analysis SD.I3:Open SD.I2:Open Design

  6. Waterfall Model: Implementation Phase I1:Closed A.I1:Closed I2:Closed I3:Closed A.I2:Closed SD.I1:Open Analysis SD.I3:Open SD.I2:Open Design Implementation

  7. Waterfall Model: Project is Done I1:Closed A.I1:Closed I2:Closed I3:Closed A.I2:Closed SD.I1:Open Analysis SD.I3:Open SD.I2:Open Design Implementation

  8. Issue-Based Model: Analysis Phase I1:Open A.I1:Open I2:Open I3:Open A.I2:Open Analysis:80% SD.I1:Open SD.I3:Open SD.I2:Open Design: 10% Implemen-tation: 10%

  9. Issue-Based Model: Design Phase I1:Closed A.I1:Open I2:Closed I3:Open A.I2:Open Analysis:40% SD.I1:Open SD.I3:Open SD.I2:Open Design: 60% Implemen-tation: 0%

  10. Issue-Based Model: Implementation Phase I1:Open A.I1:Open I2:Closed I3:Closed A.I2:Closed Analysis:10% SD.I1:Open SD.I3:Open SD.I2:Cosed Design: 10% Implemen-tation: 60%

  11. Issue-Based Model: Project is Done I1:Closed A.I1:Closed I2:Closed I3:Closed A.I2:Closed Analysis:0% SD.I1:Closed SD.I3:Closed SD.I2:Closed Design: 0% Implemen-tation: 0%

  12. Software project management • Concerned with activities involved in ensuring that software is delivered • on time • within the budget • in accordance with the requirements • Project management is needed because software development is always subject to budget and schedule constraints • Set by the development organisation or the customer

  13. Project staffing • May not be possible to appoint the ideal people to work on a project • Managers have to work within these constraints • especially when (as is currently the case) there is an international shortage of skilled IT staff

  14. Project planning • Probably the most time-consuming project management activity • Continuous activity from initial concept through to system delivery • Plans must be regularly revised as new information becomes available • Beware of grumbling developers • Various different types of plan may be developed to support the main software project plan that is concerned with schedule and budget

  15. Types of project plan

  16. Activity organization • Activities in a project should be organised to produce tangible outputs for management to judge progress • Milestones are the end-point of a process activity • Deliverables are project results delivered to customers

  17. Project scheduling • Split project into tasks and estimate time and resources required to complete each task • Organize tasks concurrently to make optimal use of workforce • Minimize task dependencies to avoid delays caused by one task waiting for another to complete • Dependent on project managers’ intuition and experience

  18. Task durations and dependencies

  19. Activity timeline – Gantt chart

  20. MS-Project Example

  21. Staff allocation

  22. Software risks

  23. PERT • Program Evaluation and Review Technique • Based on idea that estimates are uncertain • Therefore uses duration ranges • And the probability of falling to a given range • Uses an “expected value” (or weighted average) to determine durations • Use the following methods to calculate the expected durations, then use as input to your network diagram

  24. PERT • Start with 3 estimates • Optimistic • Would likely occur 1 time in 20 • Most likely • Modal value of the distribution • Pessimistic • Would be exceeded only one time in 20

  25. PERT Formula • Combined to estimate a task duration

  26. PERT Formula • Confidence Interval can be determined • Based on a standard deviation of the expected time • Using a bell curve (normal distribution) • For the whole critical path use

  27. PERT Example • Confidence interval for P2 is 4 times wider than P1 for a given probability • Ex: 68% probability of 9.7 to 11.7 days (P1) vs. 9.5-13.5 days (P2)

  28. PERT • Advantages • Accounts for uncertainty • Disadvantages • Time and labor intensive • Assumption of unlimited resources is big issue • Lack of functional ownership of estimates • Mostly only used on large, complex project • Get PERT software to calculate it for you

  29. The risk management process • Risk identification – Identify project, product and business risks • Risk analysis – Assess the likelihood and consequences of risks • Risk planning – Draw up plans to avoid/minimise risk effects • Risk monitoring – Monitor the risks throughout the project

  30. Risk identification • Technology risks • People risks • Organisational risks • Requirements risks • Estimation risks

  31. Risks and risk types

  32. Risk analysis • Assess probability and seriousness of each risk • Probability may be • very low • low • moderate • high • very high • Risk effects might be • catastrophic • serious • tolerable • insignificant

  33. Risk analysis

  34. Risk planning • Consider each risk and develop a strategy to manage that risk • Avoidance strategies • The probability that the risk will arise is reduced • Minimisation strategies • The impact of the risk on the project or product will be reduced • Contingency plans • If the risk arises, contingency plans are plans to deal with that risk

  35. Risk planning strategies

  36. Risk factors

More Related