1 / 17

Inv e nergy

Inv e nergy. The Power of Innovation. Discussion Outline. Introduction to Invenergy Wind generation development 101 The impact of HB 1871 – The Illinois state RPS. Invenergy Wind Overview. Operational Projects. Contracted Projects. Invenergy Offices. Invenergy Midwest Portfolio.

chloe-bush
Télécharger la présentation

Inv e nergy

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Invenergy The Power of Innovation

  2. Discussion Outline • Introduction to Invenergy • Wind generation development 101 • The impact of HB 1871 – The Illinois state RPS

  3. Invenergy Wind Overview Operational Projects Contracted Projects Invenergy Offices

  4. Invenergy Midwest Portfolio Forward Location: WI Size: 200 MW COD: 2007 Interconnection: ATC Grand Ridge Location: IL Size: 350 MW COD: Mid 2008 Interconnection: PJM Nelson CC Location: IL Size: 600MW COD: Mid 2009 Interconnection: PJM Bishop Hill Locations: IL Size: 400 MW COD: Late 2008 Interconnection: PJM/MISO White Oak Location: IL Size: 150 MW COD: Late 2007 Interconnections: MISO Victory Location: IA Size: 99 MW COD: December 2006 Interconnection: MidAm Wind Project Gas-Fired Project Wind Project Gas-Fired Project

  5. Wind Wind turbines Land Interconnection agreement A market for the energy A market for the renewable energy credits Wind Development 101

  6. Wind Intensity in the U.S.

  7. Wind Turbines • How big are they? • Tower - 80 meters (about 25 stories) at the hub • Blades – 38 meters (about 100 feet) long • How are they put together • Concrete footing poured • Three tower pieces assembled in place • Three blades attached to the hub and lifted into place • How fast do they turn? • 16 RPM (one rotation every four seconds)

  8. Wind farms and agriculture are very compatible Wind farms require from 50 – 100 acres per turbine, with a typical wind farm comprising of 100 turbines When completed, each turbine only removes 0.25 acres from production Hosting a wind farm greatly benefits the community Tax base increased by ~ $2.5 MM per turbine Affected landowners receive compensation through easement and waiver agreements Land Use

  9. Interconnection Agreement • The interconnection agreement allows for the generator to interconnect to the electric transmission system • This process is one of the most time consuming steps of the development process: • In recent experience, neither PJM nor MISO has been able to adhere to these timelines

  10. Marketing the Energy and RECs • How wind energy and RECs are sold varies by market • In less actively traded markets, energy and RECs are sold under long term contracts to load serving utilities • Contracts typically 20 – 25 years long • Pricing fixed for the term • Common in CO and WI • In more actively traded markets, energy and RECs are often sold separately • Energy sold into power pool • Energy price risk managed through commodity risk managers, typically for 10 years • RECs sold to load serving entities • Common in TX and PJM

  11. Impact of HB 1871 • On May 3rd, the IL House passed a bill providing for a renewable portfolio standard (RPS) for IL • Sets a requirement that 25% of IL’s energy requirements are met by renewables by 2025, with implementation beginning in 2007 • Requires in state generation through 2011 • Protects ratepayers through caps on rate impacts • Clear ratemaking requirements will be critical to its implementation • Provides for 20 year power purchase agreements • Provides for the Commission to review and approve solicitation processes

  12. U.S. Renewable Portfolio Standards MN: 25% by 2025; (Xcel: 30% by 2020) VT: RE meets load growth by 2012 ME: 30% by 2000; 10% by 2017 goal - new RE *WA: 15% by 2020 WI: requirement varies by utility; 10% by 2015 goal MT: 15% by 2015 MA: 4% by 2009 + 1% annual increase RI: 15% by 2020 CT: 10% by 2010 IA: 105 MW CA: 20% by 2010 • NY: 24% by 2013 • CO: 20% by 2020 (IOUs) *10% by 2020 (co-ops & large munis) • NJ: 22.5% by 2021 IL: 8% by 2013 • NV: 20% by 2015 • PA: 18%¹ by 2020 *MD: 7.5% by 2019 *NM: 20% by 2020 (IOUs) 10% by 2020 (co-ops) • AZ: 15% by 2025 *DE: 10% by 2019 • DC: 11% by 2022 Solar water heating TX: 5,880 MW by 2015 HI: 20% by 2020 State RPS State Goal • Minimum solar or customer-sited requirement * Increased credit for solar or customer-sited • ¹PA: 8% Tier I / 10% Tier II (includes non-renewables); SWH is a Tier II resource

  13. Comparison on State RPSs

  14. Meeting the IL RPS through Wind

  15. Proposed IL Wind Projects Source - AWEA

  16. Summary • Wind energy can contribute significantly to serving Illinois’ energy supply needs going forward • HR 1871 sets a high, but attainable, goal for renewables in IL, and wind will play a leading role in meeting it • In order to meet that goal, developers, ISO’s, landowners, utilities, and those that oversee them will have to work together

  17. Questions?

More Related