An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Draft Report of the RHIC Planning Group T. Ludlam Open Meeting on RHIC Planning Dec. 3-4, 2003

  2. RHIC Planning Group: Goal/Charge Map the broad scientific priorities of the RHIC community onto a realistic schedule for facility operations and upgrades. • Starting points… • Beam Use Requests and Decadal Plans • PAC and Detector Adv. Comm. Recommendations • Requirements for machine operation and evolution • DOE Budget Guidance • NSAC Long Range Planning process • Optimize ops scenarios • Establish the scope and spec.s for RHIC II • Update plans for eRHIC 5 Year Plan 20 Year Outlook Input to BNL plan for DOE Review, 12/31/03

  3. RHIC Planning Group Convenors: T. Kirk, T. Ludlam Ex Officio: S. Aronson, D. Lowenstein, P. Paul

  4. Some planning mileposts… Near-term beam use plans Extended Beam Use planning Start eRHIC Constr. New NSAC LRP START RHIC II Constr. First LHC data RHIC II CD-0 New NSAC LRP

  5. Section I: Overview Page 1

  6. Section II: Near-term planning Page 2

  7. C-A guidance for machine performance Page 2

  8. From the Collider Projections document

  9. Table of minimal 5-year goals Page 2 Page 3

  10. Not included in table 1…. Page 3

  11. Summary of Beam Use Proposals 27 weeks/yr

  12. Alternative ops scenarios, averaging 27 wk/yr Page 4

  13. 5-week addition to Constant Effort scenario Page 4 Page 5

  14. Constant-effort budget table

  15. Near-term priorities under a constant-effort budget Page 6-7

  16. Section III: Near term upgrades Page 7

  17. Near-Term Upgrades PHENIX Si Tracker: $6M + Japanese contrib $3M STAR Time of Flight: $5M + Chinese contrib $2M EBIS Ion Source: $17.5M

  18. Sec. IV: Mid term outlook - RHIC II Page 9

  19. RHIC II Scope Page 10

  20. RHIC II and LHC Page 10

  21. Sec. V: Long Term outlook - eRHIC Page 11

  22. eRHIC scope, cost, schedule Page 12

  23. eRHIC parameters

  24. DOE Office of Science 20-year “Roadmap” RHIC II eRHIC

  25. FY06 FY07 Constant Effort FY04 FY05 FY09 FY08 Run Scenario ON DJ F MA MJ J AS ON DJ F MA MJ J AS ON DJ F MA MJ J AS ON DJ F MA MJ J AS ON DJ F MA MJ J AS ON DJ F MA MJ J AS Alternative RHIC Run Scenarios Under Discussion 5+9 Si+ Si 200;5+5 pp 200 5+14 Au+ Au 200;5+0 pp 200 Install Si tracker 5+19 Au+Au 62.4 5+19 Au+Au 200 85 prod. Wks., but no long pp until 2007 Cold AGS Snake + ~1/2 RHIC NEG pipes 5+19 pp 200 PHENIX 27-WEEK Comp-lete RHIC NEG pipes 5+14 Au+ Au 200;5+0 pp 200 5+9 Au Escan or Cu;5+5 pp 200 5+9 d+Au 200;5+5 pp 200 5+5 Au+ Au 200;5+9 pp 200 5+10 Au+ Au 200;5+5 pp 500 71 prod. Wks., pp every year, but no long runs Install TOF barrel STAR 27-WEEK 5+14 Au+ Au 200;5+0 pp 200 91 prod. Wks., 2 longish pp runs post-improvem’ts 5+9 Si+Si 200; 5+17 Au+Au 62.4; 5+10 pp 200 PHENIX STRAWMAN* 54-WEEK Install Si tracker??? 5+24 Au+Au 200; 5+17 pp 200 Cold AGS Snake + all RHIC NEG pipes 5+14 Au+ Au 200;5+0 pp 200 STAR STRAWMAN* 54-WEEK 5+9 Cu+Cu 200; 7+13 Au+Au low-E; 5+12 pp 200 84 prod. Wks., 2 longish pp runs post-improvem’ts 5+9 d+Au 200; 5+14 Au+Au 200; 5+13 pp 200 Install TOF barrel??? comp-lete TOF barrel Cold AGS Snake + all RHIC NEG pipes 5+14 Au+ Au 200;5+0 pp 200 STAR STRAWMAN*~36-WEEK 82 prod. Wks., 2 longish pp runs post-improvem’ts 5+15 Au+Au 200; 5+8 d+Au 200 20% TOF barrel 6+11 Au+Au low-E; 5+12 pp 200 5+8 Cu+Cu 200; 5+14 pp 200 Cold AGS Snake + all RHIC NEG pipes?? 85 prod. Wks., 2 longish pp runs post-improvem’ts, no summer runs 5+14 Au+ Au 200;5+0 pp 200 PHENIX STRAWMAN* SHORT/LONG Install Si tracker 5+14 Au+Au 62.4; 5+9 Si+Si 200 5+24 Au+Au 200 5+10 pp 200 5+14 pp 200 Cold Snake + ~1/2 NEG pipes 89 prod. Wks., 2 longish pp runs, E scan, 1 species, no summer runs comp-lete TOF barrel 5+10 AuAu 200; 5+9 Cu+Cu 200 5+14 Au+ Au 200;5+0 pp 200 5+10Au+ Au 200;5+9 pp 500 STAR STRAWMAN for 32 wks/yr 5+8 d+Au 200; 5+11 pp 200 5% TOF barrel 6+8 Au+Au low-E; 5+10 pp 200 Install Si tracker * N.B. Strawman scenarios are illustrative only, not proposed BUR’s approved by the collaborations.