1 / 134

IE 514 Production Scheduling

IE 514 Production Scheduling. Introduction. Contact Information. Siggi Olafsson 3018 Black Engineering 294-8908 olafsson@iastate.edu http://www.public.iastate.edu/~olafsson OH: MW 10:30-12:00. Administration (Syllabus). Text Prerequisites Assignments Homework 35% Project 40%

Télécharger la présentation

IE 514 Production Scheduling

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. IE 514 Production Scheduling Introduction IE 514

  2. Contact Information • Siggi Olafsson • 3018 Black Engineering • 294-8908 • olafsson@iastate.edu • http://www.public.iastate.edu/~olafsson • OH: MW 10:30-12:00 IE 514

  3. Administration (Syllabus) • Text • Prerequisites • Assignments • Homework 35% • Project 40% • Final Exam 35% • Computing IE 514

  4. What is Scheduling About? • Applied operations research • Models • Algorithms • Solution using computers • Implement algorithms • Draw on common databases • Integration with other systems IE 514

  5. Application Areas • Procurement and production • Transportation and distribution • Information processing and communications IE 514

  6. Manufacturing Scheduling • Short product life-cycles • Quick-response manufacturing • Manufacture-to-order • More complex operations must be scheduled in shorter amount of time with less room for errors! IE 514

  7. Scope of Course • Levels of planning and scheduling • Long-range planning (several years), • middle-range planning (1-2 years), • short-range planning (few months), • scheduling (few weeks), and • reactive scheduling (now) • These functions are now often integrated IE 514

  8. Scheduling Systems • Enterprise Resource Planning (ERP) • Common for larger businesses • Materials Requirement Planning (MRP) • Very common for manufacturing companies • Advanced Planning and Scheduling (APS) • Most recent trend • Considered “advanced feature” of ERP IE 514

  9. Scheduling Problem • Allocate scarce resources to tasks • Combinatorial optimization problem Maximize profit Subject to constraints • Mathematical techniques and heuristics IE 514

  10. Our Approach Scheduling Problem Problem Formulation Model Solve with Computer Algorithms Conclusions IE 514

  11. Scheduling Models • Project scheduling • Job shop scheduling • Flexible assembly systems • Lot sizing and scheduling • Interval scheduling, reservation, timetabling • Workforce scheduling IE 514

  12. General Solution Techniques • Mathematical programming • Linear, non-linear, and integer programming • Enumerative methods • Branch-and-bound • Beam search • Local search • Simulated annealing/genetic algorithms/tabu search/neural networks. IE 514

  13. Scheduling System Design Order master file Shop floor data collection • Databases • Schedule generation • User interfaces Database Management Automatic Schedule Generator Performance Evaluation Schedule Editor Graphical Interface User IE 514

  14. LEKIN • On disk with book • Generic job shop scheduling system • User friendly windows environment • C++ object oriented design • Can add own routines IE 514

  15. Advanced Topics • Uncertainty, robustness, and reactive scheduling • Multiple objectives • Internet scheduling IE 514

  16. Topic 1 Setting up the Scheduling Problem IE 514

  17. Modeling • Three components to any model: • Decision variables • This is what we can change to affect the system, that is, the variables we can decide upon • Objective function • E.g, cost to be minimized, quality measure to be maximized • Constraints • Which values the decision variables can be set to IE 514

  18. Decision “Variables” • Three basic types of solutions: • A sequence: a permutation of the jobs • A schedule: allocation of the jobs in a more complicated setting of the environment • A scheduling policy: determines the next job given the current state of the system IE 514

  19. Model Characteristics • Multiple factors: • Number of machine and resources, • configuration and layout, • level of automation, etc. • Our terminology: Resource = machine (m) Entity requiring the resource = job (n) IE 514

  20. Notation • Static data: • Processing time (pij) • Release date (rj) • Due date (dj) • Weight (wj) • Dynamic data: • Completion time (Cij) IE 514

  21. Machine Configuration • Standard machine configurations: • Single machine models • Parallel machine models • Flow shop models • Job shop models • Real world always more complicated. IE 514

  22. Constraints • Precedence constraints • Routing constraints • Material-handling constraints • Storage/waiting constraints • Machine eligibility • Tooling/resource constraints • Personnel scheduling constraints IE 514

  23. Other Characteristics • Sequence dependent setup • Preemptions • preemptive resume • preemptive repeat • Make-to-stock versus make-to-order IE 514

  24. Objectives and Performance Measures • Throughput (TP) and makespan (Cmax) • Due date related objectives • Work-in-process (WIP), lead time (response time), finished inventory • Others IE 514

  25. Throughput and Makespan • Throughput • Defined by bottleneck machines • Makespan • Minimizing makespan tends to maximize throughput and balance load IE 514

  26. Due Date Related Objectives • Lateness • Minimize maximum lateness (Lmax) • Tardiness • Minimize the weighted tardiness IE 514

  27. Due Date Penalties Tardiness Lateness Late or Not In practice IE 514

  28. WIP and Lead Time • Work-in-Process (WIP) inventory cost • Minimizing WIP also minimizes average lead time (throughput time) • Minimizing lead time tends to minimize the average number of jobs in system • Equivalently, we can minimize sum of the completion times: IE 514

  29. Other Costs • Setup cost • Personnel cost • Robustness • Finished goods inventory cost IE 514

  30. Topic 2 Solving Scheduling Problems IE 514

  31. Classic Scheduling Theory • Look at a specific machine environment with a specific objective • Analyze to prove an optimal policy or to show that no simple optimal policy exists • Thousands of problems have been studied in detail with mathematical proofs! IE 514

  32. Example: single machine • Lets say we have • Single machine (1), where • the total weighted completion time should be minimized (SwjCj) • We denote this problem as IE 514

  33. Optimal Solution • Theorem: Weighted Shortest Processing time first - called the WSPT rule - is optimal for • Note: The SPT rule starts with the job that has the shortest processing time, moves on the job with the second shortest processing time, etc. IE 514

  34. Proof (by contradiction) • Suppose it is not true and schedule S is optimal • Then there are two adjacent jobs, say job j followed by job k such that • Do a pairwise interchange to get schedule S ’ j k k j IE 514

  35. Proof (continued) The weighted completion time of the two jobs under S is The weighted completion time of the two jobs under S ‘ is Now: Contradicting that S is optimal. IE 514

  36. Complexity Theory • Classic scheduling theory draws heavily on complexity theory • The complexity of an algorithm is its running time in terms of the input parameters (e.g., number of jobs and number of machines) • Big-Oh notation, e.g., O(n2m) IE 514

  37. Polynomial versus NP-Hard IE 514

  38. Scheduling in Practice • Practical scheduling problems cannot be solved this easily! • Need: • Heuristic algorithms • Knowledge-based systems • Integration with other enterprise functions • However, classic scheduling results are useful as a building block IE 514

  39. General Purpose Scheduling Procedures • Some scheduling problems are easy • Simple priority rules • Complexity: polynomial time • However, most scheduling problems are hard • Complexity: NP-hard, strongly NP-hard • Finding an optimal solution is infeasible in practice  heuristic methods IE 514

  40. Types of Heuristics • Simple Dispatching Rules • Composite Dispatching Rules • Branch and Bound • Beam Search • Simulated Annealing • Tabu Search • Genetic Algorithms Construction Methods Improvement Methods IE 514

  41. Topic 3 Dispatching Rules IE 514

  42. Dispatching Rules • Prioritize all waiting jobs • job attributes • machine attributes • current time • Whenever a machine becomes free: select the job with the highest priority • Static or dynamic IE 514

  43. Release/Due Date Related • Earliest release date first (ERD) rule • variance in throughput times • Earliest due date first (EDD) rule • maximum lateness • Minimum slack first (MS) rule • maximum lateness Current Time Processing Time Deadline IE 514

  44. Processing Time Related • Longest Processing Time first (LPT) rule • balance load on parallel machines • makespan • Shortest Processing Time first (SPT) rule • sum of completion times • WIP • Weighted Shortest Processing Time first (WSPT) rule IE 514

  45. Processing Time Related • Critical Path (CP) rule • precedence constraints • makespan • Largest Number of Successors (LNS) rule • precedence constraints • makespan IE 514

  46. Other Dispatching Rules • Service in Random Order (SIRO) rule • Shortest Setup Time first (SST) rule • makespan and throughput • Least Flexible Job first (LFJ) rule • makespan and throughput • Shortest Queue at the Next Operation (SQNO) rule • machine idleness IE 514

  47. Discussion • Very simple to implement • Optimal for special cases • Only focus on one objective • Limited use in practice • Combine several dispatching rules Composite Dispatching Rules IE 514

  48. Example Single Machine with Weighted Total Tardiness IE 514

  49. Setup • Problem: • No efficient algorithm (NP-Hard) • Branch and bound can only solve very small problems (<30 jobs) • Are there any special cases we can solve? IE 514

  50. Case 1: Tight Deadlines • Assume dj=0 • Then • We know that WSPT is optimal for this problem! IE 514

More Related