1 / 91

Design and construction of a reinforced soil embankment on soft soil

Design and construction of a reinforced soil embankment on soft soil. Russell Jones, Golder Associates Gareth Swift, University of Salford. Overview. Background Site details Design philosophy Design issues Construction issues Conclusions. Background. Introduction

cmapes
Télécharger la présentation

Design and construction of a reinforced soil embankment on soft soil

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Design and construction of a reinforced soil embankment on soft soil Russell Jones, Golder Associates Gareth Swift, University of Salford

  2. Overview • Background • Site details • Design philosophy • Design issues • Construction issues • Conclusions

  3. Background • Introduction • Site is located south of Basildon in Essex • Bounded by: • Wat Tyler country park on western boundary • Pitsea Marshes (SSSI) along the northern boundary • East Haven Creek along southern boundary (Thames beyond)

  4. Background • Introduction Covers an area of approx. 284ha (>50ha currently operational)

  5. Background • Introduction • Paper and presentation deals with design and construction issues relating to a large leachate lagoon to be constructed on soft, compressible soils • Design carried out in June 2002 • Construction between July 2002 and January 2003 • Lagoon filled to capacity March 2008 • Final Certificate issued by the Panel Engineer July 2008

  6. Background • Client brief: • Minimum leachate capacity of 150,000m3 • Maximum cost of build £1.3 million • Maximum bund height 8mAOD (planning constraint) • ……needs to be buildable!

  7. Background • Additional design constraints: • Ensure stability • Minimise soil imports • Maximise lagoon area (hence, minimise bund height) • Minimise excavation into existing soils

  8. Background • Additionally… • Satisfy requirements of Reservoir Act 1975 • the Act applies to Large Raised Reservoirs,defined as: ‘being designed to hold or capable of holding more than 25,000m3 of water as such above the natural level of any part of the land adjoining the reservoir (including the bed of any stream)’

  9. Overview • Background • Site details • Design philosophy • Design issues • Construction issues • Conclusions

  10. Site Details • Ground conditions • The area is relatively even but groundwater levels close to, or at, the ground surface • Waste dating from the 1950’s underlies the site in a layer between 1m and 7m thick • Waste comprises ash, clinker, glass, cans in hydraulic continuity with the surrounding landfill • This overlies a generally soft stratum of alluvial clays and sands (mv 0.2 – 0.8m2/kN).

  11. Site Details • Ground conditions • A similar, but earlier, lagoon encountered significant difficulties during construction associated with the high groundwater levels and the trafficability of the waste and the soft alluvial material.

  12. Site Details • Ground conditions

  13. Overview • Background • Site details • Design philosophy • Design issues • Construction issues • Conclusions

  14. Design Philosophy • Original design philosophy • Reducing the existing ground level of approximately 3 m AOD to a minimum formation level of 1.0 m AOD • Pumping and dewatering required (estimated quantity 20,000m3 to 75,000m3) • Forming embankment slopes of 1v:4h utilising the excavated waste • Using a single ethylene inter-polymer alloy geomembrane liner on both the base and embankment slopes • Liner manufactured to a specific prefabricated size and shape to suit the design

  15. Design Philosophy • Original design philosophy

  16. Design Philosophy • Original design philosophy

  17. Design Philosophy • Original design philosophy

  18. Design Philosophy • Original design philosophy • Ground conditions are poor at best: • Groundwater/leachate levels at or near to the ground surface; and • Material to be excavated to produce a formation level comprised 1950’s waste of questionable engineering integrity • Dewatering logistically difficult due to up-gradient landfill (with leachate) • Single geomembrane liner not the most effective barrier • Tenderers’ comments

  19. Design Philosophy • Proposed design • No excavation • Reinforced basal platform 20 m wide by 700 mm thick constructed at the existing ground level • Steeper face angles • Reinforced soil perimeter embankment, 5.5 m high • External side slopes 1v:2h • Internal side slopes 1v:1v

  20. Design Philosophy • Original design philosophy

  21. Design Philosophy • Proposed design

  22. Design Philosophy • Proposed design

  23. Design Philosophy • Proposed design • Base area of approximately 32,000 m2 lined with a composite lining system • 2 mm thick Linear Low Density Polyethylene (LLDPE) sheet • Geosynthetic clay liner (GCL) • Underdrainage geocomposite drainage layer to limit hydraulic pressures from the groundwater/leachate and gas • Lining of the perimeter embankment with • 2 mm thick LLDPE geomembrane • Geocomposite drainage layer connected to a piped drainage system

  24. Design Philosophy • Proposed design

  25. Overview • Background • Site details • Design philosophy • Design issues • Construction issues • Conclusions

  26. Design Issues • Proposed design • Since material was limited to on-site sources, the quality would be variable • Side slopes would be steep in order to achieve capacity • Geosynthetic reinforcement, geotextile rather than geogrid to aid dissipation of pore pressures • Primary geotextile reinforcement • Secondary geogrid reinforcement • Granular material used for foundation layer • Cohesive material used for most of embankment but granular material used for upper section

  27. Design Issues • Proposed design

  28. Design Issues • Proposed design

  29. Design Issues • Reinforcement details

  30. Design Issues • Settlement • Final top of embankment = 7.5m AOD • Constructed to = 8m AOD due to anticipated settlement

  31. Design Issues • Material parameters

  32. Design Issues • Value Engineering • Time constraints • Design optimisation during construction • Supported by field trials where possible • ECC form of contract

  33. Design Issues • Value Engineering • NEC/Engineering and Construction Contract • Six Main Options • Option A - Priced with Activity Schedule • Option B - Priced with BQ • Option C - Target with Activity Schedule • Option D - Target with BQ • Option E - Cost Reimbursement • Option F - Management Contract

  34. Design Issues • Contract • NEC/Engineering and Construction Contract • Six Main Options • Option A - Priced with Activity Schedule • Option B - Priced with BQ • Option C - Target with Activity Schedule • Option D - Target with BQ • Option E - Cost Reimbursement • Option F - Management Contract

  35. Design Issues • Stability • A key factor in the design of the perimeter embankments is their stability • Internal – Inside face and outside face • External – Global failure and siding • Major issue is the development of pore water pressure in the sub-grade due to embankment construction • Slope/w and Seep/w used to examine the effects of pore water pressure on stability • Results indicate that the rate of build up and dissipation was critical to stability

  36. Design Issues • Stability • Piezometers used on site to monitor pore water pressures • Construction of toe berms would improve short term stability • Factor of safety >1.3 if ru <0.7 • Toe berms allow increase in ru to 0.8

  37. Design Issues • Stability

  38. Design Issues • Stability • 700mm thick reinforced foundation layer: • 300mm drainage layer • 400mm stability layer

  39. Design Issues • Stability • Typical output:

  40. Design Issues • Groundwater • Geotextile reinforcement allows dissipation of pore pressures in embankment fill • Geocomposite allows dissipation of pore pressures beneath the lagoon • 75mm crushed concrete layer allows dissipation of pore pressures beneath the embankment

  41. Design Issues • Environmental considerations • Leachate containment • 2mm LLDPE geomembrane • GCL • UV protection geotextile • Under drainage • Complete system required to remove gases beneath lining system • 12mm geocomposite

  42. Overview • Background • Site details • Design philosophy • Design issues • Construction issues • Conclusions

  43. Construction Issues • Construction works • Groundwater monitoring • Settlement monitoring

  44. Construction Issues • Construction works Poor ground conditions

  45. Construction Issues • Construction works Generally, a flat lying area in a floodplain

  46. Construction Issues • Construction works

  47. Construction Issues • Construction works • Relatively flat formation level (3.0mAOD) required: • Removal of bushes/trees • Re-profiling of hummocky areas • Elevated ground in NE was excavated • Low area in south backfilled • Existing leachate trench backfilled • Dewatering, where required • Installation of piezometers • Construction of cut-off trench

  48. Construction Issues • Construction works

  49. Construction Issues • Construction works • Basal layer • Separator geotextile on existing ground • 9 mm Drainage geocomposite • 300 mm thick drainage layer • Separator geotextile on drainage layer • 400 mm thick stability layer including two layers of geogrid reinforcement

  50. Construction Issues • Construction works Foundation layer, first layer of geogrid

More Related