Long-Term Leachate Management at the Tom Howe Landfill Site. Kaela Roelens Haldimand County. MWA Spring Workshop May 2014. MWA Spring Workshop May 2014. Background Owned by Haldimand County & Norfolk County Location: Part Lots 7&8 Concession 15 Walpole

colman
Télécharger la présentation

Long-Term Leachate Management at the Tom Howe Landfill Site

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Long-Term Leachate Management at the Tom Howe Landfill Site Kaela Roelens Haldimand County MWA Spring Workshop May 2014

  2. MWA Spring Workshop May 2014 Background Owned by Haldimand County & Norfolk County Location: Part Lots 7&8 Concession 15 Walpole Incoming waste from Haldimand County, Norfolk County, & Mississaugas of the New Credit First Nations. Annual waste tonnage ~35,000 tonnes; anticipated closure: December 2015. Current on-site leachate storage: 6 x 57m³ tanks = 342m³. Controlled by SCADA. From 2008-2012 average hauled annual leachate volume: 67,000m³ Leachate Quality – ammonia is the key loading parameter in terms of WWTF impact, ~285 mg/L

  3. MWA Spring Workshop May 2014 Managing Leachate On-Site Need: free up WWTF capacity, reduce hauling/ treatment costs, and accommodate leachate treatment post closure. How? Options - Reduce volume of leachate through evapo-infiltration ponds; spray irrigation; poplar tree plantation Manage peak leachate volumes through additional on-site storage tanks; leachate ponds; hauling schedule On-Site treatment through mechanical/ chemical/ biological system; pre-treatment wetland; treatment lagoon; air stripping; breakpoint chlorination

  4. MWA Spring Workshop May 2014 Preferred Approach The following combination of options are explored for use at Tom Howe: On-site pre-treatment Pre-treatment wetland Pre-treatment aerated lagoon (which may be used in combination with wetland) On-site recirculation/irrigation Other alternatives will not reduce overall hauled leachate volumes, or involve treatment systems requiring significant operator control not appropriate at a closed landfill site.

  5. MWA Spring Workshop May 2014 to WWTF Leachate Pre-Treatment Wetland Sub-surface System: Leachate trickles through a media filter and wetland and is collected in a lagoon Anticipated 50% reduction of influent leachate flow rate Allows for reduction of ammonia loading through biological nitrification

  6. MWA Spring Workshop May 2014 Leachate Pre-Treatment Wetland Design based on: Influent flow of 220m³/day Influent ammonia of 285 mg/L *Effluent ammonia target of 50 mg/L Effluent flow target of ~110m³/day Leachate temperature of 5ºC This would result in a wetland with surface area of 6,300m², 1m depth Preliminary construction cost: $1,280,000 Annual O&M costs: $80,000

  7. MWA Spring Workshop May 2014 Leachate Re-Circulation & Poplar Plantation Leachate re-circulation: re-applying collected leachate to the waste fill areas to reduce volume through evaporation, transpiration and infiltration. Examples include: injection, surface drip application/ irrigation, spray irrigation, surface evapo-infiltration ponds, mix leachate with incoming waste. Leachate percolates through waste which may improve leachate quality overtime by slowly degrading the waste mound. Poplar plantation can be used in combination or alone Alternate cap; intercept leachate plumes; leachate irrigation plantation.

  8. Leachate Re-Circulation & Poplar Plantation Cont’d Poplar trees – 4,000/hectare or 1.5m spacing Long-term leachate production – ~6,000m³/month Residual leachate uptake - 300 L/tree/month # of trees required to manage leachate on-site – 20,000 or 5 hectares of trees Cost to purchase tree & prep ground – ~$120,000 Total Cost of whips and drip irrigation system - $740,000 If combined with pre-treatment wetland, total costs would be reduced to $370,000

  9. Summary Combination of pre-treatment wetland and poplar plantation: TOTAL Construction: $2,140,000 TOTAL Annual O&M: $160,000 Next Steps Pilot project to determine feasibility at Tom Howe

  10. MWA Spring Workshop May 2014 Questions? Kaela Roelens – Waste Mgmt Tech. Haldimand County P: 908-318-5932 Ext. 6222 E: KRoelens@haldimandcounty.on.ca OR Bruce Gall – UEM Consulting E: BGall@UEMconsulting.com