Overall planning, consolidation, stops, time line

This report discusses the 2-year cycle, technical stops, Xmas breaks, and the 2012 shut-down timeline for the Foraz Machine Advisory Committee.

colon
Télécharger la présentation

Overall planning, consolidation, stops, time line

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Overall planning, consolidation, stops, time line K. Foraz MAC – April 27th 2010 K. Foraz - Machine Advisory Committee

  2. Contents • 2 years cycles • Technical stops • Xmas breaks • Shut-down 2012 • LHC • Injector chain • Overall timeline & conclusions K. Foraz - Machine Advisory Committee

  3. 2 years cycle: Global strategy • Operate machines on a 2 year basis • Technical stops to solve N.Cs and anticipate preventive maintenance • Mid-period: Xmas break to perform minimum maintenance activities K. Foraz - Machine Advisory Committee

  4. 2 years cycle: LHC monthly technical stops • 3 days each month: • to anticipate preventive maintenance • started: ventilation, fire, gas, access, sniffer… • to perform minor consolidation works: • Heaters on current leads, QPS • To solve non conformities encountered during operation: • Cryogenics, ventilation, leaks, instrumentation… • 3 days during which ~ 1day is dedicated to RP survey, electrical lock-out and unlock-out • In late summer, we have to analyze if it would be more efficient to increase the periodicity and the length of the technical stops (ex: 1 week each 7 weeks) K. Foraz - Machine Advisory Committee

  5. 2 years cycle: Injectors Technical Stops • Technical stops • 3 days/quarter • Resources shared with LHC !!! • Observation of a rise in the number of faults occurring during operation, which might be attributed to the fact that only the “bare minimum” work was carried out in January, (example: interlocks being activated because drifting values reach the permitted limit levels) • But reliability still high K. Foraz - Machine Advisory Committee

  6. 2 years cycle: Maintenance activities (1/3) • Preventive maintenance activities have been sorted out by priorities • Priority 1 corresponds to the minimum maintenance of the systems linked to legal or security requirements (personal / machine) : Cooling-towers, pumps, ventilation, AUG, UPS, cryogenics, fire-evacuation, ODH, gas. In addition for injectors: magnets replacement, LINAC2 source, PC Siemens (rotating machine) … • Most of these activities can be performed in 4 weeks…but K. Foraz - Machine Advisory Committee

  7. 2 years cycle: Maintenance activities (2/3) Example of duration drivers K. Foraz - Machine Advisory Committee

  8. 2 years cycle: Maintenance activities (3/3) K. Foraz - Machine Advisory Committee

  9. 2 years cycle: Xmas breaks Subject of the Xmas breaks is being studied with 2 options: Availability of the machine during operation versus Xmas break length (mimimummaint.) K. Foraz - Machine Advisory Committee

  10. 2 years cycle - conclusions • Technical stops • N.C. solving, anticipation of preventive maintenance, minor consolidations • LHC: Increase frequency & length or not • Injectors: 3 days/quarter • Xmas breaks – 7/11weeks • Dilemma between risks & length of operation • Resources • Hiradmat project needs 8 weeks  Do not worsen the situation K. Foraz - Machine Advisory Committee

  11. 2012 Shut-down • LHC - Main consolidations to be performed • Interconnections (see talk of Francesco Bertinelli) • R2E (see talk of Roberto Losito) • Collimators (see talk of Ralph Assman) • Injector chain K. Foraz - Machine Advisory Committee

  12. 2012 Shut-down – LHC: Interconnections (1/3) Interconnections Rate = 50 IC/week, 14 wks for 1st sector 5 wks later for 2nd sector From warm-up to powering tests Warm-up Warm-up ELQA @ warm ELQA @ warm ELQA @ cold ELQA @ cold Sector 1 Pressure test - last leak tests - flushing Cool=down Cool=down Pressure test - last leak tests - flushing Powering tests Powering tests ? Sector 2 0 5 10 15 20 25 30 35 0 5 10 15 K. Foraz - Machine Advisory Committee

  13. 2012 Shut-down – LHC : Interconnections (3/3) Taking into account 15% of margin to absorb additional works, delays…, and postponing cool-down in order to ease access and works --- 16 months shut-down 0 5 10 15 20 25 30 35 40 45 50 55 60 65 70 K. Foraz - Machine Advisory Committee

  14. 2012 Shut-down – LHC : Maintenance One entire year is enough for the maintenance  Schedule maintenance as late as possible / remaintain --- 2 years of operation 0 5 10 15 20 25 30 35 40 45 50 55 60 65 70 K. Foraz - Machine Advisory Committee

  15. 2012 Shut-down – LHC : Collimation (1/2) Success oriented: Readiness for installation (point 3) : 2012 Then 13 weeks are needed to close, test, leak test the IC’s afterward Conservative: Installation (point 3) : shut-down 2015 K. Foraz - Machine Advisory Committee

  16. 2012 Shut-down – LHC : Collimation Latest collimator: end of December -> end of the shut-down end of June !! Being ready earlier will have an impact on the end date, because of the interconnection resources. Schedule will be reviewed as soon as a technical solution will be adopted’  Delay the collimation installation in 2014-2015 will certainly increase the length of the 14-15 shut-down (6months) Sector 34 Sector 23 0 5 10 15 20 25 30 35 40 45 50 55 60 65 70 K. Foraz - Machine Advisory Committee

  17. 2012 Shut-down – LHC : R2E At least 9-10 months are available. Shielding at points 1 & 5 and relocation of equipment at point 7 & 8 are being studied. 9-10 months looks OK, but need to check with resources used by other interventions K. Foraz - Machine Advisory Committee

  18. 2012 shut-downs - Injectors • Ususal maintenance activities: • electricity, cooling & ventilation, fire… • Usual shut-down works: • RF, magnets, cables, kickers • Projects (if approved) • Consolidation • PSB @ 2GeV • SPS upgrades (RF,…) K. Foraz - Machine Advisory Committee

  19. 2012 shut-down: conclusions • 16 months shut-down, driven by interconnection works, taking into consideration 15% margin from strict minimum. • Includes interconnections, R2E, maintenance • Collimation: • Latest collimators ready in December – 2 additional months • To be looked at in detail mid 2010 • Maintenance & R2E: OK K. Foraz - Machine Advisory Committee

  20. Overall timeline & Conclusions • Xmas breaks & Technical Stops • Lenght of Xmas break to be decided in July: 7 weeks vs 11 weeks • Dilemma between risks & length of operation • Resources • Hiradmat project - 8 weeks • Injectors: minimal maintenance & minimal tech. Stops =>  number of faults • Shut-down 2012 • LHC = 16 months shut-down • driven by the interconnection project • OK for maintenance & R2E • Re-evaluation after the choice of the technical solution for the collimation project • Injectors = 2 * 4 months LHC Injectorchain 2010 2011 2012 2013 2014 2015 K. Foraz - Machine Advisory Committee