80 likes | 204 Vues
This report summarizes the May 2006 data extraction and variance reporting for competitive retailers. A total of 5 out of 118 competitive retailers submitted their reports by the due date of June 2, 2006. Additionally, only 2 out of 15 competitive retailers that filed Development Issues within 90 days prior to the deadline reported their numbers. The incoming data for July RMS, based on June reports, is expected by July 5, 2006. Key players include AEP, CenterPoint, TXU Electric Delivery, Sharyland, and TNMP.
E N D
June Summary: CR Data Extract Variance Reporting
May CR DEV Reporting • 5 of 118 Competitive Retailers reported numbers by the due date for May Reports (06/02/06). • 2 of 15 Competitive Retailers that filed DEV Issues within the 90 days proceeding the reporting deadline reported numbers. • Numbers for July RMS (June Reports) are due by July 5, 2006.