An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. HPT001.014F Revision 0 Slide 1 of 10 Pressurized Water Reactor

  2. HPT001.014F Revision 0 Slide 2 of 10 Pressurized Water Reactor Flow

  3. HPT001.014F Revision 0 Slide 3 of 10 Primary Cooling Cycle • Reactor – heat from fission is transferred to coolant • Steam Generators (tube side) – hot reactor coolant is circulated through tubes to produce steam • Reactor Coolant Pumps – circulate the coolant through the system

  4. HPT001.014F Revision 0 Slide 4 of 10 Secondary Cooling Cycle • Steam Generators (shell side) – converts water to steam • Turbines – convert steam to mechanical work • Main Condenser – receives exhaust steam • Moisture Separators/Reheaters – remove moisture, reheat steam • Secondary Side Pumps – return the condensed steam to the steam generators

  5. HPT001.014F Revision 0 Slide 5 of 10 Tertiary Loop • Cools and condenses the steam exhausted from the turbines • Transfers heat from the steam to the river

  6. HPT001.014F Revision 0 Slide 6 of 10 PWR Design • Water on primary side is maintained at ~2235 psig to prevent boiling • Primary side water does not come into contact with secondary side water • Steam generator is the component that divides the primary side from the secondary side

  7. HPT001.014F Revision 0 Slide 7 of 10 Plant Layout • Containment Building – contains primary cooling loop, isolates radioactive water from the environment • Auxiliary Building – contains all other potentially radioactive systems • Control Building – houses main control room, cable room, aux. instrument room, computer room, and battery room • Turbine Building – contains secondary system • Additional Equipment Building – ice making equipment

  8. Fuel Cladding Reactor Coolant System Pressure Boundary Containment Vessel HPT001.014F Revision 0 Slide 8 of 10 Fission Product Barriers

  9. HPT001.014F Revision 0 Slide 9 of 10 Containment Structure • Containment consists of a steel containment vessel and separate shield building • Annulus is between the two structures • Design internal pressure is 12 psig • Containment structure is last barrier against fission product release to the environment

  10. HPT001.014F Revision 0 Slide 10 of 10 Modes of Operation • Mode 1, Plant Operation >5% > 350 ºF • Mode 2, Startup < 5% > 350 ºF • Mode 3, Hot Standby 0% > 350 ºF • Mode 4, Hot Shutdown Tavg between 200 ºF and 350 ºF • Mode 5, Cold Shutdown < 200 ºF • Mode 6, Refueling < 140 ºF • No Mode, no fuel in the core