An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. High Potential Incident Date Presented: Thursday 15th April 2010Forum : OGP/IAGC joint global forum – Rio

  2. When What Where • 29th January 2010 • Offshore French Guiana • A crewmember’s left leg became entangled in a loop of rope • A Norwegian buoy was on the outboard end of the rope, which tightened around his leg and pulled him against the deck railing

  3. Incidence Description • Recovering a rope from the sea manually due to a winch failure. • A wave caught the Norwegian buoy on the end, and dragged the rope out for the hands. • During the sudden drag, a loop of rope wrapped around the persons ankle pulling him against the deck railing .

  4. Incidence Description

  5. Immediate Actions • Another crew member was able grab the rope while a third crew member cut the rope. • Left leg treated by medic and crewmember returned to limited duties.

  6. Findings • Inadequate management of change risk assessment prior to task (winch out of operation) • Change in the process of recovering the gun separation rope. • Poor situational awareness of coils of rope (never stand in a loop of rope) • Late in shift approximately 2 hours to shift change (fatigue)

  7. Lessons Learnt • • Dynamic risk assessments (take 5) should be part of standard thought process in back deck operations • Management of Change risk assessment should have been completed since there was a significant change in the process of recovering the equipment. In this case, manually pulling in a rope with a Norwegian buoy on the end trailing in the sea rather than using a winch is a significant change in process brought on by equipment failure/malfunction.