1 / 6

TA1 Gas Section Work

TA1 Gas Section Work. Current Status Future Progress Monitoring. Ongoing work. AICE TPC: Software tests have started. CMS Distribution: We had a problem with some NBR joints -> they were damaged due to “over compression”. The modification is ongoing. Finished by Feb. 04

daire
Télécharger la présentation

TA1 Gas Section Work

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. TA1 Gas Section Work Current Status Future Progress Monitoring

  2. Ongoing work • AICE TPC: • Software tests have started. • CMS Distribution: • We had a problem with some NBR joints -> they were damaged due to “over compression”. The modification is ongoing. Finished by Feb. 04 • RPC Endcap racks will be finished in Dec. • Mixer Construction starting Jan. (+ 1 month) • ATLAS Construction starting March (+ 2 month) • Hold ups in validation of components • Component cleaning with EST is not operational (at earliest March 03) (+ 6 month) • New Lab Bldg 164 finished in Feb 04.

  3. Milestones

  4. Simple Manpower Calculation Note: This estimates accounts only the labor for rack assembly and installation. Engineering and physicist manpower is not included. The remaining 21.2 man-years have to be completed until mid 2006 (in 2.5 years), that means every 6 months we must complete work for the equivalent of ~4.0 man-years. At the moment we are a factor 2 to 3 below, but the manpower will increase over the next months.

  5. Proposal for Progress Monitoring • Collect all the schedule data from the 4 experiments (ongoing) • Define a few system specific milestones for each experiments. • Define some milestones related to the module construction. • Monitor the amount of work completed in periods of 6 months. By March 2004 we can have revised schedule and detailed proposal for the progress reporting.

  6. This Requires some further Clarifications: Reducing the non LHC work to < 1man-year/year. (was 2.5 my’s in 2002, and 1.5my’s in 2003) • User requirements (design Documents) shall be approved documents in EDMS. • Modifications will require “ECR” • Our team must reduce the installation work in the pits to the minimum possible (example: CMS) • Bottlenecks (e.g. cleaning, component validation, mechanical engineering) in the construction must addressed and removed. • QC program put in place.

More Related