CS503: Midterm Information Spring 2014
CS503: Midterm Information Spring 2014. Dongyan Xu Department of Computer Science Purdue University. Date/Time/Location. Thursday, March 13, 2013 8:00PM-9:30PM WTHR 172. Scope. Chapters 1-9 of Xinu book Lecture notes covered in class (up to Thursday, March 6)
CS503: Midterm Information Spring 2014
E N D
Presentation Transcript
CS503: Midterm InformationSpring 2014 Dongyan Xu Department of Computer SciencePurdue University
Date/Time/Location • Thursday, March 13, 2013 • 8:00PM-9:30PM • WTHR 172
Scope • Chapters 1-9 of Xinu book • Lecture notes covered in class (up to Thursday, March 6) • Research papers in reading assignments are NOT covered by the exam
Types of Questions • 10 “True or False” questions • 6 short “Q&A” problems • One problem about process scheduling • One problem about process synchronization and scheduling • One problem about process synchronization (programming using semaphore primitives) • One problem about message passing