1 / 8

CIVL202 Construction Engineering I

CIVL202 Construction Engineering I. Tutorial 4 T1 Mon 11:00 – 11:50 T2 Wed 09:00 – 09:50. Tutorial Outlines. Value Engineering Suspension, Delay or Interruption Liquidated Damages Progress Payments and Retainage Progress Reporting Acceptance and Final Payment. Value Engineering.

Télécharger la présentation

CIVL202 Construction Engineering I

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. CIVL202Construction Engineering I Tutorial 4 T1 Mon 11:00 – 11:50 T2 Wed 09:00 – 09:50

  2. Tutorial Outlines • Value Engineering • Suspension, Delay or Interruption • Liquidated Damages • Progress Payments and Retainage • Progress Reporting • Acceptance and Final Payment

  3. Value Engineering • Encourage the contractor to suggest a cost-saving construction method • Allow the contractor to share a portion of saved cost • DBB contracts, contractor seldom have input to the design process • Weighted evaluation

  4. Suspension, Delay or Interruption • For government contracts, the officer may order the contractor in writing to suspend, delay or interruption for certain period of time • But it may be costly to the contractor • The owner is required to pay an adjustment for unreasonable suspension

  5. Liquidated Damage • The contractor cannot complete the project by a certain point of time, which will lead to non-availability of service of construction • Usually given in supplementary conditions • Amount of LD should reflect the actual amount incurred • If Charges > the actual amount of damage incurred, it acts as a kind of penalty, In this case, the owner have to give bonus to the contractor if the project has been finished earlier than expected

  6. Progress Payments and Retainage • Progress payments: contractor is reimbursed on a periodic basis, usually at the end of each month • Retainage: owner retains a portion of money(say 10%) which acts as an incentive for the contractor to complete the project properly

  7. Progress Reporting • The contractor is required to report the schedule of activity periodically to reflect the actual progress of the project • S-curves and bar charts

  8. Acceptance and Final Payment • Final acceptance is implemented by joint inspection, after which, final payment including retainage will be made • Punch list: which record the deficiencies of the project under joint inspection • Similar procedure between prime contractor and sub-contractors

More Related