An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Water Control Structure L-4 Rehabilitation - Change Order 1Emergency Repair of Unforeseen Condition

  2. Scope of Work • Divert the Belleaire/Royal Palm Waterways through weir structures at B-1, B-2, and B-3 • Dewater the area adjacent to L-4 Weir with sheet piles • Determine the nature and extent of the problem • Decide on a course of action and repair the unforeseen condition • Repair the unforeseen condition • Restore the flow ways of the Belleaire/Royal Palms Waterways • Rebuild the weir structures at B-1, B-2 and B-3

  3. Divert the Royal Palms and Belleaire Waterways through the weir structures at B-1, B-2 and B-3.

  4. Determining the extent of the unforeseen conditions

  5. Three dimensional modeling indicated that the void had a volume of approximately 110 cubic yards

  6. Filling the void with 110 cubic yards of flowable fill through 19 - 6 inch holes that were drilled in the weir deck