1 / 20

Port of Redwood City, CA Marine Terminal Plan

TEC, INC Project Management Cargo Review & Port Overview (Ph. 1) Port/Terminal Operations, Requirements Analysis, Planning Alternatives Layouts, Evaluation and Selection CASH & ASSOCIATES Wharf Design, Construction and Structural Issues Cost Analysis TREADWELL & ROLLO

dasan
Télécharger la présentation

Port of Redwood City, CA Marine Terminal Plan

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. TEC, INC • Project Management • Cargo Review & Port Overview (Ph. 1) • Port/Terminal Operations, Requirements Analysis, Planning • Alternatives Layouts, Evaluation and Selection • CASH & ASSOCIATES • Wharf Design, Construction and Structural Issues • Cost Analysis • TREADWELL & ROLLO • Geotechnical Design & Construction Issues • MARSTEL DAY • Environmental and Permitting Review Port of Redwood City, CA Marine Terminal Plan

  2. Phase 1 Summary • Fundamental need for improving Wharves stems from poor current physical condition • Wharves 1 and 2 are critical to the Port revenue stream and must be maintained • BCDC lists Redwood City as a critical element in the BCDC Plan for bulk cargoes • Primary cargoes at Wharves 1 and 2 is now and is forecasted to be dry bulk • Wharves 1 and 2 should be developed as a dry bulk materials handling berth

  3. Terminal Requirements • Operational flexibility • Marine Requirements • Reduce berth conflicts; shift operations away from cement berth • Now: Offload Belted, self-discharging vessels • Future: Offload Geared and/or Gearless bulk vessels • Port’s deeper draft plans critical to increased throughput • Uplands Requirements • Provide Adequate storage for current and projected dry bulk cargoes • Optimize HS&G/CEMEX storage yard

  4. Wharf Redevelopment Plans • Relocate belted vessel receiving hopper further from cement berth • Four wharf layout alternatives • Two structural design alternatives • Existing timber structures removed only where necessary. Remaining structures removed later as Bay fill mitigation credit.

  5. Wharf Alternative 1 • Operational needs satisfied with Alternative 1 • Unload belted vessels to receiving hopper (shown) • Place portable equipment (swing crane, hoppers & conveyors) on the platform and unload open hopper barges and gearless ocean barges • Use portable equipment connected to the receiving hopper to unload geared vessels (barge or ship) • Optional platform at north end of Wharf 1 for servicing cement vessels

  6. Wharf Alternative 2 • Operational needs satisfied with Alternative 2 • All operations capable with Alt. 1 are possible with Alt. 2 • Added capabilities include: • Increased cargo handling flexibility • Unload geared vessels using ships’ gear to hoppers and trucks (shown) • May install a crane in the future to unload gearless bulk carriers • May install a conveyor on the landward side of the wharf and unload vessels to conveyors (reduced operating cost when compared to trucks) • Optional / Future Platform at Wharf 2 adds flexibility

  7. Wharf Alternative 3 • Operational needs satisfied with Alternative 3 • All operations capable with Alts. 1 & 2 are possible with Alt. 3 • No appreciable added capabilities considering current and forecasted operations • Longer wharf may prove beneficial and allow simultaneous (un)loading of two small vessels

  8. Wharf Alternatives 4 • Operational needs satisfied with Alternative 4 • Similar to Alternative 3 • No appreciable added capabilities considering current and forecasted operations • Additional platform behind Wharf 2 beneficial, but Alternative 2 with the platform is preferred

  9. Wharf Alternative 5

  10. Site Development Plans • Relocate tenants, raze Warehouse #1 and move HS&G/CEMEX closer to waterfront • Relocate tenants, move HS&G office and shop to Warehouse #2 • Provide the Port with a new 1.1 Acre parcel next to Seaport Blvd • Optimize HS&G/CEMEX storage yard • Three equipment/yard layout alternatives • Hanson Silos to remain

  11. Site Development Plan - Layout 1

  12. Site Development Plan - Layout 2

  13. Site Development Plan - Layout 3

  14. Structural and Geotechnical Review • Design Options: • Pile supported concrete vs. sheet pile bulkhead wall with solid fill • 500 psf vs. 1000 psf deck load • Key Technical Issues: • Subsurface conditions – Bay Mud • Slope Stability • Settlement and rate of consolidation • Wharf design and stockpile areas concern • Seismic Hazards

  15. Structural and Geotechnical Review Pile-Supported Wharf Bulkhead Wall with Fill Combination: Pile-Supported Wharf and Bulkhead Wall

  16. Structural and Geotechnical Review • Conclusions: • Sheet pile bulkhead wall with solid fill not practical for this location • Excessive total and differential settlement primary issue • Settlement mitigation techniques not feasible or practical • Pile Supported Concrete Wharf, 500 psf design live deck load recommended • Stockpile loading in areas not pre-consolidated are susceptible to mud waves and possible slope failure at waterfront • Detailed Geotechnical investigation recommended for stockpile areas and waterfront.

  17. Cost Estimates CONCEPTUAL LEVEL COST ESTIMATES (20% contingency) • Wharf Alternative 1 (recommended) is: $8,252,000 (+/-) • Landside infrastructure improvements are: $700,000 (+/-)

  18. Environmental & Permitting Review • Many potential issues are similar or identical for the various alternatives • Key discriminating feature is amount of Bay fill • Selected wharf alternative represents lower level of potential environmental impacts • The Port should expect a more streamlined environmental review and permitting process • Bulkhead wall with solid fill likely not considered the least environmentally damaging alternative

  19. Conclusion: Recommended Marine Terminal Plan • Recommended wharf layout alternative: • Alternative 1: 60’ wide x 300’ pile supported wharf with one approach (cost consideration) • Alternative 2: 60’ wide x 485’ pile supported wharf with two approaches (operational advantages) • Recommended site layout alternative: • Site Layout 2 • Recommended structural design: • Pile supported concrete platform, concrete piles, 500 psf design deck load

  20. Port of Redwood City, CA Marine Terminal Plan

More Related