1 / 15

Lafayette New Terminal Program Update - January 9, 2019

This update provides information on the progress of the Lafayette New Terminal Program, including updates on received cooperative agreement, construction award concurrence, bid process confirmation, capital outlay application, EDA grant application, TSA OTA application, and discussions with airlines, rental car companies, and concessions.

dempseyl
Télécharger la présentation

Lafayette New Terminal Program Update - January 9, 2019

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Lafayette New Terminal Program Update January 9, 2019

  2. Terminal Program Update

  3. LA FP&C • Received Cooperative Agreement for FP&C contribution to QTA • Provided documentation for construction award concurrence • Coordinating with FP&C to confirm bid process and eligible items for terminal contribution • 2019 Capital Outlay Application submitted • Applying for $7 million towards terminal construction to be available next Fall EDA Grant Application • Revised EDA grant application submitted. Awaiting date for Decision Committee TSA OTA Application • Submitted Grant Application, Waiting on Feedback Terminal Program Update

  4. Airlines • Working with Airlines to discuss leasable space and an agreement to buildout space in New Terminal QTA \ Ready Return • Continued to meet with Rental Car Companies, moving forward on QTA Lease Rates • Bids received • Working with FP&C on approvals for NTP Concessions Terminal Program Update

  5. Enabling Demo • Demolition - Complete • AOA fencing and gates – Complete • Fill Material and Asphalt – Complete • Seeding/Sod – Complete • Substantially Complete Terminal Program Update

  6. Enabling Demo – drone photo Terminal Program Update

  7. Terminal Program Update Sod and seed at 310 Shepard Sod and seed at John Glenn

  8. Terminal Program Update Sod and seed at demolished vaults area Sod and seed at demolished tower area

  9. QTA Timeline: • Oct. 2018: Commission Approved Updated CFC • Nov. 2018: Construction Bids Due • Dec. 2018: Approved Bids • Jan. 2019: FP&C Construction Concurrence • Feb. 2019: Award Contract and NTP • Oct. 2019: Construction Complete Terminal Program Update

  10. GMP 1: • GMP 1 approved 9/25 • Notice to Proceed 11/12 • Schedule Starts: • Nov. 2018: RTR Relocation and Enabling Parking • Parking Impacts • Nov. 2018: RTR Facility Construction • Jan. 2019: Terminal Foundation Construction GMP 2: • Structural Steel Construction/Elevations and Escalators • GMP 2 Approval – Jan Commission GMP 3 • 100% Design is on Schedule in February • April 2019 Approval Terminal Program Update

  11. New Terminal Construction Update Project 1 – RTR Cable Relocation • IRMC was approved by FAA and preconstruction meeting completed • Additional cable procured and ASI drawings in progress GMP1 – Project 1

  12. New Terminal Construction Update Project 2 – RTR Facility • Electrical service to the building trenched and concrete poured. • Building pad structural fill hauled in, wet weather delayed compaction testing. GMP 1 – Project 2 RTR Facility

  13. New Terminal Construction Update Project 5 – Enabling Parking • Installation of storm drainage pipe and boxes. • Site stripping and electrical rough-in GMP 1 – Project 5 Enabling Parking

More Related