SlideServe
Menu
Préférences
© SlideServe · v2026

1 st global run in LS1: Global Run In November (GRIN)

didier avatar
5 diapositives · 323 Views · Aug 02, 2014

1 st global run in LS1: Global Run In November (GRIN). https:// twiki.cern.ch/twiki/bin/view/CMS/GlobalRunInNovember2013. 4 – 8 November Technical run to verify we can still run after 9 months Some of the goals… Offline: test new Tier-0 hardware & exercise data flow

1 st global run in LS1: Global Run In November (GRIN) - slide 1
01 / 51 st global run in LS1: Global Run In November (GRIN)
1 / 17

Télécharger la présentation

1 st global run in LS1: Global Run In November (GRIN)
Une image / un lien ci-dessous est fourni (tel quel) pour télécharger la présentation

Politique de téléchargement : le contenu du site vous est fourni TEL QUEL pour votre information et votre usage personnel ; il ne peut être vendu, concédé sous licence ni partagé sur d’autres sites sans l’accord de son auteur.Le contenu vous est fourni TEL QUEL, pour votre information et votre usage personnel uniquement. Téléchargez la présentation en cliquant sur ce lien. Lors du téléchargement, si vous ne parvenez pas à télécharger une présentation, l’éditeur a peut-être supprimé le fichier de son serveur.Pendant le téléchargement, si vous ne parvenez pas à obtenir une présentation, le fichier a peut-être été supprimé par l’éditeur.

F I N

Plus de contenu associé

Transcription de la présentation
  1. 1st global run in LS1: Global Run In November (GRIN) https://twiki.cern.ch/twiki/bin/view/CMS/GlobalRunInNovember2013 • 4 – 8 November • Technical run to verify we can still run after 9 months • Some of the goals… • Offline: test new Tier-0 hardware & exercise data flow • HCAL: look at new hardware w/cosmics Monday • CSC: run with ME+2 and ME+3  Wednesday • L1: increase trigger latency +12bx  Thursday • DT: test new sector collector Friday G. Rakness (UCLA)

  2. Status at noon today… http://cmsonline.cern.ch/daqStatusSCX/aDAQmon/DAQstatusGre.jpg This is especially impressive, given that there was a power cut on Saturday…  We can still run and send data to Tier-0… G. Rakness (UCLA)

  3. ME4/2 commissioning Spent a couple hours with Misha, Evaldas, Karoly, and Eric to discuss what they are seeing • CSC team is running STEP tests on ME+4/2 back chambers • Most of them are functioning OK • Main issue they were asking me about… • Timing of Data AVailable bit (bits that tell DMB that TMB, ALCT, and/or CFEB are sending data) • Recall: delay values depend ~only on the cable length (is fixed value for TMB since DMB is just next to it) G. Rakness (UCLA)

  4. DAV problems • Problems… • The ALCT and CFEB values changed for the ME+4/2 chambers that were already working in Run 1 • The TMB data is not being seen by DMB at all • Suggestion: for the moment, change ALCT and CFEB values as needed, and ask OSU about the TMB DAV • Will allow them to press on to run most STEP tests on most chambers, and to think a bit about the CFEB+ALCT DAVs… • Will return again to TMB DAV tomorrow… hopefully Stan and Ben have some ideas in the meantime… G. Rakness (UCLA)

  5. To do • 12 – 14 Nov: Trigger EDR • 15 Nov: HCAL review • Run Coordination hoo-hah • Finish job description (almost there!) • Inquire about subsystem DCS status • Settle on shifts for 2014 • Control room: talk to CMS Safety (details), sysadmins(infrastructure), Austin (schedule), Frans (underground control room) • Follow up question on lumi section length • How to improve 2015 operations? • Pick up neutron note • Read it again… what all is left to be done? • Chad’s analysis documented here: http://cern.ch/rakness/internal/log/1111/log.html G. Rakness (UCLA)