1 / 61

Working Capital Mgt.

Working Capital Mgt. Important to source funds for an enterprise Equally important to manage investment in working capital Supports/necessitated by operation of fixed assets Elements of Working Capital: Stock; Debtors; Bank/Cash; Creditors. Working Capital Mgt. - Stock.

dolores
Télécharger la présentation

Working Capital Mgt.

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Working Capital Mgt. • Important to source funds for an enterprise • Equally important to manage investment in working capital • Supports/necessitated by operation of fixed assets • Elements of Working Capital: Stock; Debtors; Bank/Cash; Creditors

  2. Working Capital Mgt. - Stock • Primary requirement: stock levels should be optimal, ie. Not too large or too small • Stock levels too high: • excess capital tied up • costs of storage • risk of deterioration • obsolescence

  3. Working Capital Mgt. - stock • Stocks too low: • disruptions risk to activities, eg. Production • frequent ordering and related costs • economies of bulk buying lost • Elements of a stock control system: • Physical Security of stock assured • Diversified control of stock ordering / issue • Documentation of stock movements / issues

  4. Working Capital Mgt. - Stock • Economic Model allowing efficient stock control • Economic Order Quantity (EOQ Model): • Assumes that order costs are known; that delivery times and consumption rates known with certainty • EOQ = (2BN/C)

  5. Working Capital Mgt. - Stock • 2 aspects: • Holding Costs - costs of holding stock • Ordering Costs - costs of ordering stock • Average stock is average of high/low levels of stock over a period (Q/2) • Cost of holding stock (C ) • Annual Holding Cost is CQ/2

  6. Working Capital Mgt. - Stock • No. of units used p.a. is N • Thus, no. of orders placed is N/Q • Costs of ordering is thus associated with no. of orders placed (B) • Total Ordering Costs thus BN/Q • Total cost of stockholding is thus: • (CQ/2) + (BN/Q)

  7. Working Cap. Mgt. - Stock • Ie. Costs of ordering plus holding costs • So, as one cost rises, the other falls • Therefore derive the Economic Order Quantity or EOQ: • EOQ = (2BN/C) • Alternatives to EOQ Model: JIT/MRP

  8. Working Capital Mgt. - Debtors • Debtors: customers to whom goods have been sold on credit • This is effectively an ‘interest free loan’ to customers for goods received and unpaid • This activity has a cost, ie. The value of goods sold plus an implied ‘interest cost’

  9. Working Capital Mgt. - Debtors • Factors to consider: • offer cash discount to encourage early payment • official period of credit offered • assessing credit worthiness of customers • action taken regarding late payments • Effective ‘Credit Control’ required

  10. Working Capital Mgt. - Debtors • Other option is that of ‘Factoring’: the sales are ‘bought’ by an agency, who in turn pursues payment, with client receiving up to say 95% of original invoice • May benefit some enterprises, ie. Less hassle pursuing payments/no defaults. • Need to consider level of capital tied up in credit sales/debtors & risk of bad debts

  11. Working Capital Mgt. - Cash • Advanced planning of cash requirements is important • cash budget a useful device to determine future requirements • derived by ref. to: timing of cash flows • monitor cash inflows and cash outflows • avoid overdrafts/shortages • maximise returns on cash surpluses

  12. Sources of Finance • 2 main sources of finance: • Equity: shareholders funds/retained earnings • Debt: loans/debentures • Each source of finance has an associated cost • Referred to as ‘Cost of Capital’

  13. Sources of Finance • Cost of Capital is implied interest cost of each source • Cost of Equity: cost of returns to shareholders, likely to be the dividends paid (Ke) • Cost of Debt: cost of interest payable on loan (Kd); (must consider after-tax cost of debt within a UK context)

  14. Cost of Capital • Combination of 2 elements of Cost of Capital results in Weighted Average Cost of Capital for an enterprise (WACC) • WACC = ((Ke+Kd)/2) • 2 approaches: • WACC calculated using interest rate/rate of return • WACC calculated using implied interest rates/rates of return & market values of sources

  15. Cost of Capital • Cost of Equity: • 2 approaches: • Dividend Growth Model (Gordon Growth Model): • Return = (d/m) + g • where, d is dividend; m is market value; g is growth rate

  16. Cost of Capital • Capital Asset Pricing Model (CAPM): • Return = Rf + ßj(Rm - Rf) • where, Rf is risk free rate of investment; ßj is Beta factor of investment; Rm is expected return on market. • Each model has a number of implicit assumptions & each calculates return from different perspective

  17. Sources of Finance • Financial Markets • Stock Exchange • Listing (Regulations, Yellow Book) • Placing; Offer for sale; Tender • Process of flotation; finance house; underwriting issues • Consider other sources, eg. Debentures • Consider impact on Gearing Levels

  18. Investment Appraisal • Most enterprises undertake capital investment projects • Characteristics of Capital Investments: • long time scales • large sums of money • uncertainty with respect to future cash flows, returns, inflation/tax rates

  19. Investment Appraisal • Standardise appraisals: alternative appraisal methods: • Payback • Present Values/Net Present Value (NPV) • Internal Rate of Return (IRR) • All above use CASHFLOWS in their evaluation • Accounting Rate of Return (ARR) • This method uses profits in evaluation

  20. Investment Appraisal • Payback: indicates the length of time taken to recover the initial investment • Net Present Value: indicates the NPV of a project which would maximise the risk adjusted cashflows of an enterprise and in turn maximises it’s wealth • IRR: indicates that NPV forcing the project to recover initial risk adjusted cash flows

  21. Investment Appraisal • ARR: the return expected on a project for a given level investment (based on profits/profitability of project); similar to R.O.C.E. ratio. • Consider also the acceptance criteria or targets set for the project • Consider qualitative aspects of projects

  22. Investment Appraisal • Payback: commitment of funds to a project involves forgoing the use of funds in alternatives; also, risk that the money invested is permanently lost. • Longer funds are tied up in a project the greater the risk of non-recovery • based on concern to recover initial outlay a.s.a.p.

  23. Investment Appraisal • Payback - Advantages: • simple to understand/apply • promotes cautious investment policy • empirically validated • Disadvantages: • disregards total contributions and thus cashflows after cut-off date, which could be larger more advantageous compared to payback period cashflows

  24. Investment Appraisal • Accounting Rate of Return (ARR): recognises the profitability of a project is important and relates it to amount of capital invested. • Method uses profits - thus can be taken as a return measure similar to R.O.C.E.

  25. Investment Appraisal • Various Methods: • Total profit/total capital invested x 100% • Average annual profit/average annual investment x 100% • Factors to consider: • determination of profits • profits not same as cashflows • disposals and related profit/loss on disposal

  26. Investment Appraisal • Net Present Value (NPV): works on the assumption of discounting, ie. That £1 now is more valuable than at any stage in the future under given set of economic conditions, eg. Inflation rates, purchasing power, interest rates • Uses discounting techniques to restate future values in present day values • Employs discount factors, 10%, 20% etc.

  27. Investment Appraisal • Discount factor represents value of £1 restated to todays values under given rates of inflation/interest etc. • eg. At 10% DF, £1 in one year’s time is 90.91p; two year’s time is 82.64p etc. • Double check by reference to discount table • Under NPV all future cash flows must be discounted over projects lifetime

  28. Investment Appraisal • All cashflows discounted and netted to yield a ‘NPV’ at end of project lifespan, which is either positive or negative. • Decision Rule: ACCEPT THAT PROJECT WHICH YIELDS THE HIGHEST NPV. • BY DOING SO, THE WEALTH OF THE ENTERPRISE IS MAXIMISED

  29. Investment Appraisal • Other influences on NPV: • Taxation: • Time Delay assumed - one year • possible grants on initial investment • tax payments extend project lifespan by 1 year • capital allowances on initial investment • Be careful not to tax any allowances received

  30. Investment Appraisal • Other issues: • Discount Factor represents the Cost of Capital or vice versa, which in turn would represent the return expected by providers of capital • Inflationary pressures - Fisher Formula - easier to adjust the discount rate/factor employed rather than individual cashflows • If cashflows each year are same, cumulative discount tables can be used

  31. Investment Appraisal • Internal Rate of Return (IRR): this is that discount rate which forces the NPV of a project to be zero • Found by interpolation (remember!!): • DR1 + ((NPV1/(NPV1+NPV2)) x (DR2-DR1)) • or • DR2 - ((NPV2/(NPV1+NPV2)) X (DR2-DR2))

  32. Investment Appraisal • Where the IRR of a project exceeds the cost of capital the implication is that the investment will be profitable and should proceed • In general, the case information should be considered, and any targets/criteria observed in forming decisions about project evaluation/acceptance

  33. Investment Appraisal - Summary • Payback: computes length of time required for project to recoup initial outlay • Shorter the payback, the more favourable the project. Deadline usually set. • Decision rule is that a project with a shorter payback period will be accepted

  34. Investment Appraisal - Summary • ARR: determines overall profitability of project by subtracting initial cost from expected returns • Expressed as either absolute amount or as annual percentage • Returns compared with cost of capital

  35. Investment Appraisal - Summary • NPV: theoretically sound appraisal based on discounting principle • future monies are less valuable than present values • future returns are discounted by a factor related to the rate of interest considered appropriate • Project yielding highest NPV is accepted

  36. Investment Appraisal -Summary • IRR: determines rate of discount required to equate the PV of project to initial investment • If it is not less than cost of capital, project is generally accepted • Profitability Index: PV(Benefits)/PV(Outlay) • generally greater than 1.0 • (PV(B) equals initial outlay + NPV)

  37. Management Accounting • 3 objectives: • 1 to allocate costs between cost of goods sold and stocks for internal/external profit reporting; • 2 to provide relevant info. To assist with decision making; • 3 to provide info. For planning, operational control and performance measurement

  38. Management accounting • Encompasses: • Budgeting/planning - cash budget & master budget • Costing - costing of products/services; costing/pricing strategies; costing of activities; profit calculations. • Control - monitoring/analysis of current information compared to planned; variances.

  39. Stock Valuation Methods • Principle: Stock valuation required in order to determine stock values for inclusion in accounts - both financial and management • Valuation Methods: Choice: • LIFO: LAST IN FIRST OUT • FIFO: FIRST IN FIRST OUT • AVCO: AVERAGE COST

  40. Product/Service Costing • Costs allocated to products/services • Direct costs traced easily • Indirect costs not traced easily • Various allocation bases used from simplistic(units based) to complicated (ABC systems - 2 stage procedures) • Elements: Material/Labour/Overheads

  41. Product/Service Costs • Cost structure: Hotel Room £ • Material (linen etc) 20.00 • Labour (cleaning, porters etc.) 10.00 • Overhead (light/heat etc) 10.00 • Margin 10.00 • Sales Price/Rate 50.00

  42. Process Costing • P.C. system is an average cost system for stock valuation/profit measurement • Appropriate where units all identical or process followed in production eg. Oil refining etc. • Cost per unit is simply total costs of process divided by no. of units output at end of process

  43. Process Costing • Dr Process Account -oil Cr • ltrs £ ltrs £ • Mat’l 10 100 Proc. 2/F.G. 10 1000 • Prod’n 10 900 • Total 10 1000 10 1000 • So, 10 ltrs of oil cost £1000, 1 Ltr = £100.

  44. Process Costing • Must take account of: • Normal losses: inherent in process, borne by good production • Abnormal losses: avoidable, not reported as part of production but w/off in P&L A/c. • Work In Progress/Partly Finished Goods: translate to Equivalent units and include in process accounts.

  45. Breakeven (CVP) Analysis • Breakeven point is that point at which neither a profit nor a loss is made • Information required: • Revenue; Costs; Quantity; Relevant Range; Linear Relationship between costs/revenue; Contribution; Fixed Cost; Variable Cost; Profit • Assumes linear relationship cost/revenues

  46. Breakeven (CVP) analysis • Assumptions: • all variables remain constant • analysis based on single product/constant sales mix • profits calculated on variable costing basis • costs accurately divided between fixed and variable elements • short term horizon/relevant range

  47. Breakeven (CVP) Analysis • Multi-product environment: • Calculate c/s ratio for each product • rank according to highest c/s ratio • plot profit/sales revenue on a cumulative basis, starting with product yielding highest c/s ratio first, progressing to lowest • by cumulating in this order, total will equal total contribution and total sales revenues

  48. Budgeting - Networking • Network Analysis: idea is to identify the critical path

  49. Budgeting - Cost Reduction • Cost Reduction: • Value Analysis:

  50. Budgeting - Learning Curve • Learning Curve: Constant rate of learning will lead to a doubling of output/reduction of costs

More Related