80 likes | 190 Vues
This update provides key outcomes from the SPP Stakeholder Meeting held on December 1, 2008, in Austin, TX. Participants confirmed implementation assumptions and cost estimates with ERCOT regarding the Retail Open Access (ROA) project. The results detail ROA implementation and annual maintenance cost estimates, including ERCOT Phase II costs and internal development work. For further inquiries, please contact Beth Miller at Accenture (484) 716-1706 or via email.
E N D
Status Update: Retail Open Access for ETI within SPP Stakeholder Meeting December 1, 2008 Austin, TX
Activities Completed Since Last Meeting • Confirmed assumptions with ERCOT on Implementation activities • Confirmed cost estimates with ERCOT
ROA Implementation Cost Estimates * Includes ERCOT Phase II costs Appendix 9 and estimated one time internal ERCOT development work.
Annual ROA Maintenance Cost Estimates * Staffing rates are based on the 2009 CBTF rates