1 / 19

Recruitment of the New LTPP SPS-10: Warm Mix Asphalt Experiment

Recruitment of the New LTPP SPS-10: Warm Mix Asphalt Experiment. Gabe Cimini LTPP NARSC Project Manager. Presentation Outline. LTPP Approach to WMA Research Site Requirements Roles and Responsibilities SPS-10 Nomination Process. Why WMA?. 356 million tons of WMA produced in 2012

duke
Télécharger la présentation

Recruitment of the New LTPP SPS-10: Warm Mix Asphalt Experiment

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Recruitment of the New LTPP SPS-10:Warm Mix Asphalt Experiment • Gabe Cimini • LTPP NARSC Project Manager

  2. Presentation Outline • LTPP Approach to WMA Research • Site Requirements • Roles and Responsibilities • SPS-10 Nomination Process

  3. Why WMA? • 356 million tons of WMA produced in 2012 • 24% of all plant mix produced in US was WMA • 35 different WMA technologies • WMA is a priority innovation under FHWA’s Every Day Counts (EDC) Initiative

  4. Objectives • Long-term performance of WMA relative to HMA • Capture data on WMA with RAP

  5. Benefits to Agencies • Detailed construction information including a construction report • Rigorous materials testing (over multiple intervals) using latest testing technology • Ongoing FWD, distress, profile, and texture monitoring to study short and long term performance • Ability to study Agency-specific issues related to WMA

  6. SPS-10 Requirements • Overview • AC overlay of existing AC pavements • 2” to 4” overlay thickness • Dense graded mix • RAP content 10-25% (binder replacement) • 1 HMA control test section • 2 WMA test sections • Foaming Process • Chemical Additive • Tack Coats between lifts

  7. Site Layout Requirements • WMA: • Production of ≤ 275°F or • Production at least 30°F less than HMA

  8. Existing Pavement Requirements • Uniformity • Subgrade type/condition • Base thickness/type • Bound layer thickness/type • Surface condition • Traffic loading • Pre-overlay repairs based on Highway Agency’s standard practice

  9. Experiment Layer Requirements • Mix design/binder grade selection based on Agency’s standard practice • Overlay thickness selected by Agency’s standard practice • Uniformity between HMA and WMA • Same binder source/grade • Same aggregate source/gradations • Mix design/JMF

  10. Supplemental Sections • Agencies can build additional test sections that will be monitored as part of the LTPP program • Varying levels of RAP • Additional WMA technologies • Layer thickness variation • Open or gap graded mixtures • Varying aggregate sources/absorption levels • Other variables of interest to Agency

  11. Roles/Responsibilities • Agencies • Nominate project(s) • Validate in-situ conditions • Submit inventory data • Develop plans, specifications, mix design • Provide construction and inspection/control/management • Perform materials sampling/patching • Collect traffic data • Provide traffic control

  12. Sampling Areas (Draft)Coring at 0, 6, 12 and 18 months after construction

  13. Traffic Data Collection Guidelines • Quality traffic data is critical in assessing the vehicle loading on pavements • Permanently mounted sensors whenever possible • As long as a documented calibration plan is followed, data from both portable and permanent equipment will be accepted (required LTPP Traffic Sheet 16 – Site calibration summary) • The agency should plan to repair faulty equipment within 1 month • At a minimum, 2 weeks of continuous classification data 4 times per year (a total of 8 weeks of classification data) • Data to be submitted by the agency on a monthly basis, however, the data will be accepted if submitted quarterly as well • If a WMA test site does not have weight data, then the agency must submit an LTPP Traffic Sheet 10 (Traffic volume and load estimate). Submitting 1 Sheet 10 per year is sufficient

  14. Roles/Responsibilities • FHWA • Develop experimental design/research plan • Coordinate among Agencies • Oversee construction data collection • Perform materials testing • Provide materials sampling support • Collect performance monitoring data • Store, analyze, and report data

  15. Nomination Process • FHWA accepting nominations now • Projects to be constructed in 2014 and 2015 • Nomination forms are available from FHWA and the LTPP Regional Support Contractors (RSCs) • FHWA will evaluate nominations and notify Agencies • Coordination through LTPP RSCs

  16. Additional Tests on Materials • Material Testing somewhat limited • Additional information beneficial on national level • Agencies encouraged to perform additional tests • Recommended by the FHWA Asphalt Mixture Expert Task Group, based upon NCHRP Research Results Digest 370:

  17. Additional Tests on Materials

  18. Contact Information

More Related