In this 5th update for Milwaukee’s Best Brew Stand, we share exciting news about the progress of our brewing project. We have successfully ordered and received essential kettle parts, including valves and thermometers. Our team is also working on a donation frame while making strides in additional ongoing tasks. Upcoming steps include gas piping, pump installation and wiring, central power setup, and fabricating components like wheel castors and a propane tank holder. Stay tuned as we continue moving forward with our brewing aspirations!
E N D
Milwaukee’s Best Brew Stand 5th Update Ben Caya Carl Czajka
Parts Ordered and Received Kettle – Ordered Valves – In Thermometers - In • Ordered and Received
Parts Working on donation Free and Received Ordered
To-Do • Gas piping • Bolt on Pumps (bracket already welded in) • Pump wiring • Central power • Wire switch • Weld on castors • Weld on propane tank holder • Brew Beer